Current through Register 2024 Notice Reg. No. 52, December 27, 2024
(a)
The following definitions apply to this section:
(1) Delta Lowlands. "Delta Lowlands" means
those lands within the Sacramento-San Joaquin Delta that are approximately at
the five- (5) foot contour and below as shown in Figure 8.04.
(2) Delta Uplands. "Delta Uplands" means
those lands within the Sacramento-San Joaquin Delta that are above the five-
(5) foot contour as shown in Figure 8.04.
(b) Pipelines, conduits, utility lines, and
appurtenant structures must conform to the following criteria:
(1) Pipelines, conduits, utility lines,
utility poles, and appurtenant structures may not be installed within the levee
section, within ten (10) feet of levee toes, or within the floodway during the
flood season unless authorized by the General Manager based on reservoir
levels, stream levels, and forecasted weather conditions on a case-by-case
basis, pursuant to section
11.
(2) Appurtenant structures such as
standpipes, utility poles, distribution boxes, guy wires, and anchors, but not
including siphon breakers, are generally not permitted in or below the levee
crown, on the levee slopes, or within ten (10) feet of the levee toes.
Appurtenant structures may be permitted where they will not interfere with
levee maintenance or flood fight activities.
(3) Appropriate, visible markers acceptable
to the local maintaining agency may be required to identify the location of
buried pipelines, conduits, and utility lines. A siphon breaker or other
visible appurtenance may be considered an acceptable marker for the attached
buried line. Markers must be made of durable, long lasting, fire-resistant
material, and must be maintained by the permittee until the pipeline, conduit
or utility line is properly abandoned.
(4) Pipelines, conduits, and utility lines
that pose a threat or danger to levee maintenance or flood fight activities,
such as high-voltage lines, gas lines, and high pressure fluid lines, must be
distinctively labeled to identify the contents.
(5) Buried high-voltage lines of greater than
twenty-four (24) volts are required to be protected with schedule 40 PVC
conduit, or equivalent.
(6)
Overhead electrical and communication lines must have a minimum vertical
clearance above the levee crown and access ramps of twenty-one (21) feet for
lines carrying 750 volts or less, and twenty-five (25) feet for lines carrying
higher voltage.
(7) Fluid- or
gas-carrying pipelines installed parallel to a levee must be a minimum distance
of ten (10) feet from the levee toe and, where practical, may not encroach into
the projected levee slope.
(8)
Low-voltage electrical or communication lines of twenty-four (24) volts or less
may be installed parallel to a levee and within ten (10) feet of the levee toe
when it is demonstrated to be necessary and to not interfere with the integrity
of levee, levee maintenance, inspection, or flood fight procedures.
(9) The board may require the applicant to
have any pipelines, conduits, utility lines and appurtenant structures designed
by a registered civil engineer.
(c) Pipelines, conduits, and utility lines
installed within the floodway must conform to the following additional
conditions:
(1) Pipelines, conduits, and
utility lines installed within the floodway must have a minimum cover of five
(5) feet beneath the low-water channel, and a minimum of two (2) feet in the
remaining area of the floodway. A greater depth of cover may be required based
upon the feasibility of achieving the required cover or local soil stability
and channel hydraulics.
(2)
Open-trench backfill to cover pipes must be placed in a manner consistent with
floodway characteristics such as erosion, deposition, and streamflow
velocities. This requirement is generally ensured by using suitable material
and compacting to the density of adjacent undisturbed material. Compaction
tests by a certified soils laboratory may be required.
(3) In general, any standard material may be
used for pipelines or conduits to be installed within the floodway ten (10)
feet or more from the levee toe or the projected levee slope.
(4) All debris that accumulates around
utility poles and guy wires within the floodway must be completely removed
following the flood season and immediately after major accumulations.
(5) Pipelines and conduits which are open to
the waterway and which could cause flood damage from uncontrolled backflow
during the design flood event shall have a readily accessible positive closure
device. A flap gate is not a positive closure device.
