(a) Permittee shall notify the Department at least seven (7) calendar days prior to starting work within the Department's right-of-way as prescribed in the fully executed encroachment permit.

(b) A construction schedule outlining the anticipated duration of the construction shall be submitted to the Department for review and approval at least seven (7) calendar days prior to start of construction.

(c) Prior to construction, the condition of the Department's roads, fences, and Department land areas adjacent to the proposed project area shall be jointly inspected and documented by the permittee and Department personnel. Upon completion of the proposed construction activities, the condition of these features shall be jointly re-inspected. The permittee shall be liable for all costs associated with restoring these features to pre-construction conditions.

1. New section filed 4-22-2015; operative 7-1-2015 (Register 2015, No. 17).

Note: Authority cited: Section 12899.9, Water Code. Reference: Sections 12899.1(c), 12899.2(b), 12899.2(e) and 12899.7, Water Code.

Disclaimer: These regulations may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.