Florida Administrative Code
40 - WATER MANAGEMENT DISTRICTS
40C - St. Johns River Water Management District
Chapter 40C-1 - ORGANIZATION AND PROCEDURE
Part VII - PROCEDURES FOR CONTRACTING OF PROFESSIONAL SERVICES
Subpart B - Design-Build Provisions
Section 40C-1.717 - Competitive Negotiations for Design-Build Services
Current through Reg. 50, No. 187; September 24, 2024
(1) The District staff shall begin contract negotiations for design-build services with the designated firms in order of rank for fair, competitive and reasonable compensation.
(2) Should negotiations with the most highly-ranked firm prove unsuccessful, as determined by the Executive Director or designee, negotiations with that firm shall cease and negotiations shall begin with the next most highly-ranked firm. Negotiations shall continue in accordance with this section until an agreement is reached. The Executive Director or designee is authorized to award the contract.
(3) If a satisfactory agreement is not reached with any of the designated firms, the Board will direct the District staff to either
Rulemaking Authority 287.055, 373.044, 373.113 FS. Law Implemented 287.055, 373.083(1), (5) FS.
New 9-25-90, Amended 6-17-91, 2-13-01.