(2)
Undertaking a Project Authorized by a Certificate of Need. A Certificate of
Need will terminate after the 18-month time frame set forth in subsection (1)
unless the applicant meets one of the minimum requirements described below:
(a) Certificates of Need for New Construction
or Renovation Projects.
1. A holder of a
Certificate of Need with a project for new construction must, by the date of
termination of the Certificate of Need, be deemed to have commenced continuous
construction as defined in Section
408.032(4),
F.S. For purposes of compliance, site preparation must be completed as defined
below:
a. Completion of site preparation
activities which include clearing of land, removal of soil, placement and
compacting of fill dirt, and grading and leveling of the site for that portion
of the site which will contain the foundation;
b. Foundation permit;
c. Completion of footprint of the
certificated portion of the building, unless the contractor is building a
hospital using the fast-track method of construction and the agreement between
the contractor and the Certificate of Need holder provides for the use of that
method; and,
d. Foundation forming
with placement of concrete and steel which will become an integral part of the
final facility to be constructed.
2. A holder of a Certificate of Need for
renovation of an existing structure must, by the date of termination of the
Certificate of Need, be deemed to have commenced construction. This is
established by completing site preparation which is defined as having a
demolition permit or building permit, having an executed owner or contractor
agreement, and demonstrating proof of the commencement of demolition.
3. The Agency staff or a designated
representative shall make an unannounced visit to each project site on the
termination date of the Certificate of Need. The visit shall result in
photographs of the site and a written report. The Certificate of Need holder
may submit information for evaluation to the staff of the Agency or the
designated representative on the day of the site visit. On or before 14
calendar days of receipt of the information, staff designated by the Agency
shall evaluate the information and make a determination of whether or not the
project has commenced construction.
a. If
deemed to have commenced construction, continuous construction must be
maintained. For purposes of monitoring compliance, "continuous construction"
refers to work performed under the authority of an architect to whom the
contractor is responsible and which advances the project towards completion in
accordance with the project timetable and standard, acceptable construction
procedures. Any return to site preparation as defined in sub-subparagraphs
59C-1.018(2)(a)
1.a.-d., F.A.C., without approval, as provided in paragraphs
59C-1.021(2)(a) and
(b), F.A.C., of the Agency is strictly
prohibited and is deemed not to be continuous construction.
b. If deemed not to have commenced
construction, the holder of the Certificate of Need shall be notified, in
writing, of the determination and the right to a hearing under Section
120.57, F.S., by the director or
his or her designee from the Agency. The Certificate of Need shall terminate by
operation of law.
(b) Certificates of Need for Non-construction
Projects.
1. A holder of a Certificate of Need
for a non-construction project including Hospice, bed conversions and
establishment of new health services, or a substantial change in such services,
must provide proof of having made an enforceable capital expenditure greater
than 10% percent of the total project cost, or have received appropriate
licensure and certification by the date of termination of the Certificate of
Need.
2. A holder of a Certificate
of Need who undertook a project authorizing the offering of a new service for
which there is neither construction nor enforceable capital expenditure must
provide utilization data to the Agency within 30 calendar days after the
termination date of the Certificate of Need. The data must demonstrate that the
service became operational on or before the termination date of the Certificate
of Need.