Delaware Administrative Code
Title 2 - Transportation
2000 - Department of Transportation
2300 - Division of Planning and Policy
2309 - Development Coordination Manual
Chapter 6 - CONSTRUCTION ADMINISTRATION
Section 6.5 - SUBDIVISION STREETS
Current through Register Vol. 28, No. 3, September 1, 2024
6.5.1 Subdivision Streets - Application Process
This section outlines the application process for the construction of new subdivision streets dedicated for public use and intended for acceptance into State maintenance. Prior to issuance of a NTP the following documents must be submitted to the Public Works Engineer for review and approval:
The approved security forms are provided online at http://devcoord.deldot.gov/ > Forms.
6.5.2 Subdivision Streets - Notice to Proceed (NTP)
After review and approval of the construction agreement and security, the Public Works Engineer will address the following items prior to issuance of the NTP:
Preconstruction Meeting - The Public Works Engineer will determine if a preconstruction meeting is needed prior to issuance of the NTP. The preconstruction meeting shall be scheduled by the Public Works Engineer or designee and attended by appropriate representatives of DelDOT, the developer, the design engineer, contractor, utility firms and such other agencies as may be deemed appropriate. Items to be discussed at this meeting may include, but are not limited to, the following:
Following approval of the required submissions and a successful preconstruction meeting, the Public Works Engineer shall issue the NTP, allowing the developer to proceed with construction on bonded streets.
Construction of the entrance to the subdivision shall be complete (excluding the top paving course) prior to the 1st certificate of occupancy. Once construction has started on the roadway it must remain active until completed up to but not including the final lift of asphalt. The entrance may be required to be built sooner at the discretion of the Public Works Engineer.
If a project is nearing approval as determined by DelDOT, then the developer may request from the Public Works Engineer a temporary entrance permit, to perform specific allowable construction activities such as clearing and grading at its own risk prior to final approval of subdivision construction plans by the DelDOT Subdivision Engineer. Only the work that is directly part of the entrance permit may be performed within the State-maintained right-of-way, and no construction materials (such as graded aggregate base course, asphalt or drainage pipe) can be placed until after the construction plans of the subdivision drawings are stamped "APPROVED" by the DelDOT Subdivision Engineer. Unapproved work activities performed may result in DelDOT closing or removing the temporary construction entrance. If final approval is not received within the timeframe specified in the temporary entrance permit, then all construction activities shall be stopped and the permit shall be withdrawn.
Once the DelDOT Subdivision Engineer approves the subdivision construction drawings, two complete sets of approved construction drawings shall be forwarded to the Public Works Engineer. The drawings must have the approval stamp of the DelDOT Subdivision Engineer.
Upon receipt of approved construction drawings and following review of items required in Section 6.5.1, the Public Works Engineer will evaluate the items specified in Section 6.5.2 prior to issuance of a final "Notice to Proceed" letter, allowing the developer to proceed with permanent street construction within the subdivision.
6.5.3 Subdivision Streets - Inspection and Acceptance
Projects are divided into two levels based on their size and impact on the abutting State-maintained roadway. This categorization helps DelDOT identify the level of involvement with each project, and what division will manage the construction of the project. Figure 6.4.3-a summarizes the two levels of construction inspection to be used for subdivision entrances and/or bridges within subdivisions.
DelDOT reserves the right to inspect and approve any construction associated with the proposed subdivision in accordance to Section 6.9 and the inspection procedures outlined in the DelDOT Construction Manual. Additional inspection will be required for all proposed bridges within subdivisions.
DelDOT also reserves the right to make such changes, additions, and relocations to the approved plans that may be considered necessary to ensure compliance with this Development Coordination Manual along with applicable guidelines and standards, such as those listed in Section P.9.1 of this manual, which include but are not limited to: Manuals, Guidelines and Policies published by the American Association of State Highway and Transportation Officials (AASHTO); DelDOT's Road Design Manual (RDM); DelDOT's Bridge Design Manual; DelDOT's Design Guidance Memorandums (DGM); DE MUTCD; other Nationally Accepted Standards (NAS) and ensure the safety of the traveling public. Non-compliant structures and roadside obstructions including brick mailboxes shall be removed at DelDOT's direction prior to final acceptance.
The Developer shall request a semi-final inspection when all work is complete. Once the semi-final inspection is completed and accepted, an accessibility inspection shall be scheduled. Once the accessibility inspection punch list items are completed and accepted, a final inspection may be requested. The Public Works Engineer or the Construction Group Engineer may then schedule a final inspection which shall be conducted by DelDOT. DelDOT personnel, accompanied by the developer and/or his/her contractor, and representatives of the appropriate County and/or municipal officials, shall inspect the site and determine those items of work, if any, that must be either completed, repaired or replaced.
Once DelDOT is satisfied with the construction, the inspector shall recommend final acceptance and the release of the security by the Public Works Engineer. The local land use agency shall be notified prior to final acceptance.
In the event of failure to perform the intended construction in accordance with the terms of the construction agreement as determined by DelDOT, the developer shall receive written notice and have fourteen calendar days to provide DelDOT with an approved schedule for completion. If a schedule for completion has not been received within the specified time period, the developer shall receive a second written notice and have an additional seven calendar days to meet in person with DelDOT and present an approved schedule for completion.
Should the developer fail to provide a satisfactory construction schedule or fail to comply with the approved completion schedule, DelDOT shall have the right to collect the construction security to correct the condition as per the construction agreement. All costs incurred in the removal and/or correction of defective workmanship and/or materials over and above the construction security shall be borne by the applicant.
Withdrawal of subdivision street construction approval for failure to complete the intended construction in accordance with the terms of the construction agreement as determined by DelDOT shall be cause to increase the required construction security to 100% of the itemized cost estimate on future subdivision street construction projects proposed by the defaulting applicant.
Following completion of street construction and submission of required documentation to the satisfaction of the Public Works Engineer, the Public Works Engineer will recommend acceptance of the streets and shall prepare an "Acceptance Drawing and an Acceptance Statement" for signatures. Once accepted into the State maintenance system, the Developer shall be responsible for any failure of shared-use paths, sidewalks, pavement or drainage for three years from the date of acceptance, as noted in the Construction Agreement found at http://devcoord.deldot.gov/, and as described in Section 6.5.4. If the developer fails to correct three year good faith punch list items, this shall also be cause to increase the required construction security to 100% of the itemized cost estimate on future subdivision street construction projects. Once the three year good faith punch list items have been corrected, standard security rates will be reinstated on future subdivision street construction projects.
Upon acceptance of the streets into the State maintenance system, an entrance permit shall be required for each new entrance to the street as outlined in Chapter 7. The applicant shall be responsible for damage to the curb, gutter, shoulders, and drainage affected by any entrance construction.
In subdivisions where residential streets and cul-de-sacs have been completed and the collector street serving them is complete except for the final lift of asphalt pavement, the developer shall submit the completed residential streets and cul-de-sacs for acceptance. Additionally, the developer shall provide:
The Planning Section shall assign maintenance road numbers to the subdivision streets following acceptance by DelDOT.
6.5.4 Subdivision Streets - Maintenance
Alleys should be used within the subdivision street layout in accordance with appropriate subdivision design principles and the requirements of local land use ordinances. While DelDOT encourages the appropriate use of alleys in subdivision street layout, DelDOT shall not accept any maintenance responsibilities for alleys in the public right-of-way.