Article 7 - Requirements for New or Replacement Pipeline near Environmentally and Ecologically Sensitive Areas in the Coastal Zone; Plan to Retrofit Existing Pipelines; Notification to State Fire Marshal of New Construction or Retrofit of Pipeline; Consultation with Office of Spill Prevention and Response
Section 2112 - State Fire Marshal Risk Analysis Assessment
Current through Register 2024 Notice Reg. No. 38, September 20, 2024
(a) Timeframes
(b) Determination of Adequacy
(c) The State Fire Marshal may conduct on-site inspections to determine the adequacy of the risk analysis.
(d) The operator shall be notified when a risk analysis and plan is accepted as adequate. A Letter of Acceptance will be issued by the State Fire Marshal and will describe the conditions of acceptance, if any. The risk analysis will not be considered adequate until the operator is notified by a Letter of Acceptance from the State Fire Marshal.
(e) The State Fire Marshal shall commence enforcement consistent with the timing for compliance requirements found in Section 2108 of this Article.
(f) Operators must receive a written Letter of Acceptance of the risk analysis to implement the use of best available technology prior to commencing construction consistent with the requirements of Section 2114 (Notice of Any New Construction or Retrofit).
1. New section filed 8-31-2020; operative 10-1-2020 (Register 2020, No. 36).
Note: Authority cited: Sections 51010, 51013.1, 51013.5 and 51015, Government Code; and Sections 60104 and 60105, Title 49 of the United States Code. Reference: Sections 51010, 51010.5, 51013, 51013.1, 51013.5, 51015, 51015.4 and 51016, Government Code; and Sections 60104 and 60105, Title 49 of the United States Code.