SOUTH ARKANSAS FIELD RULE SUMMARIES
FIELD |
ORDER |
COUNTY |
RESERVOIR |
LOCATION |
UNIT |
SURFACE CASING |
AGNES ROAD NORTH |
52-90 |
Union |
Cotton Valley |
280' FUB of N/2 S/2 E/2 W/2 of gov 1/4 sec. |
80 |
750' |
14-91 |
Cotton Valley |
Ext. to cover E/2 NW/4 & W/2 NW/4 Sec. 13-17S-16W |
||||
ARKANA |
35-81 |
Lafayette |
Cotton Valley |
330' FUB |
80 |
B-15 |
143-83 |
Haynesville |
330' FUB of gov 1/4 sec. |
160 |
B-15 |
||
260-84 |
Pettet |
280' FUB of units A, B & C |
80 |
B-15 |
||
261-84 |
Tokio |
280' FUB of gov 1/4 1/4 1/4 sec |
10 |
B-15 |
||
381-84 |
Lafayette |
Haynesville |
Ext. to cover E/2 5, 9, N/2 & SW 10-T20S-R25W |
|||
10-89 |
Cotton Valley |
Ext. to cover NW/4 Sec. 10-20S-25W |
||||
51-92 |
Smackover |
660' FUB; N/2 or S/2 Gov Sec |
320 |
1500' |
||
29-94 |
Buckrange |
280' FUB of gov. 1/4 1/4 1/4 sec. |
10 |
100' |
||
182-2008-03 |
Lafayette |
Haynesville & Cotton Valley |
330' from LA state line; 660' FUB, 900' well locations |
160 |
B-15 |
|
009-2017-02 |
Lafayette |
Buckrange |
Exceptional D.U. = Frac. S/2 SW/4 Sec. 7-T20S-R24W |
51.92 |
||
ARTESIAN |
16-54 |
Calhoun |
Meakin |
165' from lease line, property line, subdivision line N/2 S/2 E/2 W/2 of gov. 10 acre unit |
10 |
100' |
9-63 |
Meakin |
50' of C gov 1/4 1/4 1/4 sec. |
||||
ARTEX |
123-82 |
Miller |
Paluxy |
330' FUB of gov. 1/4 1/4 sec. |
40 |
500' |
ATLANTA |
14-39 |
Columbia |
Smackover |
280' FUB of gov 1/4 1/4 sec |
40 |
100' |
25-39 |
Amend Rule IV(b) |
2nd string set at 50' at approx. 2550' |
||||
38-40 |
Amend Allocation |
|||||
3-45 |
Lime Pool |
Amend Rule II - Spacing 100' from center of gov. 40-ac. |
||||
15-45 |
Reynolds Lime |
Revise to include both East & West Atlanta into one field -100' from center |
40 |
2200' |
||
27-48 |
Cotton Valley |
280' FUB of gov 1/4 1/4 sec |
40 |
800' |
||
32-48 |
Cotton Valley |
Amend Surface Casing |
800' |
|||
35-64 |
Cotton Valley |
Comm. |
||||
20-66 |
Smackover |
Amend Surface Casing |
1000' |
|||
126-79 |
Cotton Valley & Smackover |
280' FUB - Ext. to cover S/2 Sec. 11, SW/4 Sec. 12, W/2 Sec. 13, N3/4 Sec. 14, N3/4 Sec. 15 & NE/4, N/2 SE/4, E/2 NW/4 & NE/4 SW/4 Sec. 16-T18S-R19W |
||||
161-80 |
Smackover & Cotton Valley |
Ext. to cover Sec. 7, 8, 9, 15, 16-18S-19W |
||||
151-81 |
Smackover Lime |
Amend to 200' of center; - reg. gov. 1/4 1/4 sec, 2 reg. gov. 1/4 1/4 sec. or 4 gov. 1/4 1/4 sec. in form of square |
40, 80 or 160 |
|||
31-82 |
Columbia |
Cotton Valley & Smackover |
280' FUB & Ext. to cover 12-T18S-R20W |
|||
BUI-82 |
Smackover |
Brine Unit "A" unitized |
||||
BUI-82A |
Columbia |
Smackover |
Brine Unit "A" Operation - amend |
|||
BUI-83 |
Brine Unit "A" Operation |
|||||
249-83 |
Columbia |
Cotton Valley & Smackover |
Ext. to cover S/2 NW/4 Sec. 9-T18S-R19W & dissolve SE/4 NW/4 & SW/4 NW/4 Sec. 9 & 2x allow. |
|||
43-84 |
Pettet |
280' FUB of E/2 W/2 S/2 or N/2 gov 1/4 sec |
80 |
B-15 |
||
398-84 |
Cotton Valley & Smackover |
280' FUB for Sec 17-18S-19W extensions thereto |
||||
46-85 |
Cotton Valley & Smackover |
Ext. to cover W/2 NE/4 & S/2 Sec. 13-T18S-R20W & Dissolve NE NE & SE NE Sec. 13-T18S-R20W & form exceptional unit in E/2 NE/4 Sec. 13 |
||||
62-85 |
||||||
272-85 |
Smackover |
Gas allowable & Ext. to cover S/2 Sec. 7-T18S-R19W |
||||
371-85 |
Pettet |
Amend spacing 280' FUB & Ext. to cover S/2 SE/4 Sec. 13 18S-20W |
- |
|||
43-86 |
Smackover |
Allow production from more than one well per unit in S/2 7 and all of secs. 17 and 18 of 18S-19W |
||||
142-2004-12 |
Columbia |
Smackover |
Allowable increase |
|||
133-1-2011-05 |
Columbia |
Lower Smackover |
Dissolve all D.U. in Sec. 15-T18S-R19W; Creation of Exc. D.U. - all of Sec. 15-T18S-R19W |
640 |
||
196-2011-07 |
Columbia |
Smackover |
Allowable increase from 15,000 to 20,000 bbl / day. |
|||
AURELLE |
156-80 |
Union |
Nacatoch |
300' FUB of N/2 E/2 S/2 W/2 gov 1/4 1/4 sec |
20 |
B-15 |
BARLOW BRANCH |
57-74 |
Columbia |
Smackover |
330' from unit Bound E/2 W/2 Gov. 1/4 sec. |
80 |
1000' |
70-75 |
Smackover |
Ext to cover N 1/2 E 1/2 S 1/2 W 1/2 gov 1/4 sec |
||||
155-80 |
Smackover |
Dissolve D. U. (E 1/2 NE 1/4 & W 1/2 NE 1/4 26-16S-21W) |
||||
BEAR CREEK |
24-51 |
Union |
Travis Peak |
330' from Property or Division Line |
40 |
100' |
BEECH CREEK |
