Florida Administrative Code
40 - WATER MANAGEMENT DISTRICTS
40E - South Florida Water Management District
Chapter 40E-63 - EVERGLADES PROGRAM
Part III - BMP RESEARCH, TESTING AND IMPLEMENTATION TO ADDRESS WATER QUALITY STANDARDS
Section 40E-63.310 - Conditions for Issuance of a Master Permit
Current through Reg. 50, No. 187; September 24, 2024
In order to qualify for the no-notice master permit provided for in Rule 40E-63.305, F.A.C., the EAA-EPD must satisfy all the following conditions:
(1)
(2) The applicant is advised that standard research protocol requires an approved Florida Department of Environmental Protection (FDEP) Comprehensive Quality Assurance (Comp QA) Plan for collection of field samples. As such, an approved FDEP Comp QA Plan for all parameters specified in subparagraphs 40E-63.310(1)(a) 1.-3., F.A.C., must be obtained by the entity collecting samples prior to initiation of field sample collection. Submit a copy of the approved FDEP Comp QA Plan obtained by the entity who will be conducting field sample collection.
(3) Submit verification of laboratory certification as required by Section 403.0625, F.S., of the laboratory to be used to perform the chemical analyses on the samples. The certification must cover analysis of water quality parameters specified in subparagraphs 40E-63.310(1)(a) 1.-3., F.A.C.
(4) All data being collected as part of the farm-scale research pursuant to subparagraph 1. shall be maintained by the EAA-EPD in a database format for all parties to access and review upon request.
(5) Reports on the status of the EAA-EPD or its successor interests sponsored program of BMP research, testing, & implementation pursuant to subparagraphs 40E-63.310(1)(a) 1.-6., F.A.C., shall be submitted according to a schedule provided in the District approved scope-of-work summarizing program data results, conclusions, milestones, and accomplishments.
(6) The program scope-of-work shall be submitted for District review by January 1, 1997. The District shall take final agency action to approve or deny the program scope-of-work pursuant to this chapter not later than July 31, 1997. The District will conduct an annual public workshop for presentation and discussion of an update of the scope of work, including any application for modification. An annual formal scope-of-work review shall be conducted as a public workshop. Written request for modification to the scope-of-work may be presented and submitted at that time. The District will receive comments from all persons at the public workshop and provide a written determination on the scope-of-work modification within 60 days of the workshop held pursuant to this subsection. The District will approve the modification if the request provides reasonable assurance that the provisions of Section 373.4592(4)(f)2., F.S., will be met.
(7) All information required in subsections (1) through (6) shall be submitted to the South Florida Water Management District, Environmental Resource Permitting Division, 3301 Gun Club Road, West Palm Beach, Florida 33406, Attention: Everglades Regulation Division.
Rulemaking Authority 373.044, 373.113 FS. Law Implemented 373.4592(4)(f) FS.
New 1-1-97, Amended 6-30-97, 7-3-01.