Section 1777.2 - Production Facility Reporting Requirements

Universal Citation: 14 CA Code of Regs 1777.2

Current through Register 2024 Notice Reg. No. 38, September 20, 2024

(a) Any operator acquiring the right to operate a facility shall notify the local district office in writing within 30 days after finalizing the sale or transfer with the following information:

(1) The facility location;

(2) A unique alphanumeric tank identification number designated by the operator consisting of 10 characters or less;

(3) The date the transaction became effective; and

(4) The facility lease name.

(b) Operators shall notify the local district office within 60 days after completing new construction, alteration, or decommissioning of a production facility, or reactivating an Out-of-Service tank . This notification report shall describe the activities and reference the production facilities that have been added, altered or decommissioned.

(c) Operators shall notify the local district office two days or more prior to conducting required tank or pipeline testing specified in Sections 1773.4 or 1774.1.

1. New section filed 12-30-2010; operative 1-29-2011 (Register 2010, No. 53).

Note: Authority cited: Sections 3013 and 3270, Public Resources Code. Reference: Sections 3106, 3202 and 3270, Public Resources Code.

Disclaimer: These regulations may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.