Florida Administrative Code
62 - DEPARTMENT OF ENVIRONMENTAL PROTECTION
62B - Beaches and Coastal Systems
Chapter 62B-56 - BUREAU OF BEACHES AND COASTAL SYSTEMS - RULES AND PROCEDURES FOR USING SAND-FILLED GEOTEXTILE DUNE CORES (PERMITS FOR CONSTRUCTION AND MAINTENANCE)
Section 62B-56.160 - Revocations, Suspensions and Removal
Current through Reg. 50, No. 187; September 24, 2024
(1) Subject to the provisions of subsection (3), below, and in accordance with sections 161.085, and 120.60, F.S., the Department shall order the revocation of the permit and removal of the structure and restoration of the project site in accordance with subsection (6), below, upon its determination that one or more of the following permit conditions have been violated:
(2) Subject to the provisions of subsection (3), below, the Department shall order the suspension of the permit upon its determination that the responsible entity failed to meet any of the requirements under rule 62B-56.030, F.A.C. Upon receipt of an order of suspension, the responsible entity shall immediately cease all construction activities unless otherwise directed by the Department.
(3) The following factors shall be considered in determining whether to suspend or revoke a permit or other authorization:
(4) Responsible entities whose permits have been suspended shall have up to 60 days to submit a written plan to correct the deficiencies that resulted in the suspension. The Department shall review the deficiency plan within 60 days of receipt and advise the responsible entity of whether it is acceptable and take action as follows:
(5) Before revoking or suspending a permit, the Department shall give written notice to the responsible entity. The notice shall specify the provision of the law, or rule or permit condition alleged to be violated, and the facts alleged to constitute a violation thereof. Within 21 days of receipt of notification, the responsible entity may petition for an administrative hearing under sections 120.569 and 120.57, F.S.
(6) Following the Department's final order upholding revocation, the responsible entity shall remove the structure. All removals, mandated or voluntary, shall be conducted pursuant to the following:
(7) Permits that have been revoked shall be returned to the Department within 30 days after the official notification.
Rulemaking Authority 161.053(20), 161.085(5) FS. Law Implemented 120.60, 161.053(6), 161.085(9) FS.
New 6-22-09.