Current through Register Vol. 47, No. 17, September 10, 2024
61.14(1)
APPLICABILITY
(a) Pursuant to
this section a permit shall be required for all land application discharges and
for all discharges from impoundments unless:
(i) The discharge is exempted under section
61.14(1)(b);
(ii) The discharge is
subject to the jurisdiction of one of the implementing agencies described in
61.14(2);
(iii) The impoundment has
received a waiver from the Division pursuant to section 61.14(9)(a);
or
(iv) The owner of a land
application system can demonstrate that:
(A)
The design and operation of the system will result in complete
evapotranspiration of the effluent;
(B) There is adequate storage provided for
the effluent during periods of inclement weather or where the ground has been
frozen unless the provisions of (A) above, can be met during the entire year;
and;
(C) Any augmentation plan or
substitute supply plan for the land application site does not provide a credit
for return of the effluent to ground water.
(v) Land application of reclaimed water is
occurring under the provisions of a notice of authorization issued pursuant to
Regulation 84, including any return flow.
(vi) The discharge consists entirely of
animal or agricultural waste on farms, ranches, floricultural, or horticultural
operations and is exempted from permitting under section
25-8-504(2)(a),
C.R.S.
(b) The
following facilities are specifically exempted from coverage under the ground
water discharge provisions of this regulation:
(i) Any impoundment subject to regulation
under the Uranium Mill Tailings Radiation Control Act,
42 U.S.C., Section
7901, et seq. as amended.
(ii) Any impoundment used in the treatment,
storage or recharge of raw or potable water.
(iii) Any stormwater retention or detention
impoundment.
(iv) Any impoundment
or land application system for which a currently valid certificate of
designation has been obtained pursuant to the Solid Waste Disposal Sites and
Facilities Act, C.R.S. 1973,
30-20-101, et seq. as amended, and
other impoundments or land application systems subject to regulation under that
Act which are not part of a wastewater treatment system for which a Colorado
Discharge Permit System (CDPS) permit for a discharge to surface waters is
required.
(v) Any tank which does
not result in a discharge to ground water.
(vi) Any beneficial use of biosolids through
land application pursuant to the "Biosolids Regulation," Regulation 64
(5 CCR
1002-64), or the beneficial use of septage through
land application pursuant to 40 CFR 503.
(vii) Any facility operating under a permit
issued pursuant to the Underground Injection Control provisions of the Safe
Drinking Water Act, 42
U.S.C. 300f, et seq.
(viii) Any on-site wastewater treatment
system with a design capacity of 2,000 gallons per day or less, if designed and
constructed in accordance with requirements pursuant to the On-site Wastewater
Treatment Systems Act, section
25-10-101 C.R.S., et.
seq.
(ix) Any onsite landscape
irrigation system located on a domestic wastewater treatment plant site using
treated effluent that is applied at an agronomic rate.
(x) Any graywater treatment works with a
design capacity of 2,000 gallons per day or less, if designed and constructed
in accordance with Regulation 86 (5 CCR 1002-86).
(c) Any ground water permit
conditions, limitations, or control plans established by the Division pursuant
to these regulations shall only be subject to enforcement through the Colorado
Water Quality Control Act section
25-8-101, C.R.S. et seq.
61.14(2)
REGULATION BY
IMPLEMENTING AGENCIES
Consistent with section
25-8-202(7),
C.R.S. this section shall only apply to those activities that are not subject
to the jurisdiction of the following implementing agencies:
(a) The Division of Reclamation and Mining
Safety of the Department of Natural Resources.
(b) The State Engineer of the Department of
Natural Resources.
(c) The Oil and
Gas Conservation Commission of the Department of Natural Resources.
(d) The Hazardous Materials and Waste
Management Division of the Department of Public Health and
Environment.
(e) The Division of
Oil and Public Safety of the Department of Labor and Employment.
61.14(3)
IMPACTS FROM
SURFACE WATERS
The Division may assign permit limitations for any pollutants
discharged to surface waters which may be shown, based on available
information, to cause an exceedance of ground water standards or numerical
protection levels. In establishing such limitations the Division shall take
into account any attenuation in the concentration(s) of the pollutant(s) of
concern in the stream up to the point of compliance.
61.14(4)
POINT OF COMPLIANCE
Point(s) of compliance, where necessary to protect ground
water standards or numerical protection levels, will be established by the
Division in accordance with section 41.6 of the "Basic Standards for Ground
Water", Regulation 41 (5 CCR 1002-41), except as
provided below. For discharges to surface waters which are impacting ground
waters the point of compliance shall be set as follows:
(a) Where the zone of aquifer recharge occurs
prior to the site boundary, the point of compliance shall be set in accordance
with section 41.6(d)(1).
(b) Where
the zone of aquifer recharge occurs beyond the site boundary, the point of
compliance shall be set at the beginning of the zone of aquifer
recharge.
61.14(5)
VERIFICATION MONITORING
(a)
Pursuant to Section 61.8 the Division may, as a condition of the permit,
require the permittee to monitor at any point prior to the point of compliance
in order to provide an indication of concentrations of pollutants prior to
application to land, in the vadose zone, or in the ground water prior to their
reaching a point of compliance.
(b)
Detection wells or vadose zone monitoring may be required in order to establish
the quality of the effluent and ground water mix immediately downgradient of
the land application site or impoundment. Where a modeled attenuation of
pollutants in the vadose zone and/or in the ground water has been used as a
basis for determining that effluent limits will be met at the point of
compliance, the Division may require detection wells or other monitoring along
one or more lines parallel with the flow path in order to verify that the
predicted attenuation is taking place. Concentration values expected to occur
prior to application to the land, in the vadose zone, or at detection wells,
which are based on an expected level of treatment or a predicted attenuation,
will be referenced in the permit for use in determining the need to prepare and
implement a control plan as described in section 61.14(6).
