Rule 672-5-.12 - Effect of Subcontracting on Contractor's Capacity
Universal Citation: GA Rules and Regs r 672-5-.12
Current through Rules and Regulations filed through December 18, 2024
(1) The prime Contractor may subcontract portions of the project to other prequalified Contractors or registered Subcontractors up to the amount provided for in the contract specifications. In figuring the total amount of Current Capacity available to a Contractor, it will be given credit for the work subcontracted after the Subcontractor has been approved in writing by the Department.
(2) No Person shall both prequalify as a Contractor and register as a Subcontractor. Any subcontract work undertaken by a prequalified Contractor shall be counted against its Current Capacity.
O.C.G.A. §§ 32-2-2, 50-13-4.
Disclaimer: These regulations may not be the most recent version. Georgia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.