Connecticut Administrative Code
Title 4b - State Real Property
24 - Selection Panels for Design-Build Teams and Special Legislation Contractors
Section 4b-24-6 - Screening panel
Current through September 9, 2024
(a) No later than six (6) weeks after the deadline for proposal submission, unless extended in writing by the commissioner, each screening panel member shall:
(b) Past performance of the design-build team, design-build team members, special legislation contractor or a member of a special legislation contractor's construction team shall be considered by the screening panel and the panel members' scores shall reflect such past performance. The information contained in any completed performance form for such team, member, or contractor; any information available pursuant to section 4a-101 of the Connecticut General Statutes; and any information or documents from department staff or contained within state agency files concerning the quality, workmanship, and performance regarding a design-build team, design-build team member, special legislation contractor, or a member of a special legislation contractor's construction team on prior work shall be considered by the panel members.
(c) The DPW chairperson and the DPW selection administrator shall tabulate the scores of all panel members and no more than the four (4) highest rated design-build teams or special legislation contractors shall be recommended for interview. Notwithstanding the provisions of this subsection, no such team or contractor shall be recommended for interview if such team or contractor failed to submit an affidavit or certification required pursuant to sections 4-251 and 4-252 of the Connecticut General Statutes.
(d) Each panel member shall submit to the commissioner the signed certification form required under section 4b-24-3(b) of the Regulations of Connecticut State Agencies.