California Code of Regulations
Title 20 - Public Utilities and Energy
Division 2 - State Energy Resources Conservation and Development Commission
Chapter 5 - Power Plant Site Certification
Article 7 - Additional Provisions for Considering Expedited Applications Under Public Resources Code Section 25550
Section 2029 - Hearings
Current through Register 2024 Notice Reg. No. 38, September 20, 2024
(a) Within 135 days after acceptance of the application, the committee shall commence evidentiary hearings.
(b) Any party may submit testimony in accordance with a schedule determined by the committee.
1. New
section filed 11-27-2000 as an emergency; operative 11-27-2000 (Register 2000,
No. 48). A Certificate of Compliance must be transmitted to OAL by 3-27-2001 or
emergency language will be repealed by operation of law on the following
day.
2. Certificate of Compliance as to 11-27-2000 order transmitted
to OAL 3-21-2001 and filed 4-25-2001 (Register 2001, No.
17).
Note: Authority cited: Sections 25213 and 25218(e), Public Resources Code. Reference: Sections 25216.5(a), 25521 and 25550, Public Resources Code.