A. Short term bark damage (0-33%/limb or trunk) = no loss

B. Long term bark damage

1. (34-49%/limb or trunk) = 33% loss

$ Loss = (# of trees) (Bu/Tree) (33%) (ORV Equivalent) (2.0) (87%) Where,

ORV Equivalent =

(ORV/Bu) - (Harvest + Haul Cost/Bu)

2.0 Factor =

Recovery Loss Adjustment for 4-year recovery period.

87% =

Present value percentage factor from column 3 of Table B of #1754.

2. (50-59%/limb or trunk) = 65% Loss

$ Loss =

(# of Trees) (Bu/Tree) (65%) (ORV Equivalent) (3.5) (80%)

Where,

ORV Equivalent =

(Orchard Run $/Bu) - (Harvest + Haul Cost/Bu)

3.5 Factor =

Recovery Loss Adjustment for 6- year recovery period.

80% =

Present value percentage factor from column3 of Table B of #1754.

C. Permanent Bark Damage (60+%/Limb or trunk) = 100% Loss

Trees which have a limb and/or truck-limb damage in excess of 60%.

1. Limb loss without 100% tree loss.

$ Loss/Tree=

(Bu/Tree) (# 100%-loss limbs/Total # Limbs) (ORV Equivalent) (Years) (P.V.1) + (Bu/Tree) (# 33%-loss limbs/Total #limbs) (33%) (ORV Equivalent) (2.0) (87%) + (Bu/Tree) (# 65%-loss limbs/total # limbs) (65%) (ORV Equivalent) (3.5) (80%)

Where

ORV Equivalent =

(ORV/Bu) - (Harvest + Haul Cost/Bu)

Years =

Remaining Commercial Life

P.V.1 =

Present value percentage factor from Column 3 of Table B of #1754 based on # of years of remaining commercial life.

2.0 and 3.5 factors =

recovery loss adjustment for 4 and 6 year recovery periods respectively.

87% and 80% =

present value percentage factors from column 3 of Table B of #1754 for 4 and 6 year recovery periods.

(Recovery period for 33% damaged tree is deemed to be 4 years and for 65% damaged tree it is deemed to be 6 years.)

Total Block $ Loss =

sum of losses calculated for individual trees.

2. Total tree loss (individual or block)

Production $ loss =

(# of trees) (Bu/tree) (ORV equivalent) (Years) (P.V.)

Replacement $ Cost =

(# of trees) (Cost of removal/tree + replacement cost/tree + replant cost/tree - operational cost savings)

Total $ loss =

Production $ loss + replacement $ cost

Where,

ORV Equivalent =

(ORV/Bu) - (Harvest + Haul Cost/Bu)

Years =

# years of remaining commercial life, but not greater than 10 years for apple, 8 years for peach/apricot, 15 years for sweet cherry, 10 years for sour cherry.

P.V. =

Present value percentage factor from column 3 of Table B of #1754 based on # years of remaining commercial life.

Disclaimer: These regulations may not be the most recent version. Colorado may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.