Section 806 - TIMING OF INJECTION FLUID SAMPLING AND ANALYSIS
Current through Register Vol. 47, No. 17, September 10, 2024
a. Initial Analysis. An injection Fluid analysis from a representative sample collected at the injection facility is required within 1 year of commencing injection after approval of an injection application.
b. Periodic Analysis. An injection Fluid analysis from a representative sample collected at the injection facility is required every 5 years after the initial analysis or 5 years after the most recent change of source analysis.
c. Change of Source Analysis. An injection Fluid analysis is required when there is a significant change in the quality of the injection Fluid and as required by Rule 807. The injection Fluid analysis will address all analytes listed in and follow all procedures required by Rules 909.j.(1)- (5).