328-85 |
Union |
Cotton Valley |
280' FUB of gov. 1/4 1/4 sec. |
40 |
B-15 |
BEECH CREEK WEST |
218-83 |
Union |
Cotton Valley |
280' FUB of gov 1/4 1/4 sec |
40 |
1000' |
386-84 |
Cotton Valley |
Amend surfacing casing |
B-15 |
|||
44-84 |
Pettet |
280' FUB of gov 1/4 1/4 sec |
40 |
B-15 |
||
65-85 |
Cotton Valley |
Commingle |
||||
328-85 (Corr.) |
Union |
Cotton Valley |
280' FUB; 1/4 1/4 gov. sec. |
40 |
B-15 |
|
BERRY |
31-75 |
Union |
Graves |
280' FUB N/2 S/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
BERT CREEK |
10-79 |
Union |
Smackover |
660' FUB Gov 1/4 sec |
160 |
750' |
49-91 |
Cotton Valley |
280' FUB; Gov 1/4 sec |
160 |
750' |
||
BIG BRANCH |
87-82 |
Lafayette |
Tokio (2470'-2490'), Tuscaloosa (2810'-2830'), Paluxy (2850'-4000') |
280' FUB any 1/2 Gov 1/4 1/4 sec |
20 |
100' (0-3000') 160' (3000'-4000')' |
BIG BRANCH EAST |
224-2006-07 |
Lafayette |
Smackover |
330' FUB auto extensions or more than 1 well |
No 126 |
1,000' |
284-2007-06 |
Lafayette |
Smackover |
Amend to permit 2nd well allowable - 100 bbls./day |
|||
BIG CREEK |
62-86 |
Columbia |
Smackover |
280' FUB of E/2 W/2 N/2 or S/2 gov 1/4 |
80 |
1000' |
BIG CREEK EAST |
402-2008-07 |
Columbia |
Pettet |
280' FUB; Any two Gov 1/4 1/4 sec. |
80 |
500' |
BLOOMBURG |
61-85 |
Miller |
Smackover |
600' FUB |
320 |
2500' |
BODCAW |
23-50 |
Nevada |
Kilpatrick |
50' of line Conn. C. Two 1/4 1/4 1/4 N/2 E/2 W/2 S/2 gov. sec. |
1/4 1/4 20 |
60' |
31-50 |
Kilpatrick |
Correct reservoir name |
||||
10-54 |
Hill |
50' of line conn. C. Two 1/4 1/4 1/4 N/2 E/2 W/2 S/2 Gov sec. |
1/4 1/4 |
100' |
||
45-70 |
Hill |
Amend size of unit |
40 |
|||
19-72 |
Hill Glen Rose& Kilpatrick |
Comm. |
||||
40-74 |
Kilpatrick |
Unitized |
||||
BODCAU CREEK |
299-84 |
Lafayette |
Pettet |
280' FUB of N/2 S/2 E/2 or W/2 of gov 1/4 sec. |
80 |
B-15 |
BOGGY BOTTOM |
81-65 |
Union |
Hogg |
280' FUB N/2 E/2 S/2 W/2 Gov. 1/4 1/4 sec. |
20 |
160' |
9-66 |
Tuscaloosa |
280' FUB N/2 E/2 S/2 W/2 Gov 1/4 1/4 sec |
20 |
160' |
||
BOGGY CREEK |
166-82 |
Miller |
Paluxy, Up & Down Thrown |
280' FUB Gov 1/4 1/4 sec. |
40 |
500' |
BOLDING |
64-86 |
Union |
Cotton Valley |
330' FUB N/2 or S/2 of gov. 1/4 sec. |
80 |
B-15 |
BOYCE LAKE |
128-80 |
Miller |
Smackover |
1000' FUB N/2 or S/2 of gov. sec. |
320 |
1000' |
41-85 |
Smackover |
Rescinded Order #128-80 as it applies to Sec. 8-16S |
-27W |
|||
BOYD |
335-85 |
Miller |
Smackover |
280' FUB |
80 |
B-15 |
59-94 |
Smackover |
660' FUB |
160 |
B-15 |
||
BOYD HILL |
244-84 |
Miller |
Smackover |
660' FUB of gov. 1/4 sec. |
160 |
750' |
62-88 |
Smackover |
Permitted to flare gas to recover oil |
1,000 mcfd |
|||
227-1-2011-08 |
Miller |
Amend to create exceptional unit: SW/4 SW/4 & W/2 SE/4 SW/4 of Sec. 2-T15S-R26W; S/2 SE/4 & E/2 SE/4 SW/4 of Sec. 3-T15S-R26W; NE/4 & E/2 E/2 NW/4 of Sec. 10-T15S-R26W; W/2 NW/4 & W/2 E/2 NW/4 of Sec. 11-T15S-R26W. |
480 |
|||
129-2015-12 |
Miller |
Amend to create exceptional unit: SW/4 SW/4 & W/2 SE/4 SW/4 of Sec. 2-T15S-R26W; S/2 SE/4 & E/2 SE/4 SW/4 of Sec. 3-T15S-R26W; NE/4 & E/2 E/2 NW/4 of Sec. 10-T15S-R26W; W/2 NW/4 & W/2 E/2 NW/4 of Sec. 11-T15S-R26W. |
480 |
|||
BRADLEY |
196-81 |
Lafayette |
Buckrange |
280' FUB gov. 1/4 1/4 sec. |
40 |
100' |
BRADLEY SOUTH |
153-2000-11 |
Lafayette |
Tokio Sand Reservoir "A" Formation |
Est Field Rules and create drilling units SW/4 SE/4 Sec. 18-19S-24W |
40 |
|
020-2015-01 |
Lafayette |
Amend to 280' FUB & increase to 35 BOPD. Ext to include NW/4 NE/4, NE/4 NW/4, & NW/4 NW/4 Sec. 19-T19S-R24West, as well as SE/4 SW/4 & SW/4 SW/4 in Sec. 18-T19S-R24W, and auto extensions. |
40 |
B-15 |
||
BRADLEY WEST |
7-55 |
Lafayette |
Mitchell |
330' FUB gov. 1/4 1/4 sec. |
40 |
500' |
24-55 |
Field Redesignation (was Kiblah East) |
|||||
57-55 |
Mitchell |
Annexing unitized area |
||||
BUCKNER |
12-39 |
Columbia & Lafayette |
Smackover |
660' from property or division line of gov. 1/4 1/4 sec. 1320' from any well |
40 |
100' |
38-40 |
Amend Allocation |
|||||
4-45 |
Smackover |
Amend Spacing 100' from center of gov. 40 acre unit |
||||
14-47 |
Travis Peak |
100' from C of Gov. 1/4 1/4 sec. |
40 |
825' |
||
22-47 |
Travis Peak |
Amend surface casing |
400' |
|||
27-51 |
Travis Peak |
Amend for upper Travis Peak & lower Travis Peak |
