ID | ELEMENT | CODES/CRITERIA | LENGTH | TYPE | INFORMATION DESCRIPTION | CERS MINIMALLY REQUIRED FIELDS |
1 | Facility ID Number | 13 | AN | A facility identifier assigned by the local regulator supporting cross-linking of CERS and local data system records. Because CUPAs do not consistently apply the original regulatory definition of this field (2 AN county 3 AN jurisdiction 6 AN facility number), CERS accepts any alphanumeric string up to 13 characters. The original regulator goals of this field are fulfilled through the CERS ID and CERS System Field "FacilityRegulatorKey" (20.0084). | False | |
1a | CERS ID | Cal/EPA assigned, 8- or 9- digit ID assigned to a specific facility that never has leading zeroes (begins at 10000001). Cal/EPA does not anticipate using 9- digit CERS IDs until the year 2020 or beyond. | 9 | N | A CERS ID is a Cal/EPA-assigned, 8- or 9- digit ID to uniquely identify a facility in CERS. The CERS ID should remain unchanged across different owners/operators of a facility. | False |
3 | Business Name | 70 | AN | Full legal name of business. | True | |
103 | Business Site Address | 70 | AN | Street address where facility is located. No post office box numbers are allowed. This information must provide a means to geographically locate the facility. The "Supplemental Location Text" field can also be used to capture additional information where the facility's formal address is unclear or not available. | True | |
104 | City (Business) | 60 | AN | City or locality name in which the facility/site is physically located. | True | |
490-3a | Monitoring | 01 = Annually | 2 | AN | Describes frequency of service performed | True |
Equipment Serviced | 99 = Other | on monitoring equipment. | ||||
490-3b | Specify Other Frequency of Monitoring Equipment Service | Narrative | 15 | AN | Describes other frequency of service performed on monitoring equipment. | False |
490-4 | Site Plot Plan Submitted | 1 = New Plan Submitted | 1 | AN | Indicates if a site plan is submitted with this plan or a previously submitted site plan is | True |
2 = Site Plan Previously Submitted | current for the facility. | |||||
490-5 | Continuous Electronic Tank | Y = Yes | 1 | AN | Indicates if continuous tank monitoring is used at the site. | False |
Monitoring | N = No | |||||
490-6 | Tank Secondary | 01 = Dry | 2 | AN | Description of Tank | False |
Containment | 02 = Liquid-Filled | secondary containment | ||||
System | 03 = Pressurized | system. | ||||
04 = Under Vacuum | ||||||
490-7 | Electronic Monitor Panel Manufacturer | 25 | AN | Name of the tank electronic monitor panel. | False | |
490-8 | Electronic Monitor Panel Model # | 35 | AN | Model number of electronic monitor panel. | False | |
490-9 | Leak Sensor Manufacturer | 20 | AN | Name of leak sensor manufacturer. | False | |
490-10 | Leak Sensor Model # | 35 | AN | Model number of leak sensor | False | |
490-11 | Automatic Tank Gauging | Y = Yes | 1 | AN | Indicates if this type of monitoring (automatic tank gauging) is being performed at the | False |
N = No | site. | |||||
490-12 | ATG Panel Manufacturer | 25 | AN | Name of ATG panel manufacturer | False | |
490-13 | ATG Model # | 35 | AN | Model of ATG panel | False | |
490-14 | In-Tank Probe Manufacturer | 25 | AN | Name of ATG in-tank probe manufacturer | False | |
490-15 | In-tank Probe Model # | 35 | AN | Model number of ATG in-tank probe. | False | |
490-16 | Tank Leak Test | 01 = Continuous | 2 | AN | Frequency of tank leak test. | False |
Frequency | 02 = Daily/Nightly | |||||
03 = Weekly | ||||||
04 = Monthly | ||||||
99 = Other | ||||||
490-17 | Other Leak Test Frequency | Narrative | 10 | AN | Other frequency of tank leak test. | False |
490-18 | Programmed | 01 = 0.1 GPH | 2 | AN | Sensitivity of the programmed leak tests. | False |
Tank Tests | 02 = 0.2 GPH | |||||
99 = Other | ||||||
490-19 | Other Programmed Tests | Narrative | 15 | AN | Other designated sensitivity of programmed leak test. | False |
490-20 | Monthly Statistical Inventory | Y = Yes | 1 | AN | Indicates if inventory reconciliation is being performed at the site. | False |