(d) Pipelines, conduits, and utility lines
installed through a levee must conform to the following additional conditions:
(1) The installation of a fluid- or gas-
carrying pipeline in a levee section or within ten (10) feet of the toe
parallel to the centerline is not permitted.
(2) Pipelines, conduits, and utility lines
must be installed through a levee as nearly at a right angle to the levee
centerline as practical.
(3) Buried
pipelines, conduits, and utility lines that do not surface near the levee toes
must have location markers near both levee toes.
(4) Buried pipelines, conduits, and utility
lines that cross the levee at right angles must have a location marker located
on the levee slope adjacent to either shoulder.
(5) Buried pipelines, conduits, and utility
lines that cross the levee at other than right angles must have location
markers on the levee slopes adjacent to each shoulder.
(6) Pipelines carrying gas or fluids under
pressure must be confirmed free of leaks during construction by pressure tests,
X-ray, or equivalent methods, and must be tested anytime after construction
upon request of the board.
(7)
Pipelines carrying gas or fluids under pressure must have a readily accessible
rapid closure device located within ten (10) feet of the landside levee
toe.
(8) Pipelines and conduits
open to the waterway must have a readily accessible positive closure device
unless it can be demonstrated it is not necessary. A flap gate is not a
positive closure device.
(9) The
side slopes of trenches excavated for the installation of pipelines, conduit,
or utility lines may be no steeper than one (1) foot horizontal to one (1) foot
vertical. The following are exceptions to this maximum slope requirement:
(A) For shallow installations above the flood
plane, e.g., twelve (12) inches, vertical side slopes may be allowed.
(B) For that portion of the trench above the
design freeboard, vertical side slopes may be allowed.
(10) The bottom width of trenches excavated
for the installation of a pipeline, conduit, or utility line must be two (2)
feet wider than the diameter of the pipeline or conduit, or two (2) times the
pipe diameter, whichever is greater.
(11) The minimum cover for pipelines,
conduits, and utility lines installed through the levee crown is twenty-four
(24) inches. If it becomes necessary to raise a levee crown to provide minimum
cover, the longitudinal slope of the crown must be a minimum of ten (10) feet
horizontal to one (1) foot vertical. Where twenty-four (24) inches of cover is
not practical, a concrete or other engineered cover is required.
(12) The minimum cover for pipelines,
conduits, and utility lines installed within the levee slope is twelve (12)
inches. Where the installation will not interfere with levee maintenance or
flood fight activities, it may not be necessary to bury the line within the
levee slopes.
(13) When practical,
pipelines, conduits, and utility lines installed within a levee section must be
separated from parallel pipelines, conduits, and utility lines by a minimum of
twelve (12) inches, or the diameter of the largest pipeline, conduit, or
utility line, whichever is larger, to a maximum of thirty-six (36)
inches.
(14) When practical,
pipelines, conduits, and utility lines must have a minimum vertical spacing of
six (6) inches when crossing other pipelines, conduits, or utility
lines.
(15) A siphon breaker with a
protective housing may be required and must be installed off the levee crown
roadway where it will not interfere with levee maintenance.
(16) Electrical and communication lines
installed through a levee or within ten (10) feet of a levee toe must be
encased in schedule 40 PVC conduit or equivalent. Low-voltage lines (24 volts
or less) and fiber optic cable may be allowed without conduit if properly
labeled.
(17) A standard reinforced
concrete U-wall for levee erosion protection is required at the outlet end of a
pipeline or conduit discharging within ten (10) feet of a levee toe. See
Figures 8.05 and 8.06 for U-Wall design criteria.
(18) Existing levee erosion protection must
be restored by the permittee if it is damaged during the installation of a
pipeline, conduit, or utility line.
(19) The permittee must replant or reseed
levee slopes to restore sod, grasses or other nonwoody ground covers that are
destroyed or damaged during the installation of a pipeline, conduit, or utility
line.
