(1) All operators are encouraged to take part in meetings with the appropriate agencies before doing substantial work on required notices or plans.

(2) All operators shall inform the Department before submitting a notice of intent to mine or conceptual plan for mining and reclamation. Within seven days, the Department shall notify the operator of the appropriate agency to which the notice of intent to mine or conceptual plan shall be submitted.

(3) Once the Department notifies the operator, under subsection (2), above, the operator shall submit all notices, plans, reports, and other required documents to the specified agency, unless the Department notifies the operator otherwise.

Rulemaking Authority 378.404, 378.411 FS. Law Implemented 378.411 FS.

New 7-16-87, Formerly 16C-36.005.

Disclaimer: These regulations may not be the most recent version. Florida may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.