||||
20-76 |
Smackover |
Amend Surface Casing |
800' |
|||
70-76 |
Travis Peak |
Comm. upper & lower |
||||
7-88 |
Smackover & Travis Peak |
Amend location provisions to 280' FUB. |
||||
44-94 |
Smackover |
Amend size of unit |
80 |
1000' (7500'-8500') |
||
24-97 |
Smackover |
Unitization |
||||
67-97 |
Smackover |
Amend unit location; 100' FUB |
||||
178A-2010-02 |
Smackover |
Amend 24-97 - Dissolved part and reconfigured field-wide unit |
||||
BUENA VISTA |
24-64 |
Ouachita |
Unit Operation of Buckrange Formation |
|||
339-85 |
Field Rules & Drilling Unit (Nacatoch) S/2 SW/4 14 S/2 S/2 15-14-19 |
|||||
116-2003-10 |
Ouachita |
DISSOLVE FIELD RULES BUCKRANGE UNIT, SEC. 14 AND 15-14S-19W |
||||
BURDELL BRANCH |
27-77 |
Kilpatrick |
Unitization |
|||
BURNS POND |
9-86 |
Smackover |
ESTABLISH FIELD RULES 330'FUB |
160 |
750' |
|
101-2004-08 |
Union |
REINSTATE FIELD RULES |
||||
BURNSIDE CREEK |
68-75 |
Union |
Hosston |
280' FUB |
40 |
B-15 |
CAIRO |
26-48 |
Smackover |
100' center of gov 1/4 1/4 sec (Temporary) |
40 |
1000' |
|
31-48 |
Smackover |
Amend production casing |
||||
28-65 |
Smackover |
Amend surface casing |
100' |
|||
78-65 |
Amend allocation formula of Order 57-65 |
|||||
108-79 |
Smackover |
Amend spacing 460' of gov. 1/4 1/4 sec. & reestablish allow. |
||||
CALION |
5-53 |
Union |
Blossom (2600'), Graves (2470'), Meakin (2330'), Nacatoch (2055') |
50' of center of two 10 acre units making a 20 acre unit N/2 S/2 E/2 W/2 of gov 40 acre unit |
20 |
150' |
72-64 |
Blossom, Graves, Meakin, Nacatoch |
Amend surface casing |
100' |
|||
6-65 |
Graves & Blossom |
Comm. |
||||
61-68 |
Blossom, Graves, Meakin, Nacatoch |
Amend drilling unit and spacing 280' FUB |
10 |
|||
158-84 |
Cotton Valley |
280' FUB of gov. 1/4 1/4 sec. |
40 |
500' |
||
192-84 |
Travis Peak |
280' FUB of gov. 1/4 1/4 sec. |
40 |
300' |
||
CAMP CREEK 2600' TO 2650' |
40-60 |
Union |
Lower Blossom |
330' FUB gov. 1/4 1/4 sec. |
40 |
75' |
45-62 |
Lower Blossom |
Unitized |
||||
5-64 |
Union |
Delete 40 ac. Tract from purview 17-T16S-R16W |
||||
192-2011-07 |
Union |
Lower Blossom |
Rescind Orders No. 40-60 & 45-62 terminating and rescinding Field Rules & F.W.U. for Lower Blossom. |
|||
17-81 |
Tokio |
280' FUB gov. 1/4 1/4 1/4 sec. |
10 |
100' (0-3000') |
||
CANFIELD |
88-83 |
Columbia |
James |
330' FUB gov. 1/4 sec. |
160 |
B-15 |
CARREYVILLE LANDING |
34-62 |
Bradley |
Blossom |
50' of center of NW/4 SE/4 of gov 1/4 1/4 sec. N/2 S/2 E/2 W/2 |
20 |
100' |
35-62 |
Hoston Travis Peak & Cotton Valley |
200' from center of gov 1/4 1/4 sec. |
40 |
160' (0-4000') |
||
87-67 |
Amend 34-62 - 50' of center of two 10-ac. Tracts) |
20 |
||||
63-77 |
Blossom, Travis Peak, & Cotton Valley |
Amend unit location 280' FUB |
||||
CATESVILLE COTTON VALLEY 6625' |
24-50 |
Union |
Jones, Cotton Valley & Smackover |
100' of C. of gov. 1/4 1/4 sec. |
40 |
1000' |
401-84 |
Union |
Ext. to cover SW NW 32-T18S-R15W |
||||
CATESVILLE JONES 7500' |
22-56 |
Union |
Jones, Cotton Valley & Smackover |
660' FUB (Unitized) |
||
CATESVILLE SMACKOVER 7700' |
Union |
|||||
CENTER |
4-53 |
Columbia |
Hogg |
50' of line conn. C. of two 1/4 1/4 1/4 sec. |
20 |
100' |
CENTRAL CHURCH |
48-85 |
Miller |
Paluxy |
280' FUB of gov. 1/4 1/4 sec. |
40 |
160' |
CHALYBEAT SPRINGS |
10-71 |
Columbia |
Cotton Valley |
660' FUB gov. 1/4 sec. |
160 |
1250' |
38-72 |
Smackover |
660' FUB gov. 1/4 sec. |
160 |
1250' |
||
45-73A |
Columbia |
Smackover |
Amend 38-72 to cover 31-T19S-R18W, 6-T20S-R18W & 30 & 31=T19S-R19W |
|||
29-74 |
Amend 38-72 - Oversized sections divided into 4 equal sized rectangular shapes & adjust allowable |
|||||
6-75 |
Columbia |
Smackover |
Extend 38-72 to cover SW 5-T20S-R18W |
|||
57-75 |
Smackover |
Unitized |
||||
60-79 |
Columbia |
Smackover |
Amend 38-72 to delete S/2 32 & SW/4 33-T19S-R19W - & Amend 57-75 - 660' FUB |
|||
154-80 |
Columbia |
Smackover |
Delete SE/4 & SW/4 & S/2 NW/4 31-T19S-R19W & move to Ware Creek |
|||
17-92 |
Smackover |
Dissolve D.U. (S/2 SW/4 NE/4 Sec. 36-19S-19W) |
||||
42-93 |
Columbia |
Smackover |
Ext. Order #17-92 for 1 year; Amend 38-72 to delete NE/4 less S/2 SW/4 NE/4 36-T19S-R19W & grant permit 330' FSL & 660' FEL NE/4 36 |
|||
130A-2015-12 |
Columbia |
