Code of Colorado Regulations
100 - Department of Personnel and Administration
101 - Division of Finance and Procurement
1 CCR 101-9 - PROCUREMENT RULES
Article 103 - SOURCE SELECTION AND CONTRACT FORMATION
Part 3 - CANCELLATION OF SOLICITATIONS: REJECTION OF BIDS OR PROPOSALS
Section R-24-103-301-03 - Waiver of Non-Material Mandatory Requirements in Solicitations
Universal Citation: 100 CO Code Regs R-24-103-301-03
Current through Register Vol. 47, No. 17, September 10, 2024
The procurement official has the authority to waive mandatory requirements in a solicitation in the event:
(a) The procurement official has determined that the requirements are not material;
(b) The solicitation discloses that the state has reserved this right;
(c) The mandatory requirements have not been met by any of the respondents to the solicitation;
(d) The waiver does not create a disadvantage to the state;
(e) The waiver does not benefit any individual bidder or offeror; and
(f) The waiver does not prejudice any non-winning bidder or offeror or potential bidder or offeror.
Disclaimer: These regulations may not be the most recent version. Colorado may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.