California Code of Regulations
Title 22 - Social Security
Division 4 - Environmental Health
Chapter 17.5 - Lead and Copper
Article 8 - Lead Service Line Requirements for Action Level Exceedances
Section 64688 - Lead Service Line Replacement
Current through Register 2024 Notice Reg. No. 38, September 20, 2024
(a) A system shall replace lead service lines if:
(b) Within 6 months after it has a lead action level exceedance, the system shall demonstrate in writing that it has conducted a materials evaluation including that in section 64676 (Sample Site Selection) to identify the initial number of lead service lines in its distribution system, and shall submit both the demonstration and a schedule for complying with subsection (c) to the Department.
(c) Except as provided in subsection (e), a system that is required to conduct lead service line replacement shall annually replace at least 7 percent of the initial number of lead service lines in its distribution system, pursuant to the following.
(d) Within 12 months after the lead action level exceedance, and every 12 months thereafter, the system shall submit in writing to the Department the number of lead service lines scheduled to be replaced during the previous year of the system's replacement schedule, along with the following information to the Department:
(e) A system shall replace lead service lines at a faster rate than that required by subsection (b), taking into account the number of lead service lines in the system, if the Department determines either that this is necessary based on elevated blood lead levels in the population served, or that it is feasible to complete the lead service line replacement program in a shorter time without increasing the water rates to the customers.
(f) A system may cease replacing lead service lines when it has two consecutive periods without a lead action level exceedance. If the system has a lead action level exceedance during any subsequent period, it shall recommence replacing lead service lines.
1. New
section filed 12-11-95 as an emergency; operative 12-11-95 (Register 95, No.
50). A Certificate of Compliance must be transmitted to OAL by 4-9-96 or
emergency language will be repealed by operation of law on the following
day.
2. Refiling of 12-11-95 order, including amendment of NOTE,
filed 4-9-96 as an emergency; operative 4-10-96 (Register 96, No. 15). A
Certificate of Compliance must be transmitted to OAL by 8-8-96 or emergency
language will be repealed by operation of law on the following
day.
3. Certificate of Compliance as to 12-11-95 order, including
amendment of subsections (c)(1)-(2) and (c)(4), transmitted to OAL 8-7-96 and
filed 9-16-96 (Register 96, No. 38).
4. Repealer of former article 8
(sections 64689-64690), new article 8 (sections 64688-64689) and repealer and
new section filed 9-11-2003; operative 10-11-2003 (Register 2003, No.
37).
Note: Authority cited: Sections 100275, 116350, 116365, 116375 and 116385, Health and Safety Code. Reference: Sections 116325- 116750, Health and Safety Code.