Smackover |
Dissolve Field-Wide Unit created by Order No. 57-75. Gas cap blow down to continue on 160 acre unit basis. (Order stayed by Circuit Court in Pulaski Cty pending appeal). |
|||
CHAMPAGNOLLE |
222-2013-09 |
Union |
Smackover |
280' FUB. Created specific D>U.N/2 SE/4 ; SW/4 NE/4 and NE/4 NE/4 Sec. 16-T17S-R14W; NW/4 NW/4 and the E/2 NW/4 of Sec. 15-T17S-R14W; SW/4 SW/4 and the E/2 SW/4 of Sec. 15-T17S-R14W. Auto Ext. |
40 |
500'. B-15 |
028-2018-04 |
Union |
Smackover |
Create 2 DUs. (1) W/2 NE/4, SE/4 of Sec 1-T17S-R14W, and (2) E/2 NW/4 SE/4 of Sec 1-T17S-R14W. Auto-extens |
20 |
500' B-15 |
|
CHAMPAGNOLLE 3900' |
48-68 |
Union |
Cotton Valley |
280' FUB N/2 E/2 S/2 W/2 gov. 1/4 1/4 sec. |
20 |
160' |
CHAMPAGNOLLE 5640' |
26-75 |
Union |
Cotton Valley |
Commingle |
||
3-86 |
Travis Peak |
Commingle |
||||
Cotton Valley |
||||||
CHAMPAGNOLLE LANDING |
32-58 |
Union |
Baker |
50' of line conn. C 1/4 1/4 1/4 of gov. 1/4 1/4 sec. |
40 |
100' w/100 sks. |
45-75 |
Baker |
Unitized |
||||
CHAVARI CREEK 2396' |
72-66 |
Bradley |
Nacatoch |
280' FUB 1/4 1/4 1/4 gov. sec. |
20 |
100' |
CHAVARI CREEK 2452' |
36-72 |
Bradley |
Nacatoch |
Amend unit size; gov. 1/4 sec. |
10 |
|
139-84 |
Nacatoch |
Unitized |
||||
CHICKEN CREEK |
155-87 |
Miller |
Paluxy |
280' FUB of N/2 S/2 E/2 W/2 gov. 1/4 1/4 sec. |
20 |
B-15 |
CHICKEN CREEK SOUTHWEST |
96-96 |
Miller |
Paluxy |
280' FUB gov. 1/4 sec. |
160 |
160' |
CHRISTMAS |
31-57 |
Miller |
1st Sturgis |
50' of line conn. C. two 1/4 1/4 1/4 W/2 E/2 S/2 W/2 gov. 1/4 1/4 in E/2 of sec. 17 W/2 or E/2 gov. 1/4 1/4 sec. 18 |
20 |
100' |
63-60 |
1st Sturgis |
Amend unit location |
||||
12-61 |
1st Sturgis |
Amend unit location |
||||
3-67 |
1st Sturgis |
Unitized |
||||
2-80 |
Tuscaloosa. & 1st Sturgis |
Commingled |
||||
116A- 1-2015-09 |
Miller |
1st Sturgis |
Dissolve and terminate EOR Unit created by Order No. 3-67 & 3-67A |
|||
CLEVELAND BRANCH |
25-2006-02 |
Lafayette |
Smackover |
330' FUB |
170 |
B-15 |
313-2007-07 |
Lafayette |
Smackover |
Amend to allow 2nd well - initial sep. allow of 150 bbls./day |
|||
COLUMBIA |
35-78 |
Columbia |
Pettet |
330' FUB N/2 or S/2 gov. 1/4 sec. |
80 |
150' |
494-2009-07 |
Columbia |
Pettet |
Ament to allow 280 FUB E/2, W/2, N/2 or S/2 gov. 1/4 sec; Ext. to cover E/2 SE/4 Sec. 23-17S-R21W & NW/4 Sec. 24-T17S-R21W). Create Unit comprised of W/2 of NW/4 Sec. 24-T17S-R21W. Allows for automatic ext. |
80 |
500 |
|
347-2010-05 |
Columbia |
Pettet |
80 acre units be comprised of any two governmental quarter-quarter 40 acre sections in the shape of a rectangle. |
80 |
||
047-2015-04 |
Columbia |
Pettet |
Exceptional D.U. = E/2 NW/4 NW/4; NE/4 NW/4; & W/2 NW/4 NE/4 Sec. 13-T17S-R21W |
80 |
||
CORNISH BRANCH |
88-67 |
Lafayette |
Mitchell |
330' FUB of gov. 1/4 1/4 sec. |
40 |
500' |
CRAIN CITY |
34-76 |
Union |
Baker |
280' FUB N/2 S/2 E/2 W/2 gov. 1/4 1/4 sec. |
20 |
100' |
CROSS COUNTRY SLOUGH |
58-59 |
Union |
Meakin, Baker & Graves |
50' of C. of two 1/4 1/4 1/4 sec. N/2 S/2 E/2 W/2 gov. 1/4 1/4 sec. |
20 |
100' |
CROSSETT |
163-80 |
Ashley |
Cotton Valley |
330' FUB gov. 1/4 1/4 sec. |
40 |
160' |
89-81 |
Cotton Valley |
Commingle |
||||
157-82 |
Cotton Valley |
Amend surface casing |
500' |
|||
CUMMINGS 8610' |
27-98 |
Rodessa |
280' FUB; Gov. 1/4 1/4 sec. |
40 |
500' |
|
CUMMINGS EAST |
788-2009-12 |
Miller |
Rodessa |
330' FUB; NW/4, NE/4, SE/4 or SW/4 1/4 1/4 sec. stand-up. 100 bopd allow |
80 |
300' |
CURTIS CREEK |
21-82 |
Union |
Hill |
280' FUB; N/2 or S/2 of Gov. 1/4 1/4 sec. |
20 |
3000'-4000'-160' |
83-90 |
Union |
Tuscaloosa |
280' FUB - S/2 SE/4 NE/4 27-T18S-R17W; 1/2 Gov. 1/4 1/4 sec. stand-up or lay-down |
20 |
160' |
|
106-91 |
Hill |
Amend loc. prov. N/2 S/2 E/2 W/2 gov. 1/4 1/4 sec. |
20 |
|||
CYPRESS |
15-97 |
Columbia |
Haynesville |
330' FUB, 280 FUB adjacent to Louisiana border of gov. 1/4 sec. |
160 |
1500' |
31-2006-02 |
Haynesville |
Field Extension and grant of second allowable |
||||
CYPRESS CREEK |
59-61 |
Union |
Travis Peak |
50' of line conn. C. 1/4 1/4 1/4 N/2 E/2 W/2 S/2 gov. 1/4 1/4 sec. |
20 |
100' |
27-65 |
Tokio |
50' of line conn. C. 1/4 1/4 1/4 N/2 E/2 W/2 S/2 gov. 1/4 1/4 sec. |
20 |
100' |
||
28-72 |
Graves & Blossom |
50' of line conn. C. 1/4 1/4 1/4 N/2 E/2 W/2 S/2 gov. 1/4 1/4 sec. |