(20) Within the levee or
within ten (10) feet of levee toes, any excavation for the installation of a
pipeline, conduit, or utility line must be backfilled in four (4) to six- (6)
inch layers with approved material and compacted to a relative compaction of
not less than ninety (90) percent, per ASTM D1557- 91, dated 1991, which is
incorporated by reference and above optimum moisture content or ninety-seven
(97) percent, per ASTM D698-91, dated 1991, which is incorporated by reference
and at or above optimum moisture content. Compaction tests by a certified soils
laboratory will be required to verify compaction of backfill within a
levee.
(21) Boring a pipeline or
conduit through a levee is permitted if the following additional conditions are
met:
(A) The invert of the pipeline or
conduit must be located at least three (3) feet above the design flood
plane.
(B) The pipeline or conduit
must be butt-welded. Polyethylene pipes may be used as provided in subdivisions
(f)(4)(A), (f)(4)(B), and (f)(4)(C) of this section.
(C) The pipeline or conduit must be installed
by the bentonite boring method or equivalent. The bentonite boring method uses
an auger followed by a pipe with multiple port openings through which a
bentonite slurry is pumped to ensure sealing of any voids resulting from the
boring process.
(e) Pipelines, conduits, and utility lines
may be installed by the open cut-method through a levee below the design flood
plane, or within the levee foundation under the following conditions:
(1) One or more of the following conditions
must apply:
(A) The pipeline, conduit, or
utility line will be maintained by a public agency with a history of good
maintenance based upon annual maintenance or inspection reports.
(B) The levee is designed to withstand a
depth of less than six (6) feet of water measured with respect to the elevation
of the landside levee toe.
(C) The
levee is designed to withstand a depth of less than twelve (12) feet of water
measured with respect to the elevation of the landside levee toe and provides
flood protection for a rural area, or an area where the board anticipates
little future urban development.
(2) Pipelines open to the waterway must be a
minimum of thirty (30) inches in diameter, and must have a readily accessible
positive closure device installed on the waterward side.
(3) Seepage along pipelines, conduits, and
utility lines must be prevented by either of the following methods:
(A) The pipeline, conduit, or utility line is
encased in reinforced concrete cast against firm undisturbed earth.
(B) The conduit has reinforced concrete
battered walls at an inclination of one (1) foot horizontal to four (4) feet
vertical or flatter.
(4)
The work must commence and be completed prior to the flood season.
(5) Levees located within the Sacramento-San
Joaquin Delta lowlands may only be cut below the design flood plane after
appropriate engineering studies are performed and approved.
(f) Pipelines, conduits, and utility lines
may be installed under a levee or stream channel by tunneling, jacking, or
boring, if the following conditions are met:
(1) The pipeline, conduit, or utility line is
at least thirty (30) feet under the levee.
(2) The pipeline, conduit, or utility line is
verified to have the required cover. A greater depth of cover may be required
based upon the feasibility of achieving the required cover or on local soil
stability and channel hydraulics.
(3) If the installation is to be more than
fifty (50) feet below the levee and the entire floodway and streambed, the
board may waive the requirement for a permit provided a letter of intent is
filed with the board prior to commencement of the project.
(4) The portal and outlet of a tunnel,
jacking, or boring must be a minimum distance of ten (10) feet beyond the
projected levee slope without an approved stability and seepage
analysis.
(5) Installation may
occur during the flood season and when the water surface elevation in the
floodway is expected to be above the elevation of the landside levee toe if
adequate containment cells are constructed at the portal and outlet.
(6) The installation of a pipeline, conduit,
or utility line under levees in the Sacramento-San Joaquin Delta lowlands
requires adequate containment cells at the portal and outlet when the
installation is less than fifty (50) feet below the streambed and levee
toes.
(7) Pipelines carrying gas or
fluids under pressure below a levee must have provision for rapid
closure.
(8) Pipelines and conduits
open to the waterway and below a levee must have a positive closure device
which is accessible at all times unless it is demonstrated to be unnecessary. A
flap gate is not a positive closure device.
