(2) In all
cases where a performance and payment bond is not provided, the following
procedures shall be followed:
(a) At any time
prior to final completion of a contract exempted from bond requirements, the
contracting authority shall not authorize or make payment to the contractor in
excess of ninety percent (90%) of the amount due on the contract on the basis
of the work suitably completed and material suitably stored on the
site.
(b) In case of default by the
contractor, the laborers, materialmen, and subcontractors, as defined in
Section 713.01, F.S., making claims for
unpaid bills, will be paid from the five percent (5%) retainage on a pro rata
basis as follows:
1. The sum of all claims
made shall be divided into each individual claim thereby deriving a percentage
value for each claim. The total retainage will then be multiplied by the
percentage value and the result shall be the pro rata share of the retainage to
be paid to the claimant; however, the payment shall not be more than the
claim.
2. The final payment of
retainage shall not be made until the project has been inspected by the
Architect/Engineer or other person designated by the contracting authority for
that purpose and until they have issued a written certificate that the project
has been constructed in accordance with the approved plans, specifications and
approved change orders and until the contracting authority has accepted the
project, and until the contractor has supplied the contracting authority with
signed and dated statements from all laborers, materialmen, and subcontractors
as defined in Section
713.01, F.S., and identified
under subparagraph 4., hereinafter, that they have no claims against the
contractor for the work under the contract. Said statements shall identify the
project by name and project number.
3. The contractor, before beginning work or
within two workdays thereafter, shall post in a conspicuous place on the
project site the following notice:
"Notice is hereby made to all those concerned and affected
that ___ (CONTRACTOR'S NAME) is performing ___ (PROJECT NAME), ___ (PROJECT
NUMBER) at ___ (LOCATION). All parties furnishing labor and/or materials to
said project are to provide notice of such in writing by certified mail to the
(AGENCY) within twenty days of first providing such labor and/or
materials."
4. The
contractor shall provide a certified list of all sub-contractors, laborers and
material suppliers to the Agency within thirty days of its receiving its notice
to proceed with the work. This list shall be updated thereafter each month with
a certified statement that the list and its updates include the names and
addresses of all of those sub-contractors, laborers, and material suppliers
furnishing labor and/or material for the project.
5. The contractor shall provide a written
statement with each pay request to the Agency which indicates how each payment
requested will be distributed. This pay request breakdown shall define the
disbursement intended for all of the funds requested.
6. When a contractor receives any payment it
shall pay such moneys received to each sub-contractor and material supplier in
accordance with Section
287.0585, F.S.
7. The contractor shall provide a written
statement with all but the first payment request from each of the
subcontractors, laborers and material suppliers indicated in subparagraph 4.,
above, that they have in fact received payment as indicated in the preceding
statements. In the event any payment is not made as indicated on a prior
statement noted in subparagraph 5., above, the contractor shall furnish an
explanation as to the reasons for such deviation and shall request approval
from the Agency.