20 |
100' |
||
CYPRESS LAKE |
27-58 |
Hill |
200' of C. of N/2 S/2 gov. sec.; N/2 or S/2 reg. Gov. sec. |
320 |
100' |
|
25-61 |
Kilpatrick |
330' FUB; gov. 1/4 1/4 sec. |
40 |
300' |
||
382-84 |
Paluxy-Stewart |
Unitized |
||||
52-95 Corr. |
Paluxy |
280' FUB; N/2 S/2 gov. 1/4 sec. |
80 |
300' |
||
DAYS CREEK |
31-72 |
Miller |
Smackover |
280' FUB N/2 S/2 E/2 W/2 gov. 1/4 sec. |
80 |
1000' |
5-79 |
Smackover |
Unitized |
||||
70-92 |
Cotton Valley |
280' FUB; Gov 1/4 1/4 sec. |
40 |
750' |
||
113-97 |
Smackover |
Ext. to cover SW/4 SW/4 of Sec. 33 & SE/4 SE/4 of Sec. 32-16S-28W |
||||
DODDRIDGE |
228-87 |
Miller |
Pettet |
330' FUB of N/2 S/2 E/2 W/2 of gov. 1/4 sec. |
80 |
B-15 |
DORCHEAT-MACEDONIA |
3-43 |
Cotton Valley |
Unitized |
1000' (7500'-9000') |
||
12-44 |
Columbia |
Reynolds Lime & Cotton Valley Sand |
Designate Dorcheat & Macedonia as one field; 150' of center; 660' FUB & 1320' from well; E-W; two gov. 40-ac. 1/4 1/4 sec. N/2 or S/2 of gov. 1/4 sec. |
80 |
100'; 2nd string 2400' |
|
2-47 |
Amend 12-44 - Allow. |
|||||
3-48 |
Amend 2-47 - Allow. |
|||||
6-50 |
Cotton Valley |
Commingle |
||||
10-51 |
Amend 3-48 - Allow. |
|||||
54-55 |
Rodessa |
100' of line conn. C. of two 1/4 1/4 N/2 S/2 1/4 sec. |
80 |
500' |
||
90-65 |
Rodessa G-3 |
Unitized |
||||
52-67 |
Rodessa |
Unitized |
||||
63-68 |
Smackover & Cotton Valley |
Casing Amend |
500' (6000'-6500') 750' (6500'-7500') 1000' (7500'-9000') |
|||
9-70 |
Pettet |
200' of line Conn C. of two 1/4 1/4 sec N/2 S/2 E/2 W/2 Gov 1/4 sec. |
80 |
500 |
||
63-71 |
Cotton Valley |
Amend Loc. Prov.150' of line conn. C. of two 40-acre tracts comprising an 80 D.U. |
||||
24-72 |
Smackover |
Amend Loc. Prov.150' of line conn. C. of two 40-acre tracts comprising an 80 D.U. |
||||
2-76 |
Travis Peak & Cotton Valley |
Commingle. |
||||
83-77 |
Columbia |
Cotton Valley & Smackover |
Ext. 12-44 to cover S/2 SE/4, N/2 SE/4, N/2 SW/4, S/2 SW/4 7-T18S-R22W |
|||
16-78 |
Travis Peak & Cotton Valley |
Commingle |
||||
11-79 |
Pettet, Travis Peak |
Commingle |
||||
24-82 |
Pettet |
Permitting two wells in 1 unit |
||||
185-85 |
Columbia |
Ext. 9-70 to cover SE/4 Sec. 7 & SW/4 Sec. 8-T18S-R21W |
||||
375-85 |
Pettet Lime |
Ext. 9-70 to cover S/2 NE/4 Sec. 7 & N/2 SW/4 Sec. 8-T18S-R21W |
||||
78-86 |
Ext. 9-70 to cover E/2 Sec. 5-T18S-R21W; SE/4 & S/2 NE/4 Sec. 23, Sec. 25, E/2 Sec. 26-T18S-R22W |
|||||
61-88 |
Gloyd |
280' FUB of gov 1/4 1/4 sec. |
40 |
300' |
||
68-91 |
Cotton Valley |
Dissolve DU (S/2 NW/4 & N/2 SW/4 Sec. 16-18S-22W ) |
||||
65-98 |
Rodessa |
Amend to allowable (80 BOPD) |
||||
1-2003-01 |
Columbia |
Cotton Valley & Smackover |
Interests in oil and gas leases |
|||
278-2010-04 |
Columbia |
Smackover |
Exclude Sec. 12-T18S-R23W from field for Smackover Formation only / Establish Expl. Unit |
640 |
||
472-2010-08 |
Columbia |
Smackover |
Exclude Sec. 7-T18S-R22W from field for Smackover Formation only / Establish Expl. Unit |
640 |
||
027-2011-02 |
Columbia |
Smackover |
Exclude Sec. 17-T18S-R22W from field for Smackover Formation / Estabish Expl. Unit |
640 |
||
026-2014-01 |
Columbia |
Pettet & Rodessa |
Comm. S/2 NE/4 Sec. 24-T18S-R22W |
80 |
||
117-2014-04 |
Columbia |
Cotton Valley |
8 wells in any 80 acre lay down unit (grandfathered in one unit with 9 existing wells). After 2nd well in unit, wells are to be drilled with at least 2 well bores per pad, and additinal financial assurances required. Authority to commingle Cotton Valley Sandstones without approval. 150 BOPD for Cotton Valley wells |
80 (lay down only) |
B-15 |
|
164-2014-05 |
Columbia |
Cotton Valley |
Extended same provisions of Order 117-2014-04 to two different stand-up 80 acre units. (SW/4 SE/4 Sec. 16 & NW/4 NE/4 of Sec. 21-T18S-R21W; and SE/4 SE/4 of Sec. 16 & NE/4 NE/4 of Sec. 21-T18S-R21W |
80 |
B-15 |
|
090A-2015-07 |
Columbia |
Rodessa G-3 & Rodessa |
Dissolve and terminate EOR Units created by Order Nos. 90-65 & 52-67 (and others in other fields) |
|||
DRY FORK |
134-89 |
Lafayette |
Tokio |
280' FUB of gov 1/4 1/4 sec. |
40 |
B-15 |
EL DORADO EAST |
23-51 |
Union |
Glen Rose |
50' of C 1/4 1/4 1/4 sec N/2 S/2 E/2 W/2 1/4 1/4 sec |
20 |
100' |
Ezzell Area |
26-52 |
Pettet Nacatoch Cotton Valley |
