California Code of Regulations
Title 14 - Natural Resources
Division 2 - Department of Conservation
Chapter 4 - Development, Regulation, and Conservation of Oil and Gas Resources
Subchapter 2 - Environmental Protection
Article 3 - Requirements
Section 1777.2 - Production Facility Reporting Requirements
Current through Register 2024 Notice Reg. No. 38, September 20, 2024
(a) Any operator acquiring the right to operate a facility shall notify the local district office in writing within 30 days after finalizing the sale or transfer with the following information:
(b) Operators shall notify the local district office within 60 days after completing new construction, alteration, or decommissioning of a production facility, or reactivating an Out-of-Service tank . This notification report shall describe the activities and reference the production facilities that have been added, altered or decommissioned.
(c) Operators shall notify the local district office two days or more prior to conducting required tank or pipeline testing specified in Sections 1773.4 or 1774.1.
1. New section filed 12-30-2010; operative 1-29-2011 (Register 2010, No. 53).
Note: Authority cited: Sections 3013 and 3270, Public Resources Code. Reference: Sections 3106, 3202 and 3270, Public Resources Code.