Current through Reg. 50, No. 187; September 24, 2024
(1) In addition to implementing an approved
BMP Plan, permittees may elect or be required to participate in a discharge
monitoring program pursuant to Rules
40E-63.437,
40E-63.438, paragraph
40E-63.444(1)(r),
subsection 40E-63.461(4)
or 40E-63.461(6),
F.A.C., and be subject to:
(a) For permittees
electing a discharge monitoring program or permittees required to implement a
monitoring program pursuant to subsection
40E-63.461(6),
F.A.C.: alternative, site-specific evaluations of compliance with phosphorus
load targets and limits for the areas represented by the monitoring plan when
the C-139 Basin is collectively determined to be out of compliance in
accordance with Chapter 40E-63, F.A.C., Appendix B2 (incorporated by reference
in subsection 40E-63.446(1),
F.A.C.); and
(b) Compliance with
permit conditions in accordance with Rule
40E-63.464,
F.A.C.
(2) To implement a
discharge monitoring program, permittees must submit a permit application with
the following information:
(a) An acceptable
discharge (quantity and quality) monitoring plan that provides reasonable
assurance that annual water discharge and total phosphorus load are accurately
documented.
(b) All flow quantity
discharge from the property shall be calculated using a method proposed by a
Florida-Registered Professional Engineer in a flow calibration report approved
by the District. A calibration report shall be required for each pump, culvert
or other discharge structure. Uncontrolled off-site discharges, such as
overland sheet flow, shall also be quantified in the report. Each calibration
report shall contain, at a minimum: data collection methodology,
instrumentation and procedures; the actual field data collected; the basis for
the full operating range represented by the data; the methodology for
development of the calibration equation; operational information needed to
calculate flow with a temporary backup methodology to be used if the primary
equipment becomes inoperable; and the final calibration equation and primary
method for calculating the flow. A plan that includes the items specified in
the "Flow Calibration Guidelines Developed in Support of Chapter 40E-63, F.A.C.
Everglades BMP Permit Program", amended July 1997, incorporated by reference
herein, generally provides reasonable assurance that methods to measure water
quantity will be reasonably accurate, however, other alternatives may be
proposed by the applicant and authorized by the District. A copy of the "Flow
Calibration Guidelines Developed in Support of Chapter 40E-63, F.A.C.,
Everglades BMP Permit Program, is available on the District's website (
www.sfwmd.gov/rules), or from the South
Florida Water Management District Clerk, 3301 Gun Club Road, West Palm Beach,
FL 33406, 1(800) 432-2045, ext. 6436 or (561) 682-6436, upon request;
(c) A schedule to install equipment and
implement the monitoring plan no later than 30 days after issuance of the
permit; and
(d) Other site specific
information required by Appendix B3.1 (incorporated by reference in paragraph
40E-63.446(2)(a),
F.A.C.).
Rulemaking Authority
373.044,
373.113,
373.4592 FS. Law Implemented
373.016,
373.085,
373.086,
373.451,
373.453,
373.4592(4)(f)
FS.
New 11-9-10.