Section 15177 - Subsequent Projects Within the Scope of the MEIR

Universal Citation: 14 CA Code of Regs 15177

Current through Register 2024 Notice Reg. No. 38, September 20, 2024

(a) After a Master EIR has been prepared and certified, subsequent projects which the lead agency determines as being within the scope of the Master EIR will be subject to only limited environmental review.

(b) Except as provided in subdivision (2) of this subdivision, neither a new environmental document nor the preparation of findings pursuant to section 15091 shall be required of a subsequent project when all of the following requirements are met:

(1) The lead agency for the subsequent project is the lead agency or any responsible agency identified in the Master EIR.

(2) The lead agency for the subsequent project prepares an initial study on the proposal. The initial study shall analyze whether the subsequent project was described in the Master EIR and whether the subsequent project may cause any additional significant effect on the environment which was not previously examined in the Master EIR.

(3) The lead agency for the subsequent project determines, on the basis of written findings, that no additional significant environmental effect will result from the proposal, no new additional mitigation measures or alternatives may be required, and that the project is within the scope of the Master EIR. "Additional significant environmental effect" means any project-specific effect which was not addressed as a significant effect in the Master EIR.

(c) Whether a subsequent project is within the scope of the Master EIR is a question of fact to be determined by the lead agency based upon a review of the initial study to determine whether there are additional significant effects or new additional mitigation measures or alternatives required for the subsequent project that are not already discussed in the Master EIR.

(d) Prior to approval of the proposed subsequent project, the lead agency shall incorporate all feasible mitigation measures or feasible alternatives appropriate to the project as set forth in the Master EIR and provide notice in the manner required by Section 15087.

(e) When the lead agency approves a project pursuant to this section, the lead agency shall file a notice in the manner required by Section 15075.

1. New section filed 5-27-97; operative 5-27-97 pursuant to Government Code section 11343.4(d) (Register 97, No. 22).
2. Change without regulatory effect amending subsection (b) and NOTE filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).

Note: Authority cited: Section 21083, Public Resources Code. Reference: Sections 21157, 21157.6 and 21158, Public Resources Code.

Disclaimer: These regulations may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.