Florida Administrative Code
62 - DEPARTMENT OF ENVIRONMENTAL PROTECTION
62C - Division of Resource Management
Chapter 62C-16 - BUREAU OF MINE RECLAMATION - MANDATORY PHOSPHATE MINE RECLAMATION
Section 62C-16.0041 - Conceptual Plans and Modifications
Current through Reg. 50, No. 187; September 24, 2024
Each conceptual plan application and conceptual plan modification application shall describe in writing and graphically, as required by the Department, the activities which are the subject of the application.
(1) Conceptual plan. A conceptual plan application shall:
(2) Conceptual plan modification. All reclamation and restoration activities shall be carried out as approved; however, when it becomes apparent or is anticipated that a modification in an approved conceptual plan is needed, the operator shall inform the Department that a modification to the conceptual plan is needed and obtain approval before proceeding with the change. The Department shall approve any complete application for a conceptual plan modification that meets the standards of Section 62C-16.0051, F.A.C. A conceptual plan modification shall:
(3) Field changes. The following activities listed in Reclamation Form No. 6 shall not constitute a change requiring a conceptual plan modification but shall be reported to the Department by the operator on Reclamation Form No. 6 for approval by the Department as a field change:
Prior Department notification shall not be required before the operator undertakes an activity listed in Reclamation Form No. 6; instead, the operator shall report such activities to the Department for approval on a quarterly basis in conjunction with the quarterly inspection. The Department shall approve any change listed in Reclamation Form No. 6 that does not alter the character of the reclamation parcel as originally approved and that meets the standards of Rule 62C-16.0051, F.A.C. If the Department does not approve the field change, then the operator must reclaim the site in accordance with the approved conceptual plan or obtain a modification to the conceptual plan.
(4) Activities not requiring Department approval. Movement of internal roadways or changes in the reclamation time table of one year or less that are the result of a change in the rate of mining within a reclamation parcel shall not require a conceptual plan modification or Department approval; instead, the operator shall notify the Department in the Annual Mining and Reclamation Report.
Rulemaking Authority 378.205 FS. Law Implemented 211.32, 378.205 FS.
New 10-6-80, Formerly 16C-16.041, Amended 2-22-87, Formerly 16C-16.0041, Amended 5-28-06.