Section 2031 - Construction Deadline

Universal Citation: 20 CA Code of Regs 2031

Current through Register 2024 Notice Reg. No. 38, September 20, 2024

(a) The deadline for the commencement of substantial construction of the project shall be 12 months after the effective date of the decision on an application accepted and processed pursuant to this Article.

(b) Substantial construction shall be defined as the following:

(1) completion of at least thirty percent of the engineering design of the entire project and

(2) completion of at least five percent of the physical construction of the entire project, absent circumstances beyond the control of the applicant.

1. New section filed 11-27-2000 as an emergency; operative 11-27-2000 (Register 2000, No. 48). A Certificate of Compliance must be transmitted to OAL by 3-27-2001 or emergency language will be repealed by operation of law on the following day.
2. Certificate of Compliance as to 11-27-2000 order transmitted to OAL 3-21-2001 and filed 4-25-2001 (Register 2001, No. 17).

Note: Authority cited: Sections 25213 and 25218(e), Public Resources Code. Reference: Sections 25216.5(a), 25523(a), 25550 and 25550(f), Public Resources Code.

Disclaimer: These regulations may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.