(a) During construction or installation, liners (except in the case of existing portions of landfills exempt from § 264.301(a)) and cover systems (e.g., membranes, sheets, or coatings) must be inspected for uniformity, damage and imperfections (e.g., holes, cracks, thin spots, or foreign materials). Immediately after construction or installation:
(1) Synthetic liners and covers must be
inspected to ensure tight seams and joints and the absence of tears, punctures,
or blisters; and
(2) Soil-based and
admixed liners and covers must be inspected for imperfections including lenses,
cracks, channels, root holes, or other structural non-uniformities that may
cause an increase in the permeability of the liner or cover.
(b) While a landfill is in operation, it must be inspected weekly and after storms to detect evidence of any of the following:
(1) Deterioration,
malfunctions, or improper operation of run-on and run-off control
systems;
(2) Proper functioning of
wind dispersal control systems, where present; and
(3) The presence of leachate in and proper
functioning of leachate collection and removal systems, where
present.
(c)
(1) An owner or operator required to have a
leak detection system under § 264.301(c) or (d) must record the amount of
liquids removed from each leak detection system sump at least once each week
during the active life and closure period.
(2) After the final cover is installed, the
amount of liquids removed from each leak detection system sump must be recorded
at least monthly. If the liquid level in the sump stays below the pump
operating level for two consecutive months, the amount of liquids in the sumps
must be recorded at least quarterly. If the liquid level in the sump stays
below the pump operating level for two consecutive quarters, the amount of
liquids in the sumps must be recorded at least semi-annually. If at any time
during the post-closure care period the pump operating level is exceeded at
units on quarterly or semi-annual recording schedules, the owner or operator
must return to monthly recording of amounts of liquids removed from each sump
until the liquid level again stays below the pump operating level for two
consecutive months.
(3) "Pump
operating level" is a liquid level proposed by the owner or operator and
approved by the Department based on pump activation level, sump dimensions, and
level that avoids backup into the drainage layer and minimizes head in the
sump.
Disclaimer: These regulations may not be the most recent version. Colorado may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.