Reconciliation | N = No | |||||
490-21 | Weekly Manual Tank Gauge | Y = Yes | 1 | AN | Indicates if weekly manual tank gauging is being performed at this site. | False |
N = No | ||||||
490-22 | Tank Gauging | 01 = 36 Hours | 2 | AN | Length of time for manual tank gauging period. | False |
Test Period | 02 = 60 Hours | |||||
490-23 | Tank Integrity Testing | Y = Yes | 1 | AN | Indicates if tank integrity testing is performed at the site. | False |
N = No | ||||||
490-24 | Tank Integrity | 01 = Annually | 2 | AN | Frequency of tank integrity | False |
Testing | 02 = Biennially | testing. | ||||
Frequency | 99 = Other | |||||
490-25 | Specify Other Tank Integrity Testing Frequency | Narrative | 15 | AN | Frequency of other tank integrity testing. | False |
490-26 | Other Monitoring | Y = Yes | 1 | AN | Indicates if another type of monitoring is used at the site, not already indicated. | False |
N = No | ||||||
490-27 | Specify Other Monitoring | Narrative | 100 | AN | Specifies the other type of monitoring. | False |
490-28 | Continuous Monitoring of | Y = Yes | 1 | AN | Indicates if continuous monitoring of the piping secondary containment occurs at the site. | False |
Piping Secondary Containment | N = No | |||||
490-29 | Piping Secondary | 01 = Dry | 2 | AN | Type of piping secondary | False |
Containment | 02 = Liquid | containment. | ||||
03 = Pressurized | ||||||
04 = Under Vacuum | ||||||
490-30 | Panel Manufacturer | Narrative | 25 | AN | Name of panel manufacturer. | False |
490-31 | Panel Model # | 35 | AN | Model number of panel. | False | |
490-32 | Leak Sensor Manufacturer | Narrative | 25 | AN | Name of leak sensor manufacturer. | False |
490-33 | Leak Sensor Model | 35 | AN | Model of leak sensor. | False | |
490-34 | Leak Alarm Triggers | Y = Yes | 1 | AN | Indicates pump shutdown when a leak alarm occurs. | False |
Automatic Pump Shutdown | N = No | |||||
490-35 | Failure/Disconnect Triggers | Y = Yes | 1 | AN | Indicates pump shutdown when failure or disconnect occurs. | False |
Pump Shutdown | N = No | |||||
490-36 | Mechanical Line Leak Detector | Y = Yes | 1 | AN | Indicates that a 3 GPH line mechanical line leak detector is used at the site. | False |
Performs 3 GPH Leak Test | N = No | |||||
490-37 | MLLD Manufacturer | Narrative | 25 | AN | Name of leak detector manufacturer. | False |
490-38 | MLLD Model | 35 | AN | Model of leak detector. | False | |
490-39 | Electronic Line Leak Detector | Y = Yes | 1 | AN | Indicates that an electronic line leak detector (ELLD) is used at the site. | False |
Performs 3 GPH Leak Test | N = No | |||||
490-40 | ELLD Manufacturer | Narrative | 25 | AN | Manufacturer of electronic line leak detector (ELLD). | False |
490-41 | ELLD Model | 35 | AN | Model of electronic line leak detector (ELLD). | False | |
490-42 | ELLD | 01 = 0.2 GPH | 2 | AN | Type of electronic line leak | False |
Programmed In-Line Testing | 02 = 0.1 GPH | detector (ELLD) test performed. | ||||
490-43 | ELLD Triggers Automatic Pump | Y = Yes | 1 | AN | Indicates if electronic line leak detector (ELLD) triggers automatic pump shutdown. | False |
Shutdown | N = No | |||||
490-44 | ELLD Failure/Disconnect | Y = Yes | 1 | AN | Indicates if electronic line leak detector (ELLD) triggers auto-shutdown for failure or | False |
Triggers Automatic Shutdown | N = No | disconnection. | ||||
490-45 | Pipeline Integrity Testing | Y = Yes | 1 | AN | Indicates if pipeline integrity testing occurs at the site. | False |
N = No | ||||||
490-46 | Pipeline Integrity | 01 = Annually | 2 | AN | Frequency of pipeline integrity testing. | False |
Testing | 02 = Every 3 Years | |||||
Frequency | 03 = Other | |||||
490-47 | Specify Other Integrity Testing Frequency | 10 | AN | Other frequency of pipeline integrity testing. | False | |
490-48 | Visual Pipeline Monitoring | Y = Yes | 1 | AN | Indicates if visual pipeline monitoring occurs at the site. | False |
N = No | ||||||
490-49 | Visual Pipeline | 01 = Daily | 2 | AN | Frequency of visual pipeline | False |
Monitoring | 02 = Weekly | monitoring. | ||||
