California Code of Regulations
Title 14 - Natural Resources
Division 5 - San Francisco Bay Conservation and Development Commission
Chapter 6 - Permit Procedures: Administrative and Emergency Permits
Subchapter 1 - Procedures for Permits for Minor Repairs or Improvements (Administrative Permits)
Article 3 - Approval or Denial of Administrative Permits
Section 10625 - Environmental Documentation Required for Approval of Minor Permit
Current through Register 2024 Notice Reg. No. 38, September 20, 2024
Before the Executive Director may approve a minor permit, the Commission must receive a copy of any required environmental determination and certified environmental document issued by the lead agency, as follows:
(a) If a negative declaration or environmental impact document for a project must be certified by the lead agency under the California Environmental Quality Act (CEQA), then the applicant may submit the certification and document as part of the permit application.
(b) When the certification and document are not submitted as part of a permit application, either (1) the applicant must submit a copy of the lead agency's certification and document before the Executive Director submits an administrative listing of the application to the Commission as specified in Section 10620, or (2) the Executive Director shall deny a permit for the project.
1. New section filed 1-26-98; operative 2-25-98 (Register 98, No. 5).
Note: Authority cited: Section 66632, Government Code; and Section 29201(e), Public Resources Code. Reference: Sections 65941 and 66632(f), Government Code; and Sections 21000(g) and 29520, Public Resources Code.