Code of Colorado Regulations
400 - Department of Natural Resources
404 - Oil and Gas Conservation Commission
2 CCR 404-1 - PRACTICE AND PROCEDURE
Section 418 - FORM 21, MECHANICAL INTEGRITY TEST

Current through Register Vol. 47, No. 17, September 10, 2024

a. Results of all mechanical integrity tests, including tests that show a lack of integrity, will be submitted on Form 21, Mechanical Integrity Test, within 30 days after the test.

b. A mechanical integrity test that shows the Well lacks integrity is considered a failed test.

c. The Form 21 will be completely filled out except for Part II, which is required only for injection Wells. An original copy of the pressure chart will be submitted with every Form 21.

Disclaimer: These regulations may not be the most recent version. Colorado may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.