Compilation of Rules and Regulations of the State of Georgia
Department 110 - RULES OF GEORGIA DEPARTMENT OF COMMUNITY AFFAIRS
Chapter 110-12 - MINIMUM STANDARDS AND PROCEDURES
Subject 110-12-7 - DEVELOPMENTS OF REGIONAL IMPACT: ALTERNATIVE REQUIREMENTS: ATLANTA REGIONAL COMMISSION
Rule 110-12-7-.05 - Determining if a Project is a DRI
Current through Rules and Regulations filed through September 23, 2024
(1) Regional Commissions mustuse the following criteria to determine if a development project is a DRI. The determination of the Regional Commission is final; however, a determination by the Regional Commission that a project is not a DRI as herein defined will not affect GRTA's authority pursuant to O.C.G.A. 50-32-14.
Developments of Regional Impact Development Thresholds |
|||||
Type of Development |
Notification Only |
Rural and Developing Rural |
Maturing Neighborhoods, Established Suburbs, Developing Suburbs, and other places not mentioned in this table |
Regional Centers, and Regional Employment Corridors |
Region Core |
(1) Office |
400,000 gross square feet |
400,000 gross square feet |
500,000 gross square feet |
600,000 gross square feet |
700,000 gross square feet |
(2) Commercial |
Greater than 300,000 gross square feet |
300,000 gross square feet |
400,000 gross square feet |
500,000 gross square feet |
600,000 gross square feet |
(3) Wholesale & Distribution |
Greater than 500,000 gross square feet |
500,000 gross square feet |
500,000 gross square feet |
500,000 gross square feet |
500,000 gross square feet |
(4) Hospitals and Health Care Facilities |
Greater than 300 new beds; or generating more than 375 peak hour vehicle trips per day |
300 new beds |
400 new beds |
500 new beds |
600 new beds |
(5) Housing |
Greater than 400 new lots or units |
400 new lots or units |
500 new lots or units |
600 new lots or units |
700 new lots or units |
(6) Industrial |
Greater than 500,000 gross square feet; or employing more than 1,600 workers; or covering more than 400 acres |
500,000 SF or 1600 workers |
500,000 SF or 1600 workers |
500,000 SF or 1600 workers |
500,000 SF or 1600 workers |
(7) Hotels |
Greater than 400 rooms |
400 rooms |
500 rooms |
600 rooms |
700 rooms |
(8) Mixed Use |
Gross square feet of 400,000 or more (with residential units calculated at either 1800 square feet per unit or, if applicable, the minimum square footage allowed by local development regulations); or covering more than 120 acres; or if any of the individual uses meets or exceeds a threshold as identified herein |
400,000 gross square feet (with residential units calculated at 1800 square feet per unit, or the minimum allowed by the host local government) |
500,000 gross square feet (with residential units calculated at 1500 square feet per unit, or the minimum allowed by the host local government) |
600,000 gross square feet (with residential units calculated at 1000 square feet per unit, or the minimum allowed by the host local government) |
700,000 gross square feet (with residential units calculated at 1000 square feet per unit, or the minimum allowed by the host local government) |
(9) Airports |
All new airports, runways and runway extensions |
New airports and runway extensions of 500 ft. or more |
New airports and runway extensions of 500 ft. or more |
New airports and runway extensions of 500 ft. or more |
New airports and runway extensions of 500 ft. or more |
(10) Attractions & Recreational Facilities |
Greater than 1,500 parking spaces or a seating capacity of more than 6,000 |
1,500, seating capacity of 6,000+ |
1,500, seating capacity of 6,000+ |
1,500, seating capacity of 6,000+ |
1,500, seating capacity of 6,000+ |
(11) Post-Secondary School |
New school with a capacity of more than 2,400 students; or expansion by at least 25 percent of capacity |
New school with 2,400 students or expansion of at least 25% |
New school with 2,400 students or expansion of at least 25% |
New school with 2,400 students or expansion of at least 25% |
New school with 2,400 students or expansion of at least 25% |
(12) Waste Handling Facilities |
New facility or expansion of use of an existing facility by 50 percent or more |
New facility within 1 mile of public facility (airport, school, reservoir, river, etc.), otherwise, notification only |
New facility within 1 mile of public facility (airport, school, reservoir, river,...), otherwise, notification only |
New facility within 1 mile of public facility (airport, school, reservoir, river,...), otherwise, notification only |
New facility within 1 mile of public facility (airport, school, reservoir, river,...), otherwise, notification only |
(13) Quarries, Asphalt & Cement Plants |