61.14(6)
CONTROL PLAN
(a) The Division may, as a condition of a
permit, require the permittee to complete and submit a control plan if the
concentration of an effluent parameter at any verification monitoring point
exceeds;
(A) A value based on the predicted
attenuation at that point which was used to determine that an effluent
limitation could be met at the point of compliance, or
(B) The effluent limitation itself where the
effluent limit is established at a point other than the point of
compliance.
(b) The
control plan described in section 61.14 shall describe the action to be taken
by the permittee which will insure that the concentration of the pollutant(s)
of concern will not exceed the effluent limit(s) for the pollutant(s) at any
point of compliance. As part of the plan the permittee may show, through
additional monitoring or ground water quality modeling, that effluent
limitations will not be exceeded at the point of compliance. As a condition of
accepting the permittee's conclusions based on modeling or additional
monitoring the Division may require the permittee, through a schedule of
compliance, to install additional detection wells to verify the accuracy of the
conclusions stated in the control plan. Where additional monitoring or modeling
does not demonstrate that effluent limitations will be met at the point of
compliance, the control plan must include an analysis of viable alternatives
for elimination of the excess pollutant level(s) and selection of a preferred
alternative/The Division may require the permittee to implement the selected
alternative, or any other alternative if it find the selected alternative to be
inadequate, in the form of a schedule of compliance to be added in an amendment
to the permit. Implementation of a control plan does not abrogate the
requirement to comply with all effluent limits at any point of
compliance.
(c) A control plan will
not be required where the permittee can demonstrate that the elevated pollutant
concentrations are being caused by an off-site activity for which the permittee
has no responsibility.
61.14(7)
LAND DISPOSAL
(a) Discharges to land which qualify as land
disposal pursuant to section 61.2 are required to meet effluent limitations
determined in accordance with section 61.8 to be necessary for protection of
ground water standards, or numerical protection levels at any point(s) of
compliance.
(b) Effluent
limitations for land disposal systems shall, as a minimum, meet the applicable
limitations found in section 61.8(2) of this regulation.
61.14(8)
LAND TREATMENT
(a) Discharges to land which, pursuant to
section 61.2 meet the definition of land treatment are required to meet
effluent limitations at any point(s) of compliance determined in accordance
with Section 61.8 to be necessary for protection of ground water standards or
numerical protection levels.
(b)
Where effluent limits at a point of compliance are not required, due to a
determination by the Division that no impact to ground water inconsistent with
ground water standards or numerical protection levels is likely, the Division
may require reasonable monitoring and reporting to continue to verify that the
probability of impact to ground water is not significantly increasing due to
the possible addition of new pollutants or to higher loading rates.
61.14(9)
IMPOUNDMENTS
(a) The owner of any impoundment who can
demonstrate, using a method which has been approved by the Division, that the
seepage from the impoundment does not exceed 1 X
10-6 cm/sec ("Allowable Seepage") will be considered
not to have a discharge to waters of the state, by virtue of the insignificant
nature of the seepage, and a waiver of the requirement to obtain a permit will
be granted by the Division. In addition to demonstrating that the allowable
seepage will not be exceeded, the owner must also receive the Division's
concurrence, based on a review of the design, operating plan, and any other
available information, that the type of liner or other impermeable material
which is in place will maintain their integrity for the projected life of the
impoundment. Such Division determination shall take into consideration the
material(s) expected to be placed in the impoundment and other operation or
maintenance factors which may affect the permeability. If the Division
discovers that an incompatible material has been placed in the impoundment, or
that proper operation and maintenance procedures for the specific type of liner
or other impermeable material have not been followed, it may require a water
balance or other additional testing to demonstrate that the seepage rate does
not exceed the allowable seepage. Failure by the owner to conduct such testing
will be grounds for the Division to require a permit for the discharge from the
impoundment.
(b) Any owner of an
impoundment who fails to demonstrate that the seepage from the impoundment is
less than or equal to 1 X 10-6 cm/sec shall be
required to submit an application and obtain a permit as required in section
61.14(10) which follows.
(c) Where
effluent limits at a point of compliance are not required, due to a
determination by the Division that no impact to ground water inconsistent with
ground water standards or numerical protection levels is likely, the Division
may require reasonable monitoring and reporting to continue to verify that the
probability of impact to ground water is not significantly increasing due to
the possible addition of new pollutants or to higher loading rates.
61.14(10)
APPLICATION AND
OPERATION REQUIREMENTS
(a) The owner
of any land application system whose construction is commenced after July 1,
1993, is prohibited from applying any effluent to the land prior to obtaining
an effective discharge permit. The owner of any impoundment who construction is
commenced after July 1, 1993 and who has not received a waiver, pursuant to
section 61.14 , is prohibited from placing any material, other than raw or
potable water, in the impoundment prior to obtaining a discharge
permit.
(b) Consistent with section
61.4 , the owner of any existing land application system or impoundment which
has not received a waiver pursuant to section 61.14 must submit a permit
application to the Division within sixty days of being so notified. If the land
application system and/or impoundment is already described in the rationale for
CDPS permit, the information pertinent to the land application system and/or
impoundment is not required to be submitted until the application for renewal
of the CDPS is due. The owner of any other existing facility shall submit an
application within two years of July 1, 1993, whether notification has been
provided by the Division or not. The owner of any existing land application
system or existing impoundment may continue operation of those facilities
pending action on a permit application filed in conformance with the above
stated requirements.