Frequency | 03 = Minimum Monthly | |||||
490-50 | Suction Piping Meets | Y = Yes | 1 | AN | Indicates if suction piping that meets the criteria is the method to monitor the pipeline. | False |
Exemption Criteria | N = No | |||||
490-51 | No Regulated Piping Per | Y = Yes | 1 | AN | Indicates that any piping connected to the tank system is not regulated under the UST law, or | False |
Health and Safety Code, Division 20, Chapter 6.7 Is Connected To The Tank System | N = No | there is no piping connected to the tank system. | ||||
490-52 | Other Pipeline Monitoring | Y = Yes | 1 | AN | Indicates if other pipeline monitoring option used at site. | False |
N = No | ||||||
490-53 | Specify Other Pipeline Monitoring | Narrative | 100 | AN | Identifies other monitoring option. | False |
490-54a | UDC | 1 = Continuous | 2 | AN | Indicates type of under dispenser containment | True |
Monitoring | 2 = Float and Chain Assembly | (UDC) monitoring. | ||||
3 = Electronic Standalone | ||||||
4 = No Dispensers | ||||||
99 = Other | ||||||
490-54b | Specify Other UDC Monitoring | Narrative | 15 | AN | Indicates type of other under dispenser containment (UDC) monitoring. | False |
490-55 | UDC Panel Manufacturer | Narrative | 25 | AN | Manufacturer of under dispenser containment (UDC) panel. | False |
490-56 | UDC Panel Model # | 35 | AN | Model # of under dispenser containment (UDC) panel. | False | |
490-57 | UDC Leak Sensor Manufacturer | Narrative | 20 | AN | Manufacturer of under dispenser containment (UDC) leak sensor. | False |
490-58 | UDC Leak Sensor Model | 35 | AN | Model # of under dispenser containment (UDC) leak sensor. | False | |
490-59 | Detection of a Leak into the | Y = Yes | 1 | AN | Indicates if alarms are triggered when a leak is detected in the under dispenser containment | False |
UDC Triggers Audible and Visual Alarms | N = No | (UDC). | ||||
490-60 | UDC Leak Alarm Triggers | Y = Yes | 1 | AN | Indicates if an under dispenser containment (UDC) leak alarm causes automatic pump | False |
Automatic Pump Shutdown | N = No | shutdown. | ||||
490-61 | Failure/Disconnection of UDC | Y = Yes | 1 | AN | Indicates if failure or disconnection of the under dispenser containment (UDC) monitoring | False |
Monitoring System Triggers Automatic Pump Shutdown | N = No | system causes pump shutdown. | ||||
490-62 | UDC Monitoring Stops Flow | Y = Yes | 1 | AN | Indicates if the under dispenser containment (UDC) monitor stops the flow of product at | False |
of Product at Dispenser | N = No | the dispenser. | ||||
490-63 | UDC | 1 = Single-walled | 1 | AN | Indicates the type of under | False |
Construction | 2 = Double-walled | dispenser containment (UDC) construction. | ||||
490-64a | UDC Secondary | 01 = Liquid | 2 | AN | Type of under dispenser | False |
Containment | 02 = Pressure | containment (UDC) | ||||
Monitoring | 03 = Vacuum | secondary containment monitoring. | ||||
490-64b | A Leak Within the Secondary | Y = Yes | 1 | AN | Indicates that a leak in the under dispenser containment (UDC) secondary containment | False |
Containment of UDC Causes Audible and Visual Alarms | N = No | causes audible and visual alarms. | ||||
490-65 | ELD Testing | Y = Yes | 1 | AN | Indicates if tanks are enhanced leak detection (ELD) tested on a periodic basis. | False |
N = No | ||||||
490-66 | Secondary Containment | Y = Yes | 1 | AN | Indicates if secondary containment testing is conducted every 36 months. | False |
Testing | N = No | |||||
490-67 | Spill Bucket Testing | Y = Yes | 1 | AN | Indicates if spill bucket testing is conducted annually. | False |
N = No | ||||||
490-68a | Alarm Logs | Y = Yes | 1 | AN | Indicates that alarm log records are kept for the facility. | False |
N = No | ||||||
490-68b | Visual Inspection Records | Y = Yes | 1 | AN | Indicates that visual inspection records are kept for the facility. | False |
N = No | ||||||
490-68c | Tank Integrity Testing Results | Y = Yes | 1 | AN | Indicates that tank integrity testing results are kept for the facility. | False |
N = No | ||||||
