Code of Colorado Regulations
1501 - Office of the Governor
1501 - Colorado Land Use Commission
8 CCR 1501-1 - RULES AND REGULATIONS
Part 1 - LAND USE COMMISSION PROCEDURES
Chapter 4 - PROCEDURES FOR INITIATION AND REVIEW OF LOCAL GOVERNMENT ACTION UNDER H.B. 1041 (1974)
Article II - REQUESTS FOR LOCAL GOVERNMENT DESIGNATION
Section 8 CCR 1501-1-4-II-204 - Local Government Action

Current through Register Vol. 47, No. 17, September 10, 2024

(1) Within 30 days of receipt of a formal Commission request to take action with respect to a matter of state interest, the local government shall publish notice and within 60 days shall hold a public designation hearing pursuant to § 24-65.1-404, C.R.S. 1973.

(2) Upon completion of the public designation hearing it shall be the duty of the local government to issue an order either adopting, adopting with modification, or rejecting the matters encompassed by the formal request.

Disclaimer: These regulations may not be the most recent version. Colorado may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.