Section 220 - FORM 12, GAS FACILITY REGISTRATION/CHANGE OF OPERATOR
Current through Register Vol. 47, No. 17, September 10, 2024
a. Facility Registration. The Operator of a new gas gathering system, a new gas compressor station, a new gas processing plant, or a new underground gas storage facility will submit a Form 12, Gas Facility Registration/Change of Operator, within 30 days of placing the new facility into service. The following information will be included:
b. Annual Reports. For a gas gathering system, gas processing plant, gas compressor station, or underground storage facility that has had any Gathering Lines added or removed during the preceding year, the Operator will submit a Form 12 by May 1st of each year to report the changes made during the prior calendar year. For an underground storage facility that has had an expansion or reduction of its capacity of more than 10% during the preceding year, the Operator will submit a Form 12 by May 1st of each year to report the changes made during the prior calendar year.
c. Change of Operator. The previous or new Operator of a gas gathering system, gas compressor station, gas processing plant, or an underground gas storage facility, will submit a Form 12 within 30 days of change of Operator. Documentation confirming transfer of ownership will be attached to the Form 12.
d. Gas Storage Projects. The Commission's 800 Series Rules do not apply to Gas Storage Wells and underground gas storage facilities.