(g) The following pipe materials are allowed
within a levee section when designed to resist all anticipated loading
conditions and properly installed:
(1)
Galvanized iron pipe is allowed if all joints are threaded. Galvanized iron
pipe joints must be corrosion protected with PVC tape or polyethylene tape
wrapped to a thickness of thirty (30) mils or equivalent.
(2) Schedule 80 polyvinyl chloride (PVC) pipe
is allowed if it is entirely buried, all joints are threaded and the components
were continually protected from ultraviolet radiation damage or were newly
manufactured.
(3) Polyvinyl
chloride (PVC) plastic pipe schedule 40, or better, may be used as a conduit
for power or communication cables.
(4) High-density polyethylene pipe may be
used for pipeline or conduit installations provided the following conditions
are met:
(A) High-density polyethylene
pipeline or conduit joints must be heat or electrofusion welded (ASTM Standard
F1055-93, dated 1993 or D3261-93, dated 1993 which is incorporated by
reference).
(B) High-density
polyethylene pipelines and conduits must be designed to resist all anticipated
loading conditions, and the design calculations must be submitted to the
board.
(C) High-density
polyethylene pipelines and conduits must be ultraviolet radiation
protected.
(5)
Cast-in-place reinforced concrete pipes and box culverts may be used above and
below the design flood plane if the concrete is at least six (6) inches
thick.
(6) Precast reinforced
concrete pipes and box culverts and concrete cylinder pipes may be used above
and below the design flood plane if the following conditions are met:
(A) Precast reinforced concrete pipe meets
ASTM Specification C76-90, dated 1990 which is incorporated by
reference.
(B) Precast reinforced
concrete pipe joints and precast box culvert joints are encased in reinforced
concrete cast-in-place against firm undisturbed earth.
(C) The cylinders of concrete cylinder pipes
are welded and corrosion protected internally and externally.
(D) When installed below the design flood
plane, precast reinforced concrete pipe and concrete cylinder pipe must be
encased below the springline in concrete cast against undisturbed
earth.
(7) Steel pipe may
be used for all types of pipeline or conduit installations through a levee
above the design flood plane if the pipe meets the following requirements:
(A) The steel pipe is resilient and not
materially reduced in quality due to weathering, prior use or other
deteriorating conditions.
(B) The
steel pipe joints are butt-welded or threaded.
(C) The steel pipe installations are
corrosion-proofed externally with a coating of material such as coal-tar
enamel, asphalt-dipped wrap, mortar, PVC tape, or polyethylene tape wrapped to
a thickness of thirty (30) mils, high solids epoxy, or equivalent.
(D) Unless a continuous internal lining of
cement, mortar, or equivalent is provided, as appropriate for the fluid to be
conveyed, new steel pipe installations may convey only non- corrosive material,
and water is considered corrosive.
(E) Steel pipe installations must be designed
to resist all anticipated loading conditions, and the design calculations must
be submitted to the board. Steel pipe meeting the following criteria may be
used without submittal of design calculations to the board:
(i) Twelve- (12) inches in diameter or less
ten- (10) gauge steel pipe.
(ii)
Greater than twelve- (12) inches and a maximum of thirty- (30) inches in
diameter seven- (7) gauge steel pipe.
(iii) Greater than thirty- (30) inches and a
maximum of forty-eight (48) inches in diameter three- (3) gauge steel
pipe.
(h) The following materials are not allowed
for pipelines or conduits used to carry natural gas or fluids:
(1) Aluminum pipe within a levee section or
within ten (10) feet of levee toes.
(2) Cast iron pipe within a levee section or
within ten (10) feet of levee toes.
(3) Pipe with flanges, flexible couplings, or
other mechanical couplings within a levee section or within ten (10) feet of
levee toes.
(4) Prestressed
concrete pipe within a levee section or within ten (10) feet of levee
toes.
1. New
section and figures 8.04, 8.05 and 8.06 filed 9-30-96; operative 10-30-96
(Register 96, No. 40).
Note: Authority cited: Section
8571, Water
Code. Reference: Sections
8608,
8710 and
8712, Water
Code.