Delaware Administrative Code
Title 7 - Natural Resources and Environmental Control
5000 - Division of Watershed Stewardship
5103 - Delaware Dam Safety Regulations
Section 5103-8.0 - Requirements for Engineering and Design
Universal Citation: 7 DE Admin Code 5103-8.0
Current through Register Vol. 28, No. 3, September 1, 2024
8.1 Geotechnical Investigation
8.1.1 A geotechnical investigation shall be
conducted to characterize the soil, concrete and rock conditions at the dam and
spillway site and borrow areas (if appropriate) sufficient for design purposes.
The investigations may consist of intrusive and/or non-intrusive techniques
that are deemed acceptable to the Department.
8.1.2 The means and methods for conducting
the investigation of existing dams shall be selected so as not to jeopardize
the integrity of the dam or ancillary facilities.
8.2 Spillway Requirements
8.2.1 The minimum Spillway Design Flood (SDF)
used to calculate required spillway capacity shall be determined as follows:
8.2.1.1 Hazard Class I - The SDF shall be the
PMF
8.2.1.2 Hazard Class II - the
SDF shall be 50% of the PMF
8.2.1.3
Hazard Class III - the SDF shall be the 24-hour, 100-year frequency, Type II
storm. Any later technology adopted by the U.S. Department of Agriculture,
Natural Resources Conservation Service, may be substituted for the use of the
Type II storm with the approval of the Department.
8.2.2 For existing dams, it is recognized
that the relationships between valley slope and width, total reservoir storage,
drainage area, and other hydrologic factors have a critical bearing on
determining the safe SDF. When appropriate, and upon the approval of the
Department, an incremental flooding assessment may be used for the rational
selection of a reduced spillway design for specific site conditions based on
quantitative and relative impact analysis. The spillway should be sized so that
the increased downstream damage resulting from overtopping failure of the dam
would not be significant as compared with the damage caused by the flood in the
absence of a dam overtopping failure. The minimum design storm for the dam
shall be the 100-year storm.
8.2.3
All Class II and III dams shall, where practicable, incorporate in the proposed
design the ability to make modifications necessary to increase the spillway
capacity of the facility or other alternative measures if the downstream hazard
potential increases.
8.2.4 All dams
shall have an adequate storage for the SDF or have a spillway system that will
safely pass the SDF without endangering the safety of the dam.
8.2.5 Each spillway shall include a
satisfactory means of dissipating the energy of flow at its outlet without
endangering the safety of the dam.
8.2.6 The capacity of the spillway system
shall be equal to the peak inflow of the design flood unless the applicant
demonstrates by flood routing procedures that the spillway system has the
capacity to safely pass the resulting water flow.
8.2.7 Pipe conduits may be used for the
primary (principal) spillway. When so used, the following requirements shall be
met:
8.2.7.1 Pipe conduits shall be of such
design as to safely support without leakage the total external loads in
addition to the total internal hydraulic pressure. The type of construction
material used shall be consistent with the anticipated life of the structure.
Corrugated metal pipe shall not be used in the construction of new dams
8.2.7.1.1 For Class I and II dams, the
minimum allowable inside dimension of the pipe conduit is 30 inches to allow
for inspection.
8.2.7.1.2 For Class
III dams, the minimum allowable inside diameter of the pipe conduit is 18
inches.
8.2.7.2 All pipe
conduits shall convey water at the maximum design velocity without damage to
the interior surface.
8.2.7.3 The
pipe conduit must be designed so that negative pressures will not occur at any
point along the primary (principal) spillway system.
8.2.7.4 Filter diaphragms or other seepage
control methods approved by the Department must be installed to control seepage
along the conduit.
8.2.7.5 Adequate
allowances shall be incorporated in the design to compensate for differential
settlement and possible elongation of the pipe conduit.
8.2.7.6 An anti-vortex device must be
included in the design, unless the applicant can demonstrate that one is not
necessary.
8.2.7.7 A self-cleaning
trash rack, approved by the Department, shall be installed at the intake to
prevent clogging of the pipe conduit.
8.2.7.8 An emergency spillway shall be
provided.
8.2.7.9 Corrosion
protection shall be provided for all steel pipes as necessary.
8.2.7.10 Concrete cradles or encasements
shall be provided for conduits through earth dams.
8.2.7.11 All structural concrete and steel
structures shall be designed to resist the anticipated design loads using
current design methodologies acceptable to the Department.
8.2.8 Should a vegetated or unlined auxiliary
spillway, approved by the Department, be installed, it must be able to pass the
SDF without jeopardizing the safety of the structure and with a computed
average frequency of use less than:
8.2.8.1
Once in 100 years for Class I dams,
8.2.8.2 Once in 50 years for Class II dams,
or
8.2.8.3 Once in 25 years for
Class III.
