Current through Register 2024 Notice Reg. No. 38, September 20, 2024
(a) A few statutes or ordinances require agencies to make decisions on permits within time limits that are so short that review of the project under CEQA would be difficult. To enable the lead agency to comply with both the permit statute and CEQA, the lead agency shall deem an application for a project not received for filing under the permit statute or ordinance until such time as progress toward completing the environmental documentation required by CEQA is sufficient to enable the lead agency to finish the CEQA process within the short permit time limit. This section will apply where all of the following conditions are met:
(b) Examples of time periods subject to this section include but are not limited to:
(c) In any case described in this section, the environmental document shall be completed or certified and the decision on the project shall be made within the period established under the Permit Streamlining Act (Government Code Sections 65920, et seq.).
1. Repealer of subsection (b)(1), subsection renumbering, amendment of subsection (c) and amendment of NOTE filed 10-26-98; operative 10-26-98 pursuant to Public Resources Code section 21087 (Register 98, No. 44).
2. Change without regulatory effect amending NOTE filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).
Note: Authority cited: Section 21083, Public Resources Code. Reference: Sections 21100.2 and 21151.5, Public Resources Code; N.R.D.C. v. Arcata National Corp. (1976) 59 Cal. App. 3d 959.