Each operator of an Inert Debris Type A Disposal Facility that is required to obtain a Registration Permit pursuant to Title 14 CCR, section 14 CCR, section 17388.4 shall, at the time of application, file a Disposal Facility Plan with the EA. In order to maintain the permit, the operator must file amendments as necessary to maintain the accuracy of the Plan. Such amendments, or lack thereof, may become the basis for changes in the permit or for revocation of the permit. A Disposal Facility Plan shall contain the following:

(a) Name(s) of the operator, owner, and the company they represent, if applicable;

(b) Scaled schematic drawing of the building and other structures showing layout and general dimensions of the operations area, including but not limited to, unloading, storage, loading, and parking areas;

(c) Descriptive statement of the manner in which activities are to be conducted at the facility;

(d) Days and hours of operation. If the hours of waste receipt differ from the hours of material processing, each schedule may be stated. For facilities with continuous operations, indicate the start of the operating day for the purpose of calculating the amount of waste received per operating day. The operator may also indicate whether or not, and when, other activities such as routine maintenance will take place, if those activities will occur at times other than those indicated above;

(e) Total acreage contained within the operating or disposal areas;

(f) Facility design capacity, including the assumptions, methods, and calculations performed to determine the total capacity;

(g) Information indicating the types and daily quantities of waste or debris to be received. If tonnage is determined from records of cubic yardage, include the conversion factor used in the calculation;

(h) Description of methods used by the facility to comply with each State Minimum Standard;

(i) Anticipated volume of quench or process water and the planned method of treatment and disposal of any wastewater;

(j) Description of provisions to handle unusual peak loading;

(k) Description of transfer, recovery and processing equipment, including classification, capacity and the number of units.

(l) Planned method for final disposal of the solid waste;

(m) Planned method for the storage and removal of salvaged material.

(o) Resume of management organization that will operate the facility.

(p) A description of road building and seasonal tipping pad design.

(q) A description of a program to prevent the acceptance of unapproved materials and hazardous wastes.

(r) A description of the planned method for storage and removal of prohibited wastes.

(s) A copy of the operator's Injury and Illness Prevention Plan (as applicable under current law).

1. New section filed 12-26-2003; operative 2-24-2004 (Register 2003, No. 52).
2. Editorial correction of HISTORY 1 (Register 2004, No. 2).

Note: Authority cited: Sections 40502, 43020, 43021 and 48007.5, Public Resources Code. Reference: Sections 40053, 43020, 43021 and 48007.5, Public Resources Code.

Disclaimer: These regulations may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.