Current through Register 2024 Notice Reg. No. 38, September 20, 2024
(a) Cranes shall not be operated with wheels or tracks off the ground or working surface at any time unless properly bearing on outriggers or stabilizers. Power actuated jacks (outriggers or stabilizers), where used, shall be provided with means to prevent loss of support under load.
(b) Outriggers or stabilizers shall be used when the load to be handled at that particular radius exceeds the rated load without outriggers or stabilizers as given by the certified agent for that crane.
(c) The brakes shall be tested each time a load is 90% or more of the rated load as configured by raising the load a few inches and applying the brakes. In duty cycle and repetitive lifts where each lift is 90% or more of the rated load, this requirement applies to the first lift but not to successive lifts.
(d) The load or the boom shall not be lowered below the point where less than two full wraps of rope remain on grooved drums and three full wraps on ungrooved drums.
(e) When two or more cranes are used to lift one load, a qualified person, other than the operators, shall direct the operation. This person shall analyze the operation and instruct all personnel involved in the proper positioning, rigging of the load, and the movements to be made. A qualified person shall be in direct audible communication with both crane operators at all times to direct the lifting operation. Where two cranes or more are used to lift one load, the rating chart shall be reduced on each crane by not less than 25 percent, unless equalizer or other acceptable provisions assure safe distribution of both vertical and horizontal load to the cranes involved, in which case a lesser reduction may be applied.
(f) Multiple crane/derrick lifts -- Supplemental requirements.
1.
Amendment of subsection (a) filed 2-13-75; effective thirtieth day thereafter
(Register 75, No. 7).
2. Amendment filed 8-29-86; effective
thirtieth day thereafter (Register 86, No. 39).
3. New subsections
(b)(3)-(5) filed 1-29-2009; operative 2-28-2009 (Register 2009, No.
5).
4. Editorial correction of subsection (b)(3) (Register 2011, No.
8).
5. Amendment of subsections (a)-(b)(2) and (b)(2)(B), repealer
of subsection (b)(2)(C), amendment of subsection (b)(3), repealer and new
subsection (b)(4) and amendment of subsection (b)(5) filed 5-30-2013; operative
7-1-2013 (Register 2013, No. 22).
6. Amendment of subsections (b)(5)
and (c) and new subsections (f)-(f)(2)(B) filed 7-26-2022; operative 7-26-2022
pursuant to Government Code section
11343.4(b)(3)
(Register 2022, No. 30). Filing deadline specified in Government Code section
11349.3(a)
extended 60 calendar days pursuant to Executive Order N-40-20 and an additional
60 calendar days pursuant to Executive Order
N-71-20.
Note: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code.