280' FUB |
10 |
100' |
|
Rogers Area |
14-53 |
Graves |
280' FUB |
10 |
100' |
|
Amason Area |
23-54 |
Saulsbury & Travis Peak |
50' of line Conn. C. Two 1/4 1/4 1/4 N/2 S/2 W/2 E/2 1/4 1/4 sec. |
20 |
100' |
|
Ezzell Area |
9-64 |
Between Nacatoch & Cotton Valley |
Amend 26-52 Rule II - N/2, S/2, E/2, or W/2 of Gov. 1/16 sec. - 50' of center of two 10-ac. tracts |
20 |
||
Ezzell Area |
4-70 |
Cotton Valley & Smackover |
280' FUBof gov. 1/4 1/4 sec. |
|||
Ezzell & Rogers |
43-61 |
Commingle |
40 |
300' |
||
Rogers |
77-65A |
Amend unit size & location provisions (280' FUB) |
10 |
|||
Ezzell |
77-65B |
Nacatoch & Cotton Valley |
Amend loc. prov. 280' FUB & unit size |
10 |
||
Ezzell Area |
221-2012-09 |
Cotton Valley |
Admin approval of add. completions w/in pay sands of Cotton Valley - subject to restrictions. |
|||
335-2014-10 |
Union |
Exc. D.U. - NE/4 SW/4 Sec. 13-T17S-R15W |
40 |
|||
EL DORADO SOUTH |
20-79 |
Union |
Smackover |
280' FUB any two Gov 1/4 1/4 sec in form of Rectangle having a N-S or E-W Axis |
80 |
1000' |
197-81 |
Smackover |
Dissolve D.U. (SE/4 SE/4 of Sec. 15 NE/4 NE/4 of Sec. 22-18S-16W) |
||||
ELLIOTT' |
31-74 |
Ouachita |
Nacatoch |
280'FUB any two contiguous 1/2 1/4 Gov. Sec. |
160 |
100' |
ELLIOTT SOUTH |
146-82 |
Ouachita |
Nacatoch |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 sec |
80 |
100' |
ENYART LANE |
49-71 |
Lafayette |
Mitchell |
330' FUB any two Contiguous Gov. 1/4 1/4 sec with longitudal axis to be E-W or N-S direction |
80 |
500' |
121-91 |
Mitchell |
Ext. to cover E/2 SE/4 of Sec 6-20S-25W with longitudal axis to be E-W or N-S direction |
||||
FALCON |
7-53 |
Nevada |
Nacatoch |
165' from any lease line N/2 S/2 E/2 W/2 of 1/4 1/4 1/4 sec |
5 |
100' |
3-54 |
Tokio & Blossom |
Not to exceed 75 Bbls./day; gas-oil ratio cf/bbl. |
||||
8-54 |
Blossom |
200' from property or division line on Gov 10 acre tract |
10 |
100' |
||
11-54 |
Nevada |
Tokio & Rodessa |
Amend 7-53 - Spacing (Nroth Area) Gov. 20-ac. N/2, S/2, E/2 or W/2 Gov. 40-ac. Tract - 200' FUB |
40 |
||
29-54 |
Nevada |
Tokio, Nacatoch, Rodessa |
Amend 11-54 & 7/53 (North Area) - Gov. 20-ac. N/2, S/2, E/2 or W/2 Gov. 40-ac. Tract - 200' FUB |
40 |
||
30-54 |
Nevada |
Blossom |
Amend 8-54 Spacing & drilling unit - 200' FUB, Gov. 20-ac. N/2, S/2, E/2 or W/2 Gov. 40-ac. Tract - 200' FUB |
40 |
||
11-55 |
Tokio Rodessa |
200' from property line on Gov. 10 acre tract 50' of line conn C. 1/4 1/4 1/4 of 20 acre unit |
20 20 |
100' 100' |
||
23-86 |
Nacatoch |
75' FUB of 1.11 acre unit 220' X 220' |
1.11 |
100' |
||
FLATWOODS |
125-2013-05 |
Lafayette |
Tokio |
E/2 SW/4 SW/4 & W/2 SE/4 SW/4 Sec. 5-T16S-R24W & auto ext. 280' FUB. 40 bopd. |
40 |
B-15 |
FOUKE |
14-40 |
Miller |
Blossom, Paluxy & Deeper |
Paluxy: 933' from well or less than 330' FUB, Lower: 100' of center of gov. 40-ac. Tract |
40 |
Paluxy: 200' Below: 200', 2nd string 4000 |
24-47 & Corr. |
Miller |
Blossom, Paluxy & Deeper |
Gov. tract 100' of center; Paluxy: 933' from well or 330' FUB Glen Rose & Above: 400' |
40 |
400' |
|
21-52 |
Miller |
Beuford Sand |
50' from center of two 10-ac. Tracts |
20 |
400' |
|
29-52 |
Miller |
3rd Sturgis |
50' of cneter of two 10-ac. Tracts; E/2 or W/2 of Gov. 40-ac. Tract. |
20 |
400' |
|
36-52 |
Miller |
Blossom, Paluxy & Deeper |
Amend 24-47 - Rule VII |
|||
27-54 |
1st Sturgis C |
Unitized |
||||
48-55 |
Miller |
Paluxy |
50' of center of SE/4 of Gov. 1/16 sec. |
40 |
400' |
|
11-56 |
Miller |
Paluxy (Zanger) |
50' of center of NW/4 & SW/4; reg. Gov. 1/16 sec. |
40 |
400' |
|
19-57 |
Miller |
Smackover |
Within 1000' of C. of Gov sec |
640 |
200' min., 1800' cem. Into |
|
19-57(A) |
Smackover |
Correct 19-57 - Rule I Wording |
||||
13-60 |
Smackover |
Amend 19-57 to add Rules 9-10 - Allow. |
||||
4-62 |
Miller |
1st Sturgis Sand |
Unitized portion of 1st Sturgis sand |
|||
13-65 |
Unitized Beauford sand |
|||||
73-67(A) |
Buckrange, Tokio, Tuscaloosa & Paluxy |
Except zones covered by 73-67B; 280' FUB N/2 S/2 E/2 W/2 of 1/4 1/4 sec. |
20 |
100' (0-3000') 160' (3000-4000') |
||
73-67(B) |
Holman, Zanger, Silberberg & other Paluxy Below 4th Sturgis and Glen Rose |
330' FUB |
40 |
300' |
||
34-70 |
Miller |
First Sturgis Southwest |
Unitized |
|||
68-71 |
Miller |
