Code of Colorado Regulations
400 - Department of Natural Resources
408 - Colorado Water Conservation Board
2 CCR 408-2 - RULES CONCERNING THE COLORADO INSTREAM FLOW AND NATURAL LAKE LEVEL PROGRAM
Section 9 - MODIFICATION OF ISF RIGHTS

Universal Citation: 2 CO Code Regs 408-2 ยง 9

Current through Register Vol. 47, No. 17, September 10, 2024

The Board may modify any existing decreed ISF right according to the procedures set forth in this Rule. "Modification" of an ISF right within the meaning of this Rule includes a decrease in the rate of flow described in the existing ISF decree, segmenting an existing ISF reach into shorter reaches with the result of decreasing the rate of flow in any portion of an ISF reach, or subtracting water from an ISF right during any particular time period or season.

9a. Need for Modification.

Modification may be requested by the Staff or by any Person who has filed a water right application on an ISF reach or who has applied for any governmental permit for facilities located in or near an ISF reach and who complies with Rules 9b. and 9c. Any request for modification, except by staff, shall be made in writing, submitted to Staff and such writing shall contain the following information:

(1) name, address and telephone number of the Person seeking modification;

(2) stream or lake subject of request;

(3) modification requested;

(4) reason for modification; and

(5) the scientific data supporting the request.

9b. Need for Water.

Any Person who requests a modification of an ISF right must, as a precondition to the Board's consideration of the request, establish a need for the water made available by the modification. Staff does not have to comply with this rule and any governmental entity seeking to implement the terms of an agreement specified in Rule 9f. does not have to comply with this section.

9c. Grounds for Modification.

No request for modification may be considered until the applicant establishes that one of the following reasons for modification exists:

(1) Mistake.

An ISF right may be considered for modification if the requesting Person establishes that an error was made in the calculations upon which the original or supplemental appropriation or enlargement to an original appropriation was made.

(2) Excessive Flow.

An ISF right may be considered for modification if the requesting Person establishes that the ISF flow rate is in excess of the amount of water necessary to accomplish the purpose of the original, supplemental or enlarged ISF right when that right was appropriated.

9d. Recovery Implementation or Other Intergovernmental Agreement.

An ISF right may be modified if such modification was agreed upon by the Board as part of the Recovery Implementation Program for the Endangered Fishes of the Colorado River Basin or any other agreement between the Board and another governmental entity. Modifications made as a part of the Recovery Implementation Program for the Endangered Fishes of the Colorado River Basin need not be subject to the public review process in Rule 9e. Criteria for modifications made in the ISF rights decreed as part of the Recovery Implementation Program for the Endangered Fishes of the Colorado River Basin will be established in the decrees governing such appropriations.

9e. Public Review Process of Requests for Modification.

The Board shall adhere to the following public review process when considering requests for modification:

(1) Notice.

Notice of the proposed modification and the date of the public meeting at which it will first be considered shall be printed in the resume in the Water Court having jurisdiction over the decree that is the subject of the modification. The first public meeting of the Board at which the modification is to be considered shall occur at least sixty days after the month in which the resume is published. Notice shall also be published in a newspaper of statewide distribution within thirty to forty-five days prior to such first public meeting.

(2) Public Meeting.

If the Board decides at such first public meeting to give further consideration to the proposed modification, the Board shall announce publicly the date of a subsequent public meeting for such purpose. If the Board decides that it will not give further consideration to the proposed modification, it shall state, in writing, the basis for its decision.

(3) Request for Delay.

On the written request of any Person made within thirty days after the date of the first public meeting, the Board shall delay the subsequent public meeting for up to one year to allow such Person the opportunity for the collection of scientific data material to the proposed modification. The Board need not grant the request if it determines that the request is made solely to delay the proceedings.

(4) Procedures.

On the written request of any Person made within thirty days after the date of the first public meeting, the Board shall, within sixty days after such request, establish fair and formal procedures for the subsequent public meeting, including the opportunity for reasonable disclosure, discovery, subpoenas, direct examination, and cross examination. Subject to these rights and requirements, where a meeting will be expedited and the interests of the participants will not be substantially prejudiced thereby, the Board may choose to receive all or part of the evidence in written form.

(5) Final Determination.

The Board shall issue a final written determination regarding the modification that shall state its effective date, be mailed promptly to the Persons who appeared by written or oral comment at the Board's proceeding, and be filed promptly with the water court.

Disclaimer: These regulations may not be the most recent version. Colorado may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.