490-68d | SIR Testing Results | Y = Yes | 1 | AN | Indicates that statistical inventory reconciliation (SIR) testing results and supporting | False |
N = No | documentation records are kept for the facility. | |||||
490-68e | Tank Gauging Results | Y = Yes | 1 | AN | Indicates that tank gauging results and supporting documentation records are kept for the | False |
N = No | facility. | |||||
490-68f | ATG Testing Results | Y = Yes | 1 | AN | Indicates that ATG testing results and supporting documentation records are kept for the | False |
N = No | facility. | |||||
490-68g | Corrosion Protection Logs | Y = Yes | 1 | AN | Indicates that corrosion protection logs are kept for the facility. | False |
N = No | ||||||
490-68h | Equipment Maintenance and | Y = Yes | 1 | AN | Indicates that equipment maintenance and calibration records are kept for the facility. | False |
Calibration Records | N = No | |||||
490-69a | Personnel with UST Monitoring | Y = Yes | 1 | AN | Indicates that personnel within the facility are familiar with the indicated documents. | False |
Responsibilities are Familiar with Training Documents | N = No | |||||
490-69b | UST Monitoring Plan | Y = Yes | 1 | AN | Indicates that facility personnel are familiar with the UST monitoring plan for the facility. | False |
N = No | ||||||
490-69c | Operating Manuals | Y = Yes | 1 | AN | Indicates that facility personnel are familiar with the UST operating manuals for the facility. | False |
N = No | ||||||
490-69d | CA UST Regulations | Y = Yes | 1 | AN | Indicates that facility personnel are familiar with the California UST regulations. | False |
N = No | ||||||
490-69e | CA UST Law | Y = Yes | 1 | AN | Indicates that facility personnel are familiar with the California UST law. | False |
N = No | ||||||
490-69f | SWRCB Handbook for Tank | Y = Yes | 1 | AN | Indicates that facility personnel are familiar with the SWRCB Handbook for Tank Owners - | False |
Owners - Manual and SIR | N = No | Manual and SIR. | ||||
490-69g | SWRCB Publication: | Y = Yes | 1 | AN | Indicates that facility personnel are familiar with the SWRCB Publication: Understanding | False |
Understanding Automatic Tank Gauging Systems | N = No | Automatic Tank Gauging Systems. | ||||
490-69h | Other Training Documents | Y = Yes | 1 | AN | Indicates that other training documents are used. | False |
N = No | ||||||
490-69i | Specify Other Training Documents | Narrative | 100 | AN | List of the other training documents that are used. | False |
490-70 | Designated Operator Training | Y = Yes | 1 | AN | Indicates that the facility has a designated operator and that training will be provided. | False |
N = No | ||||||
490-71 | Comments and Additional Information | Narrative | 300 | AN | Additional information to support the application for an operating permit. | False |
490-72 | Name of First Person Having Responsibility | 80 | AN | Name of first person having responsibility for monitoring. | True | |
490-73 | Title of First Person Having Responsibility | 50 | AN | Title of first person having responsibility for monitoring. | True | |
490-74 | Name of Second Person Having Responsibility | 80 | AN | Name of second person having responsibility for monitoring. | False | |
490-75 | Title of Second Person Having Responsibility | 50 | AN | Title of second person having responsibility for monitoring. | False | |
490-76 | Signature Representation | 01 = Tank Owner/Operator | 2 | AN | Indicates who signed the monitoring plan. | False |
02 = Facility Owner/Operator | ||||||
03 = Authorized Representative of Owner | ||||||
490-77 | Signature Date | YYYY-MM-DD | 10 | D | Date monitoring plan is certified. | False |
490-78 | Applicant Name | 80 | AN | Name of applicant signing monitoring plan. | False | |
490-79 | Applicant Title | 50 | AN | Title of applicant signing monitoring plan. | False |
1. New form filed 12-18-2007; operative 1-17-2008 (Register 2007, No. 51).
2. Amendment filed 12-17-2013; operative 12-17-2013 pursuant to Government Code section 11343.4(b)(3) (Register 2013, No. 51).
Disclaimer: These regulations may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.