Code of Colorado Regulations
1000 - Department of Public Health and Environment
1002 - Water Quality Control Commission (1002 Series)
5 CCR 1002-22 - REGULATION NO. 22 - SITE LOCATION AND DESIGN REGULATIONS FOR DOMESTIC WASTEWATER TREATMENT WORKS
Section 5 CCR 1002-22.11 - APPLICATION PROCEDURES FOR DEMONSTRATION PROJECTS
Current through Register Vol. 47, No. 17, September 10, 2024
(1) A domestic wastewater treatment works with a site location approval may submit a site location demonstration project application to temporarily modify their site location approval or conditional site location approval to evaluate process and technologies prior to permanently changing the treatment works. The application for a demonstration project at an approved site location shall be made to the Division on the proper form.
(2) Demonstration projects have a limited time period during which testing may be conducted. As a general rule, demonstration projects must be completed as expeditiously as practical and cannot extend beyond two years without receiving an extension from the Division. The Division may authorize the operation of demonstration equipment and processes beyond two years upon written request. The written request shall specify the reason(s) for the extension request, set forth a proposed schedule for completion of the demonstration project, and identify a specific date by which the demonstration project will conclude. For example, extension requests may be made for the following; awaiting a division decision of site location and design review applications, alternative technology application, or permit modification; construction of the permanent installation; or other circumstance that could not reasonably be foreseen at the time of the initial demonstration project approval.
(3) During the duration of the demonstration project, the domestic wastewater treatment works must comply with permit effluent limitations, conditions, and local, state, and federal requirements.
(4) A demonstration project may not:
(5) The design application process pursuant to Section 22.13 is not required for pilot projects.
(6) Posting of the site and agency notifications are not required for demonstration projects.