(a) A lead agency is required to recirculate an EIR when significant new information is added to the EIR after public notice is given of the availability of the draft EIR for public review under Section 15087 but before certification. As used in this section, the term "information" can include changes in the project or environmental setting as well as additional data or other information. New information added to an EIR is not "significant" unless the EIR is changed in a way that deprives the public of a meaningful opportunity to comment upon a substantial adverse environmental effect of the project or a feasible way to mitigate or avoid such an effect (including a feasible project alternative) that the project's proponents have declined to implement. "Significant new information" requiring recirculation include, for example, a disclosure showing that:
(b) Recirculation is not required where the new information added to the EIR merely clarifies or amplifies or makes insignificant modifications in an adequate EIR.
(c) If the revision is limited to a few chapters or portions of the EIR, the lead agency need only recirculate the chapters or portions that have been modified.
(d) Recirculation of an EIR requires notice pursuant to Section 15087, and consultation pursuant to Section 15086.
(e) A decision not to recirculate an EIR must be supported by substantial evidence in the administrative record.
(f) The lead agency shall evaluate and respond to comments as provided in Section 15088. Recirculating an EIR can result in the lead agency receiving more than one set of comments from reviewers. The following are two ways in which the lead agency may identify the set of comments to which it will respond. This dual approach avoids confusion over whether the lead agency must respond to comments which are duplicates or which are no longer pertinent due to revisions to the EIR. In no case shall the lead agency fail to respond to pertinent comments on significant environmental issues.
(g) When recirculating a revised EIR, either in whole or in part, the lead agency shall, in the revised EIR or by an attachment to the revised EIR, summarize the revisions made to the previously circulated draft EIR.
1. New section filed 8-19-94; operative 9-19-94 (Register 94, No. 33).
2. New subsections (f)-(g) filed 10-26-98; operative 10-26-98 pursuant to Public Resources Code section 21087 (Register 98, No. 44).
3. Amendment of subsections (f)-(f)(2) and new subsection (f)(3) filed 9-7-2004; operative 9-7-2004 pursuant to Public Resources Code section 21083(e) (Register 2004, No. 37).
4. Change without regulatory effect amending NOTE filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).
Note: Authority cited: Section 21083, Public Resources Code. Reference: Section 21092.1, Public Resources Code; Laurel Heights Improvement Association v. Regents of the University of California (1993) 6 Cal. 4th 1112.