Connecticut Administrative Code
Title 8 - Zoning, Planning, Housing, Economic and Community Development
198 - Municipal Development Projects
Section 8-198-6 - Requirements for the adoption and approval of the project plan
Current through December 12, 2024
(a) Upon commitment of planning or special planning grant funds, the development agency begins preparing the project plan for the development project. The required elements of the project plan are contained in Section 8-189 of the General Statutes.
(b) When the proposed project plan is completed and prior to approval by the development agency, the development agency shall send a number of copies, to be determined by the Department, to the Commissioner. The proposed project plan shall be reviewed by appropriate state agencies through a review process coordinated by the Office of Policy and Management using copies of the proposed project plan provided to the Office of Policy and Management by the Department. The appropriate state agencies shall make a determination that the proposed project plan is, or is not, inimical to the planning program objectives of the agencies. If a determination is made that the plan is inimical, the individual agency shall state its reasons for making this determination. Upon receipt of the remarks of the state agencies through the Office of Policy and Management, the Department shall transmit the remarks to the development agency. In a case of an inimical determination, the Department shall indicate to the development agency that the proposed project plan cannot be determined by the Department to be complete without resolution of the inimical determination.
(c) Prior to the approval of the plan by the development agency:
(d) Upon receipt of the results of the plan review from the Department and of actions required in subsection (c) of this section, the development agency shall approve the project plan by adopting a resolution that specifically approves the findings made in the project plan in accordance with Section 8-189(k) of the General Statutes.
(e) The development agency shall then submit the approved plan to the legislative body of the municipality for its approval. The legislative body shall approve the plan through a resolution that shall specifically include the approval of the findings made in the plan in accordance with Section 8-189(k) of the General Statutes.
(f) After approval of the project plan by the development agency and the legislative body of the municipality, the development agency shall submit the project plan, with certified copies of all resolutions, to the Commissioner requesting the Commissioner's approval of the project plan. Prior to the approval of the project plan by the Commissioner and concurrent with or prior to submittal of the project plan to the Commissioner: