California Code of Regulations
Title 13 - Motor Vehicles
Division 3 - Air Resources Board
Chapter 1 - Motor Vehicle Pollution Control Devices
Article 4 - Diesel Particulate Matter Control Measures
Section 2021.2 - Compliance Requirements for Heavy Cranes
Current through Register 2024 Notice Reg. No. 38, September 20, 2024
A fleet owner with a fleet comprised of one or more heavy cranes shall comply using one or more of the following options. Regardless of the option chosen, the heavy crane fleet as a whole must remain in compliance.
(a) Heavy Crane Phase-In Schedule. Beginning July 1, 2019 and January 1 of every subsequent compliance year, a fleet owner with a fleet comprised of one or more heavy cranes as defined in section 2021(b)(16) may comply by meeting the requirements as set forth below in Table A-1 for the entire fleet of heavy cranes excluding low use vehicles as defined in section 2021(b)(18) or publicly funded vehicles during the funding contract period. The upgrade deadline for 2019 will be 60 days after the effective date, July 1, 2019, of this regulation. The owner must comply with the reporting and record keeping requirements in sections 2021.3(a) and 2021.3(b) for all heavy cranes in the fleet.
Table A-1: Upgrade Schedule for Heavy Cranes from 2019 to 2027
Upgrade Deadline as of January 1 | Percent of Heavy Cranes in the Fleet of Heavy Cranes with 2010 or Newer Model Year Engines |
2019* | 20% |
2020 | 30% |
2021 | 40% |
2022 | 50% |
2023 | 60% |
2024 | 70% |
2025 | 80% |
2026 | 90% |
2027 | 100% |
* The Upgrade Deadline for 2019 is 60 days after July 1, 2019.
(b) Exemption for Low Use Heavy Cranes
(c) Heavy Crane Engine Model Year Schedule. A fleet owner with a fleet comprised of one or more heavy cranes may comply by upgrading each heavy crane in the fleet to a 2010 or newer model year engine according to the heavy crane engine model year schedule as shown in Table A-2, for the model years listed.
Table A-2: Heavy Crane Engine Model Year Schedule
Engine Model Year | Upgrade to 2010 or Newer Model Year Engine by January 1 |
1998 to 2003 | 2019* |
2004 to 2006 | 2022 |
2007 to 2009 | 2025 |
* The Upgrade Deadline for 2019 is 60 days after July 1, 2019.
(d) Compliance Extension for Engine Manufacturer Delays. Beginning with the 2020 compliance year, a fleet owner who has purchased a heavy crane or replacement heavy crane engine, or has entered into contractual agreement with the seller for the purchase of a heavy crane or replacement heavy crane engine, but has not received a replacement heavy crane engine or heavy crane due to manufacturing delays will be excused from immediate compliance with section 2021.2(a) or 2021.2(c) for the given heavy crane until May 1 of the compliance year as long as all the conditions below are met:
1. New
section filed 7-20-2004; operative 7-20-2004 pursuant to Government Code
section
11343.4
(Register 2004, No. 30).
2. Renumbering of former section 2021.2 to
new section
2021.1 and new section 2021.2
filed 6-25-2019; operative 7-1-2019 pursuant to Government Code section
11343.4(b)(3)
(Register 2019, No. 26).
Note: Authority cited: Sections 39600, 39601, 39666 and 39667, Health and Safety Code. Reference: Sections 39002, 39003, 39650, 39655, 39656, 39657, 39658, 39659, 39660, 39661, 39662, 39665, 39666, 39667, 39668, 43000, 43013, 43018, 43101, 43102, 43104, 43105 and 43700, Health and Safety Code.