8.3 Outlet Works and Drawdown Requirements
8.3.1
Except for excavated impoundments, dams shall include a device to allow
draining of the reservoir within a reasonable amount of time. The following
factors shall be considered in determining the reasonable time period for
drainage:
8.3.1.1 The risk and nature of a
potential dam failure
8.3.1.2 The
time likely to be available to avert a failure after notice of conditions
threatening the safety or stability of the dam
8.3.1.3 The influence of rapid drawdown on
the stability of the dam, its appurtenant works, and the natural upstream
slopes of the reservoir
8.3.2 Unless the applicant demonstrates to
the satisfaction of the Department that there is a need to locate a valve
downstream from the dam and that the areas downstream of the dam will remain
protected, all valves or sluice gates in pipe conduit drains must be installed
upstream of the dam.
8.3.3 All pipe
conduits used as drawdown drains for all dam classifications shall meet the
requirements of Section 8.2.7, except that the minimum allowable inside
dimension may be less than 30 inches.
8.4 Dam Requirements
8.4.1 The dam design shall designate what
materials are suitable for the foundation of the dam, estimate the amount of
foundation settlement, and describe the necessary foundation treatment for the
structure.
8.4.2 The dam design
shall designate what materials are to be used to construct the dam structure
and provide the necessary design criteria for those materials. For embankment
dams this includes, but is not limited to gradation, plasticity, strength,
permeability, compaction and moisture criteria, lift thickness, and other
properties that may be required by the Department. The source of the materials
for embankment dams shall be designated. For concrete dams, the information
provided shall include, but not be limited to the type of concrete, type of
cement, aggregates, mix design, unconfined compressive strength, slump, and
placement and curing procedures.
8.4.3 The applicant must demonstrate that the
dam structure is stable under its various loading conditions, which must
include at a minimum: during and after construction case, steady state case,
maximum pool case, rapid drawdown case, and appropriate earthquake loading
case. The engineering analysis and design shall follow current accepted
engineering practices such as those of the U.S Army Corps of Engineers, the
Natural Resources Conservation Service, the U.S. Bureau of Reclamation, the
Federal Energy Regulatory Agency or other recognized standards and
methodologies acceptable to the Department.
8.4.4 A seepage analysis shall be conducted
to estimate the quantity of seepage that is anticipated to flow through,
beneath, and/or around the dam. Unless it can be demonstrated that they are
unnecessary, the design should include seepage reduction and/or control
features to limit and/or collect and control seepage. Example techniques to
reduce seepage include cut-off trenches, low-permeability cores, slurry
trenches, or other proven methodologies acceptable to the Department. Example
techniques for controlling and collecting seepage generally include drains,
filters, and relief wells or other methodologies acceptable to the
Department.
8.4.5 The design shall
allow for certain freeboard as a minimum, not to be reduced under any
circumstances during the operation of the dam and reservoir. The design
freeboard is for that reservoir stage that will exist when the pool has reached
maximum level during the spillway design flood with the outlet works and
overflow spillway operating as planned. The freeboard is to be calculated to
prevent overtopping and protect the dam against the destructive forces of
waves, frost, settlement, and surface erosion.
8.4.6 The design shall provide for upstream
slope protection against the action of waves and ice.
8.5 Other Requirements
8.5.1 Design references used shall be cited
in the information submitted to the Department.
8.5.2 The Department may include, either at
the time of granting a Permit to Construct a New Dam, or a Permit to Alter or
Repair an Existing Dam or at a later date, a requirement that the owner provide
and install devices necessary for the future inspection and surveillance of the
dam. The number, type, and location of the devices shall be determined as a
result of the Department's evaluation of the site and nature of the dam, the
complexity of local natural conditions, and the degree of risk resulting from
any future deterioration or failure. The requirement may include provisions for
the measurement of the settlement of the crest or slopes of dams, the movement
of walls in the valley or reservoir, the increases in pore water pressure in
earth or increases in flow from drainage systems, and the installation of other
devices required to detect serious changes in the structure or the affected
area to allow the repair of deficiencies before more serious risk
develops.
8.5.3 The applicant shall
demonstrate to the Department that the riparian rights of downstream property
owners will be protected during construction, during the period when the
reservoir is being filled and during the life of the dam and
reservoir.
8.5.4 The Department may
require the design and installation of any additional or modified measures by
any applicant for a dam permit where appropriate to ensure the protection of
human health or safety.
8.5.5 In
the case of multiple dams, when they are spaced so that the failure of an
upstream dam or structure could endanger the safety of one downstream, the
possibility of a multiple failure shall be considered in reviewing the
design.
8.5.6 Utilities crossing
within dam embankments are prohibited unless demonstrated to the satisfaction
of the Department that such utilities will not jeopardize the safety of the
dam.
Disclaimer: These regulations may not be the most recent version. Delaware may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.