Compilation of Rules and Regulations of the State of Georgia
Department 391 - RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES
Chapter 391-3 - ENVIRONMENTAL PROTECTION
Subject 391-3-4 - SOLID WASTE MANAGEMENT
Rule 391-3-4-.03 - Public Participation
Current through Rules and Regulations filed through September 23, 2024
(1) Any city, county, group of counties, or authority beginning a process to select a site for a municipal solid waste disposal facility shall first call a public meeting as described herein.
(2) The governing authority of any county or municipality taking action resulting in a municipal solid waste disposal facility siting decision shall notify the public as follows:
(3) Upon submission of an application to the Division for any municipal solid waste disposal facility for which a permit (other than a permit-by-Rule) is required, the applicant, within fifteen (15) days of the submission of said application, shall take the following actions:
(4) The governing authority of the county or municipality will hold a public hearing not less than two weeks prior to the issuance of any permit, except for a private industry disposal facility, and notice of such hearing shall be posted at the proposed site in a location closest to the primary existing entrance or primary proposed entrance where it can be viewed unaided from a public right-of-way and advertised in a newspaper of general circulation serving the county or counties in which the proposed activity will be conducted, at least thirty (30) days prior to such hearing. A typed copy of the hearing transcript shall be submitted to the Division.
(5) Whenever the Director issues, denies, revokes, suspends, or transfers, a permit or approves a major modification of a permit for a facility, he shall notify the chief elected official of the host local government in which the facility is located or is proposed to be located.
O.C.G.A. § 12-8-20 et seq., as amended.