Compilation of Rules and Regulations of the State of Georgia
Department 121 - STATE CONSTRUCTION INDUSTRY LICENSING BOARD
Chapter 121-6 - BUSINESS REGISTRATION
Rule 121-6-.05 - Grace Period for Utility Contractors

Universal Citation: GA Rules and Regs r 121-6-.05

Current through Rules and Regulations filed through September 23, 2024

(1) In the event that a licensed utility contractor temporarily does not have employed a utility manager certificate holder to oversee the work performed by the contractor, including any branch offices, the contractor must notify the Division of Utility Contractors within 5 days following the last day of employment of the certificate holder. Except as provided in paragraph (4), upon such notice, the division shall grant the utility contractor a 90 day grace period in which to employ a utility manager certificate holder before any action may be taken to revoke the utility contractor's license. If the utility contractor fails to notify the division within 5 days or allows the grace period to expire without employing a utility manager certificate holder to oversee the work, the utility contractor no longer has the right to engage in the business of utility contracting, and failure to employ a certificate holder shall be grounds for revocation or suspension of the utility contractors license.

(2) Utility contractors who are granted a grace period to employ a utility manager certificate holder must report within five (5) days the employment of a certificate holder.

(3) In the event that a licensed utility contractor can show good cause for being unable to employ a utility manager certificate holder within the 90-day grace period, the contractor may apply for one additional 90-day grace period. Such applicant must be submitted to the division at least 15 days prior to the expiration of the original grace period. One additional 90-day grace period may be approved if the contractor can show good cause which is acceptable to the division. Such application must show the contractor's efforts to employ a certificate holder, the reason for the contractor's inability to employ a certificate holder, and the contractor's plan for employing a certificate holder within the next 90 days. Good cause for not having hired a certificate holder may include but is not limited to medical emergencies, natural emergencies, or employee who has a certificate application on file pending approval by the division. To be approved, the division must determine that the failure to hire a certificate holder was beyond the contractor's ability and that the contractor can be expected to hire a certificate holder within the next 90 days.

(4) A utility contractor may not be granted grace periods totaling more than 180 days during any two-year period. The number of days applied to this limit will be determined by the number of days granted and should not be reduced if the contractor employs a certificate holder prior to the expiration of the grace period.

O.C.G.A. Secs. 43-14-5, 43-14-6, 43-14-8.

Disclaimer: These regulations may not be the most recent version. Georgia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.