Code of Colorado Regulations
400 - Department of Natural Resources
404 - Oil and Gas Conservation Commission
2 CCR 404-1 - PRACTICE AND PROCEDURE
Section 410 - DIRECTIONAL DRILLING
Universal Citation: 2 CO Code Regs 404-1 ยง 410
Current through Register Vol. 47, No. 17, September 10, 2024
a. Deviated Drilling Plan.
(1) If an
Operator intends to drill a deviated (directional, highly deviated, or
horizontal) wellbore utilizing controlled directional drilling methods, the
Operator will prepare a deviated drilling plan that includes sufficient data to
describe the location of the wellbore in three dimensions from not greater than
500 feet below the surface of the ground to total depth.
(2) The Operator will file the deviated
drilling plan with the Form 2 in a format approved by the Director.
b. Directional Survey for a Deviated Wellbore.
(1) For an
intentionally drilled deviated wellbore the Operator will perform a directional
survey of the wellbore in a manner to gather sufficient data to describe the
location of the wellbore in three dimensions and from not greater than 500 feet
below the surface of the ground to total depth.
(2) The directional survey will be included
with the Form 5, and in a format approved by the Director.
c. Inclination Survey for a Non-deviated Wellbore.
(1) For a newly
drilled non-deviated wellbore or for the re-entry, recompletion or deepening of
an existing wellbore, the Operator will perform an inclination survey of the
wellbore and file the inclination survey with the Form 5.
(2) The first shot point of such inclination
survey will be made at a depth not greater than 500 feet below the surface, and
succeeding shot points will be made either at 500-foot intervals or at the
nearest drill bit change thereto, but will not exceed 1,000 feet apart. The
inclination survey may be made either during the normal course of drilling or
after the Well has reached total depth. A directional survey meeting the
requirements of Rule 410.b may be filed in lieu of an inclination
survey.
(3) In the event a Form 5
is not required for re-entry, recompletion, or deepening of an existing
wellbore, the Operator will file the inclination survey with a Form
4.
(4) The survey will be provided
in a format approved by the Director.
d. Wellbore Setback Compliance. The Operator will ensure that the wellbore complies with the setback requirements in the Commission's orders or Rules prior to producing the Well.
Disclaimer: These regulations may not be the most recent version. Colorado may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.