California Code of Regulations
Title 14 - Natural Resources
Division 5.8 - San Gabriel and Lower los Angeles Rivers and Mountains Conservancy
Chapter 2 - Selection Process for Private Architectural, Landscape Architectural, Engineering, Environmental, Land Surveying and Construction Project Management Firms
Section 14029 - Contracting in Phases

Universal Citation: 14 CA Code of Regs 14029
Current through Register 2024 Notice Reg. No. 38, September 20, 2024

If the Executive Officer determines it is necessary or desirable for the project to be performed in separate phases, the Executive Officer may negotiate a partial compensation for the initial phase of the services required; provided, however, that the Executive Officer first determines that the firm selected is best qualified to perform the entire project. The contract shall include a provision that the Conservancy may, at its option, utilize the firm to perform other phases of the services at a compensation which the Conservancy determines is fair and reasonable, to be later negotiated and included in a mutually acceptable written agreement. In the event that the Conservancy exercises its option under the contract to utilize the firm to perform other phases of the project, the procedures of this Chapter with regard to estimates of value of services and negotiation shall similarly be followed.

1. New section filed 1-9-2002; operative 2-8-2002 (Register 2002, No. 2).

Note: Authority cited: Section 32613, Public Resources Code. Reference: Section 32614, Public Resources Code.

Disclaimer: These regulations may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.