Smackover |
Delete 29 & 32-T16S-R26W from Ord. 19-57 Purview |
|||
53-72 |
First Tokio Paluxy |
Unitized Below 4th Sturgis Glen Rose |
||||
104-79 |
Miller |
Smackover |
Ext. Ord. 19-57A & 13-60 to cover S/2 S/2 25 & N/2 N/2 36-T16S-R27W |
|||
324-85 |
Miller |
Ext. Ord. 19-57 to cover 30-T16S-R26W - 594' FSL |
||||
32-95 |
Kilpatrick |
280' FUB N/2 or S/2 of gov. 1/4 1/4 sec. |
20 |
B-15 |
||
81-99 |
Paluxy |
660' FUB of gov. 1/4 1/4 sec. |
160 |
300' |
||
150-2000-11 |
Miller |
Paluxy |
N/2 SE/4 SW/4 and the S/2 SE/4 SW/4 of Sec. 32-16S- |
|||
151-2000-11 |
Miller |
Paluxy |
SW/4 SE/4 Sec. 36-16S-27W |
|||
46-2002-04 |
Miller |
1st Sturgis "C" |
Ext. Unitized Area - Ord. 27-54 - S/2 SE/4 36-T16S-R27W; NE/4 E/2 W/2, W/2 SE/4, E/1 SW/4 SW/4 1-T17S-R27W; NE/4 NW/4 & E/2 NW/4 NW/4, NW/4 NE/4 12-T17S-R27W |
600 |
||
101B-2002-08 |
Miller |
Paluxy (2nd & 3rd Sturgis, Sturgis "D") |
Establish Field-Wide Unit - 2 & 11-T17S-R27W |
400 |
||
97-2003-08 |
Miller |
Paluxy (Sturgis 3 & 3A) |
Estalbish Field-Wide Unit |
463.79 |
||
98-2003-08 |
Miller |
Paluxy (4th Sturgis "F") |
Establish Field-Wide Unit |
585.19 |
||
343-1-2007 -08 |
Miller |
Paluxy |
Ext. 14-40 to cover N/2 NW NE 1-T17S-R27W & S/2 SW 36-T16S-R27W |
|||
297-2008-05 |
Miller |
Paluxy |
Amend and Correct Order 343-1-2007-08 to clarify a bore hole unit only |
|||
153-2012-06 |
Miller |
Tokio |
Exc. bore hole unit only - SW/4 NW/4 SW/4 & NW/4 SW/4 SW/4 of Sec. 32-T16S-R26W - Hunter-Collins #1 |
20 |
||
154-2012-06 |
Miller |
Paluxy |
Exc. bore hole unit - SE/4 NW/4 SE/4 & NE/4 SW/4 SE/4 Sec. 31-T16S-R26W - Goldman-Mariman #1 |
20 |
||
252-2013-10 |
Miller |
Paluxy |
Exc. D.U.: SW/4 SW4 NE/4 & NW/4/ NW/4 SE/4 of Sec. 32-T16S-R26W |
20 |
||
FOUKE NORTH |
15-53 |
Miller |
Paluxy-upper |
within 50' C. two 1/4 1/4 1/4 N/2 S/2 E/2 or W/2 Gov. |
20 |
400' |
15-53 |
Basal-Tuscaloosa |
E/2 W/2 Gov. 1/4 1/4 |
||||
56-60 |
Amend Casing Requirements |
160' - Max. depth of 4000' |
||||
33-63 |
Upper Tuscaloosa |
Unitized |
||||
38-78 |
Comm. |
|||||
105-81 |
Smackover |
480' FUB any two 1/2 gov. 1/4 sec in the shape of a square |
160 |
1250' |
||
091A-2015-07 |
Miller |
Upper Tuscaloosa |
Dissolve and terminate EOR Unit created by Order No. 33-63 (and another EOR unit in another field) |
|||
FOUKE WEST |
16-53 |
Miller |
Paluxy |
50' of C. of 1/4 1/4 1/4 sec |
10 |
150' |
57-68 |
Mooringsport |
280' FUB Gov. 1/4 1/4 sec. |
40 |
300' |
||
17-73 |
Paluxy 4320'-5520' |
280' FUB Gov. 1/4 1/4 sec. |
40 |
300' |
||
30-75 |
Paluxy |
Amend 17-73 to apply to all zones & 280' FUB |
||||
81-90 |
Paluxy |
Comm. |
||||
5-94 & Corr. |
Smackover |
660' FUB of two irregular D. U. |
660' (1) 640' (2) |
B-15 |
||
51-94 |
Smackover |
660' FUB of two irregular D. U. |
600' |
|||
40-96 |
Smackover |
Amend to form irregular D.U. |
||||
67-96 |
Mooringsport |
Ext. to cover SE/4 NW/4 of Sec. 30-17S-27W of gov. 1/4 1/4 sec. |
||||
46-2002-04 |
Miller |
Paluxy |
Amend, Extend and Enlarge 1st Sturgis C. Field Wide Unit |
|||
FOUR MILE CREEK |
15-73 |
Miller |
Smackover |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 sec. |
80 |
1000' |
FOUR MILE CREEK SOUTH |
147-87 |
Miller |
Smackover |
330' FUB |
320 |
B-15 |
FT. LYNN |
18-54 |
Miller |
Rodessa |
Within area formed by connections C. of four 1/4 1/4 sec. |
160 |
1200' of 9 5/8 or 103/4 |
25-59 |
Miller |
Rodessa |
Amend to add balancing mechanism & period |
|||
25-68 |
Tokio |
280' FUB N/2 S/2 E/2 W/2 of gov. 1/4 1/4 sec. |
20 |
160' |
||
155-84 |
Rodessa |
280' FUB for Sec 16-18S-27W |
||||
263-84 |
Dees Lime |
Casing Rule B-15 |
||||
218-85 |
Rodessa |
Amend Location provisions 280' FUB |
||||
GALILEE CHURCH |
5-76 |
Miller |
Smackover |
660' FUB Gov. 1/4 sec. |
160 |
1000' |
GARLAND CITY NEW |
8-52 |
Miller |
Paluxy |
50' of C. of ten acre tract |
10 |
100' |
57-59 |
Buckrange |
50' of C. of ten acre tract N/2 & S/2 E/2 W/2 Gov. 1/4 1/4 |
20 |
150' |
||
GENOA |
29-57 |
Miller |
Paluxy |
50' of C. of two Gov. 1/4 1/4 1/4 sec. N/2 S/2 E/2 W/2 |
20 |
100' |
45-59 |
Paluxy |
Amend to 50' of C. of two reg. Gov. 1/64 sec.; N/2, S/2, E/2 or W/2 reg. Gov. 1/16 sec. |
20 |
|||
47-63 |
Miller |
Purifoy (Tokio) Sand Unit |
Unitized |
|||
6-62 |
Miller |
Young Sand |
Unitized |
|||
287A-2014-08 |
Miller |