New facility or expansion of existing facility by more than 50 percent |
New facility within 1 mile of public facility (airport, school, reservoir, river,...), otherwise, notification only |
New facility within 1 mile of public facility (airport, school, reservoir, river,...), otherwise, notification only |
New facility within 1 mile of public facility (airport, school, reservoir, river,...), otherwise, notification only |
New facility within 1 mile of public facility (airport, school, reservoir, river,...), otherwise, notification only |
(14) Wastewater Treatment Facilities |
New major conventional treatment facility or expansion of existing facility by more than 50 percent; or community septic treatment facilities exceeding 150,000 gallons per day or serving a development project that meets or exceeds an applicable threshold as identified herein |
Notification only (MNGWPD) |
Notification only (MNGWPD) |
Notification only (MNGWPD) |
Notification only (MNGWPD) |
(15) Petroleum Storage Facilities |
Storage greater than 50,000 barrels if within 1,000 feet of any water supply; otherwise, storage capacity greater than 200,000 barrels |
50,000 barrels if within 1,000 ft. of water supply |
50,000 barrels if within 1,000 ft. of water supply |
50,000 barrels if within 1,000 ft. of water supply |
50,000 barrels if within 1,000 ft. of water supply |
(16) Water Supply Intakes/Public Wells/Reservoirs/ Treatment Facilities |
New Facilities |
Notification only (MNGWPD) |
Notification only (MNGWPD) |
Notification only (MNGWPD) |
Notification only (MNGWPD) |
(17) Intermodal Terminals |
New Facilities |
New facilities |
New facilities |
New facilities |
New facilities |
(18) Truck Stops |
A new facility with more than three (3) diesel fuel pumps, or containing a half acre of truck parking or 10 truck parking spaces |
10 or more diesel fuel pumps or 20 or more truck parking spaces |
10 or more diesel fuel pumps or 20 or more truck parking spaces |
10 or more diesel fuel pumps or 20 or more truck parking spaces |
10 or more diesel fuel pumps or 20 or more truck parking spaces |
(19) Correctional/Detention Facilities |
Greater than 300 new beds; or generating more than 375 peak hour vehicle trips per day |
Greater than 300 new beds; or generating more than 375 peak hour vehicle trips |
Greater than 300 new beds; or generating more than 375 peak hour vehicle trips |
Greater than 300 new beds; or generating more than 375 peak hour vehicle trips |
Greater than 300 new beds; or generating more than 375 peak hour vehicle trips |
(20) Any other development types not identified above (includes parking facilities) |
1000 parking spaces or, if available, more than 5,000 daily trips generated |
1000 spaces or 5,000 daily trips |
1000 spaces or 5,000 daily trips |
1000 spaces or 5,000 daily trips |
1000 spaces or 5,000 daily trips |
* Speculative Developments. If final development type is difficult to determine because project tenants have not yet been identified, use the thresholds for the highest intensity development type allowed by current land use regulations. If there are no such local development regulations, estimate the likely type and scale of development based on the real estate market potential of the project site.
* Multi-phased Developments. Applicants shall submit all phases of the project at inception of the project, rather than submitting each phase one at a time. However, if the applicant seeks local government approvals for smaller phases individually, the determination of whether the project is in fact a multi-phased development should be based on considerations as to whether a master plan has been prepared for the overall project or whether any approvals have been sought for the entire project as a unit. If the multi-phased nature of the project cannot be established in advance, whenever a phase is submitted for approval that, when combined with all previously approved phases of the project built during the past five years, cumulatively equals or exceeds the applicable DRI threshold, the proposed new phase, plus any incomplete portions of the project must be submitted as a DRI.
* Multiple Land Parcels. If parts of the project are located on separate land parcels, the decision whether the project is a single (perhaps multi-phased) development, or actually separate projects should be based on such considerations as whether the separate parcels are owned by the same entity, whether a master plan has been prepared for the overall project, or whether any approvals have been sought for the overall project as a unit.
Examples of issues that may lead to a determination that developments which meet or exceed the tiered ARC thresholds include, but are not limited to:
50-8-7.1(b).