a. Operators will submit a Form 15, Earthen Pit Report/Permit to the Director for review and approval prior to constructing any of the following:
b. Operators will submit a Form 15, to the Director for review and approval prior to enlarging or otherwise modifying an existing properly permitted Pit.
c. Operators will submit a Form 15 within 30 days after constructing:
d. In order to allow adequate time for Pit permit review and approval, Operators will submit a Form 15 at the same time they submit a Form 2A or Oil and Gas Development Plan. The Director may condition approval of the Form 15 upon compliance with additional terms, provisions, or requirements necessary to protect and minimize adverse impacts to public health, safety, welfare, the environment, and wildlife resources. The Director may deny a Form 15 if the Director determines it does not provide necessary and reasonable standards to protect and minimize adverse impacts to public health, safety, welfare, the environment, and wildlife resources. Notwithstanding the foregoing, no Form 15 will be approved until the associated Form 2A or Oil and Gas Development Plan is approved.