(a) When a proposed subsequent project is identified in the Master EIR, but the lead agency cannot make a determination pursuant to Section 15177 that the subsequent project is within the scope of the Master EIR, and the lead agency determines that the cumulative impacts, growth inducing impacts and irreversible significant effects analysis in the Master EIR is adequate for the subsequent project, the lead agency shall prepare a mitigated negative declaration or a focused EIR if, after preparing an initial study, the lead agency determines that the project may result in new or additional significant effects. Whether the cumulative impacts, growth inducing impacts and irreversible significant effects analyses are adequate is a question of fact to be determined by the lead agency based upon a review of the proposed subsequent project in light of the Master EIR.
(b) A lead agency shall prepare a mitigated negative declaration for any proposed subsequent project if both of the following occur:
(c) A lead agency shall prepare a focused EIR if the subsequent project may have a significant effect on the environment and a mitigated negative declaration pursuant to subdivision (b) of this section cannot be prepared.
(d) A lead agency shall file a notice of determination shall be filed pursuant to Section 15075 if a project has been approved for which a mitigated negative declaration has been prepared pursuant to this section and a notice of determination shall be filed pursuant to Section 15094 if a project has been approved for which a focused EIR has been prepared pursuant to this section.
(e) When a lead agency determines that the cumulative impacts, growth inducing impacts and irreversible significant effects analysis in the Master EIR is inadequate for the subsequent project, the subsequent project is no longer eligible for the limited environmental review available under the Master EIR process and shall be reviewed according to Article 7 (commencing with Section 15080) of these guidelines. The lead agency shall tier the project specific EIR upon the Master EIR to the extent feasible under Section 15152.
1. New section filed 5-27-97; operative 5-27-97 pursuant to Government Code section 11343.4(d) (Register 97, No. 22).
2. Change without regulatory effect amending NOTE filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).
Note: Authority cited: Section 21083, Public Resources Code. Reference: Sections 21081(a)(2), 21157.5 and 21158, Public Resources Code.