Compilation of Rules and Regulations of the State of Georgia
Department 110 - RULES OF GEORGIA DEPARTMENT OF COMMUNITY AFFAIRS
Chapter 110-12 - MINIMUM STANDARDS AND PROCEDURES
Subject 110-12-3 - DEVELOPMENTS OF REGIONAL IMPACT
Rule 110-12-3-.05 - Determining if a Project is a DRI
Current through Rules and Regulations filed through September 23, 2024
(1) Regional Commissions mustuse the following criteria to determine if a development project is a DRI. The determination of the Regional Commission is final; however, a determination by the Regional Commission that a project is not a DRI as herein defined will not affect GRTA's authority pursuant to O.C.G.A. 50-32-14.
Developments of Regional Impact Development Thresholds |
||
Type of Development |
Metropolitan Tier |
Non-Metropolitan Tier |
(1) Office |
Greater than 400,000 gross square feet |
Greater than 125,000 gross square feet |
(2) Commercial |
Greater than 300,000 gross square feet |
Greater than 175,000 gross square feet |
(3) Wholesale & Distribution |
Greater than 500,000 gross square feet |
Greater than 175,000 gross square feet |
(4) Hospitals and Health Care Facilities |
Greater than 300 new beds; or generating more than 375 peak hour vehicle trips per day |
Greater than 200 new beds; or generating more than 250 peak hour vehicle trips per day |
(5) Housing |
Greater than 400 new lots or units |
Greater than 125 new lots or units |
(6) Industrial |
Greater than 500,000 gross square feet; or employing more than 1,600 workers; or covering more than 400 acres |
Greater than 175,000 gross square feet; or employing more than 500 workers; or covering more than 125 acres |
(7) Hotels |
Greater than 400 rooms |
Greater than 250 rooms |
(8) Mixed Use |
Gross square feet greater than 400,000 (with residential units calculated at either 1800 square feet per unit or, if applicable, the minimum square footage allowed by local development regulations); or covering more than 120 acres; or if any of the individual uses meets or exceeds a threshold as identified herein |
Gross square feet greater than 125,000 (with residential units calculated at either 1800 square feet per unit or, if applicable, the minimum square footage allowed by local development regulations); or covering more than 40 acres; or if any of the individual uses meets or exceeds a threshold as identified herein |
(9) Airports |
All new airports, runways and runway extensions |
Any new airport with a paved runway; or runway additions of more than 25% of existing runway length |
(10) Attractions & Recreational Facilities |
Greater than 1,500 parking spaces or a seating capacity of more than 6,000 |
Greater than 1,500 parking spaces or a seating capacity of more than 6,000 |
(11) Post-Secondary School |
New school with a capacity of more than 2,400 students; or expansion by at least 25 percent of capacity |
New school with a capacity of more than 750 students; or expansion by at least 25 percent of capacity |
(12) Waste Handling Facilities |
New facility or expansion of use of an existing facility by 50 percent or more |
New facility or expansion of use of an existing facility by 50 percent or more |
(13) Quarries, Asphalt & Cement Plants |
New facility or expansion of existing facility by more than 50 percent |
New facility or expansion of existing facility by more than 50 percent |
(14) Wastewater Treatment Facilities |
New major conventional treatment facility or expansion of existing facility by more than 50 percent; or community septic treatment facilities exceeding 150,000 gallons per day or serving a development project that meets or exceeds an applicable threshold as identified herein |
New major conventional treatment facility or expansion of existing facility by more than 50 percent; or community septic treatment facilities exceeding 150,000 gallons per day or serving a development project that meets or exceeds an applicable threshold as identified herein. |
(15) Petroleum Storage Facilities |
Storage greater than 50,000 barrels if within 1,000 feet of any water supply; otherwise, storage capacity greater than 200,000 barrels |
Storage greater than 50,000 barrels if within 1,000 feet of any water supply; otherwise, storage capacity greater than 200,000 barrels |
(16) Water Supply Intakes/Public Wells/Reservoirs/ Treatment Facilities |
New Facilities |
New Facilities |
(17) Intermodal Terminals |
New Facilities |
New Facilities |
(18) Truck Stops |
A new facility with more than three (3) diesel fuel pumps, or containing a half acre of truck parking or 10 truck parking spaces |
A new facility with more than three (3) diesel fuel pumps, or containing a half acre of truck parking or 10 truck parking spaces |
(19) Correctional/Detention Facilities |
Greater than 300 new beds; or generating more than 375 peak hour vehicle trips per day |
Greater than 200 new beds; or generating more than 250 peak hour vehicle trips per day |
(20) Any other development types not identified above (includes parking facilities) |
1000 parking spaces or, if available, more than 5,000 daily trips generated |
1000 parking spaces or, if available, more than 5,000daily trips generated |
* Speculative Developments. If final development type is difficult to determine because project tenants have not yet been identified, use the thresholds for the highest intensity development type allowed by current land use regulations. If there are no such local development regulations, estimate the likely type and scale of development based on the real estate market potential of the project site.
* Multi-phased Developments. Applicants shall submit all phases of the project at inception of the project, rather than submitting each phase one at a time. However, if the applicant seeks local government approvals for smaller phases individually, the determination of whether the project is in fact a multi-phased development should be based on considerations as to whether a master plan has been prepared for the overall project or whether any approvals have been sought for the entire project as a unit. If the multi-phased nature of the project cannot be established in advance, whenever a phase is submitted for approval that, when combined with all previously approved phases of the project built during the past five years, cumulatively equals or exceeds the applicable DRI threshold, the proposed new phase, plus any incomplete portions of the project must be submitted as a DRI.
* Multiple Land Parcels. If parts of the project are located on separate land parcels, the decision whether the project is a single (perhaps multi-phased) development, or actually separate projects should be based on such considerations as whether the separate parcels are owned by the same entity, whether a master plan has been prepared for the overall project, or whether any approvals have been sought for the overall project as a unit.
O.C.G.A. 50-8-7.1(b).