Florida Administrative Code
40 - WATER MANAGEMENT DISTRICTS
40B - Suwannee River Water Management District
Chapter 40B-3 - PERMITTING OF WELL CONSTRUCTION
Section 40B-3.321 - Duration of Permits
Current through Reg. 50, No. 187; September 24, 2024
(1) Each permit shall be consecutively numbered, dated, and valid for a period of ninety (90) days, unless the time limit is extended by the District pursuant to subsection (3) or (4), below.
(2) Construction, repair, modification, or abandonment of a well shall not commence or continue after the expiration of a permit.
(3) One extension of an existing permit for a period not to exceed 90 days shall be granted by the District upon written request if:
(4) Public supply well permits shall be extended for a period of not more than one year from the date of issuance, in increments of 90 days per written request for permit extension, provided the requirements of subsection (3) above have been met. Extensions pursuant to subsections (3) or (4) will be covered under the original permit fee, with no additional fee required.
Rulemaking Authority 373.044, 373.113, 373.171 FS. Law Implemented 373.308, 373.309, 373.313, 373.326 FS.
New 7-1-85, Amended 1-3-96, 6-22-99.