Young Sand |
Dissolution of Young Sand Unit - Order No. 6-62 |
|||
091A-2015-07 |
Miller |
Purifoy (Tokio) Sand Unit |
Dissolve and terminate EOR Unit created by Order No. 47-63 (and another EOR unit in another field) |
|||
GOODMAN CREEK |
222-2012-09 |
Union |
Cotton Valley |
280' FUB. Gov 1/4 1/4 sec. |
40 |
B-15. Min of 300' |
GOODMAN CREEK EAST |
011-1-2019-03 |
Union |
Cotton Valley |
DU - NE/4 SW/4 of Sec 17-T16S-R14W. |
40 |
|
011-2-2019-03 |
Union |
Cotton Valley |
NE/4 SW/4 of Sec 17-T16S-R14W. Gov 1/4 1/4 sec. 280' FUB. 60 BOPD. |
40 |
B-15. Min of 500' |
|
GOLD POINT CHURCH |
203-87 |
Miller |
Smackover |
660' FUB of N/2 S/2 E/2 or W/2 of gov sec |
320 |
500' |
GRAVES CREEK |
10-92 |
Union |
Hill |
330' FUB; Gov 1/4 1/4 Sec |
40 |
300' |
GRAYSON |
37-93 |
Columbia |
Smackover |
330' FUB N/2 S/2 E/2 W/2 of gov. 1/4 sec. |
80 |
B-15 |
41-95 |
Smackover |
Unitization |
||||
GREEN GROVE |
257-84 |
Union |
Blossom |
280' FUB of N/2 S/2 E/2 W/2 of gov 1/4 1/4 sec |
20 |
100' |
258-84 |
Travis Peak |
280' FUB of gov 1/4 1/4 sec |
40 |
B-15 |
||
GREER'S CHURCH |
85-79 |
Columbia |
Pettet |
N/2 S/2 E/2 W/2 of Gov. 1/4 sec |
80 |
300' |
GREGORY |
72-78 |
Union |
Cotton Valley |
330' FUB 1000' between wells |
160 |
B-15 |
41-81 |
Union |
Cotton Valley (Jones) |
Ext. to cover S/2 Sec. 21, S/2 Sec. 22, N/2 Sec. 27, N/2 Sec. 28, NW/4 Sec. 26-T19S-R18W |
|||
Cotton Valley (GasProduction) |
Ext. to cover S/2 Sec. 21, SE/4 & NW/4 of Sec. 22-T19S-R18W. Max allowable 1000 mcf per day + all liquid hydrocarbons |
|||||
GUM CREEK |
22-45 |
Ouachita |
Nacotoch, Blossom, Tokio, Glen Rose, Travis Peak |
Est. Field Rules |
||
10-48 |
Nacatoch, Blossom & Tokio |
330' FUB |
10 |
100' |
||
23-64 |
Travis Peak (Hosston) |
280' FUB Gov. 1/4 1/4 sec. |
40 |
100' (0-3000') |
||
20-65 & Corr. |
Glen-Rose |
280' FUB Gov. 1/4 1/4 sec. |
40 |
560' subsea |
||
21-65 |
Cotton Valley |
280' FUB Gov. 1/4 1/4 sec. |
40 |
560' subsea |
||
68-65 |
Smackover |
280' FUB N/2 E/2 S/2 W/2 gov. 1/4 sec. |
80 |
560' subsea |
||
35-66 |
Travis Peak Sands |
Comm. |
||||
48-72 |
Travis Peak |
Comm. |
||||
302-1-2008-06 |
Creation of Exc. D.U. - S/2 SE/4 NE/4 NW/4 & N/2 NE/4 SE/4 NW/4 of Sec. 27-T15S-R18W |
10 |
||||
609-1-2009-08 |
Creation of Exc. D.U.- S/2 SE/4 NE/4 NW/4 and the N/2 NE/4 SE/4 NW/4 of Sec. 27-T15S-R18W |
10 |
||||
575-2010-12 |
Ouachita |
Rescind Order # 105-79. Creation of Exc. D.U. - S/2 NE/4 SW/4, S/2 NW/4 SE/4, N/2 SE/4 SW/4, N/2 SW/4 SE/4 |
80 |
|||
HARPER CREEK |
112-86 |
Cotton Valley |
330' FUB E/2 W/2 of gov. 1/4 sec. |
80 |
Statewide requirements |
|
HAYNESVILLE |
30-42 & Corr. |
Columbia |
Pettet |
100' of C. of an alternate N-S 1/4 1/4 out of a N-S 80 unit |
80 |
200' |
7-44 |
Pettet |
Unitized |
||||
20-51 |
Columbia |
Pettet |
Unitized |
|||
3-68 |
Amend 7-44 - Unitization & Pressure Maintenance Agreement |
|||||
38-68 |
Columbia |
Pettet |
Enlarge unitized area to cover N. 25.23 ac. NE/4 SE/4 & S 54.77 ac. East/2 NE/4 Sec. 27-T19S-R20W |
. 80 |
||
32-72 |
Columbia & Claiborne Parish, LA |
Pettet Lime |
Enlarge unitized area to cover W/2 NW/4 28-T23N-R8W |
|||
51-72 |
Cotton Valley |
660' FUB Gov. 1/4 sec. |
160 |
1250' |
||
23-75 |
Claiborne Parish, LA |
Enlarge unitized area to cover W/2 SW/4 Sec. 27-T23N-R8W |
||||
145-85 |
Columbia |
Pettet |
Extend 30-42 to cover W/2 NW (52.08 ac.) & W/2 SW/4 Sec. 34-T19S-R20W (27.92 ac.) |
80 |
||
HAYNESVILLE NORTH |
22-62 |
Columbia |
Pettet |
E/2 or W/2 of 1/4 sec. within 200' of C. of NW/4 or SE/4 of 1/4 sec. |
80 |
500' |
68-64 |
Smackover (B) |
Unitized |
160 |
|||
28-82 |
Cotton Valley |
660' FUB Gov. 1/4 sec in shape of square |
||||
188-86 |
Cotton Valley & Haynesville |
660' FUB of gov 1/4 sec |
160 |
1250' |
||
61-87 |
Columbia |
Cotton Valley |
Ext. 188-86 to cover Sec. 1 & Frc. Sec. 12-T20S-R20W & remove SE/4 Sec. 1-T20S-R20W from Ord. 28-82 |
|||
HENDERSON CREEK |
74-76 |
Columbia |
Travis Peak |
280' FUB of gov 1/4 1/4 sec |
40 |
300' |
HIBANK |
6-53 |
Union |
Graves & Meakin |
Within 50' of C. 1/4 1/4 1/4 sec. |
10 |
100' |
27-53 |
Tuscaloosa |
50' of line conn C. of two 1/4 1/4 1/4 sec N/2 S/2 E/2 W/2 1/4 1/4 sec. |
20 |
150' |
||
13-59 |
Cotton Valley |
330' FUB gov. 1/4 1/4 sec. |
40 |
100' |
||
46-61 |
Pettet |
280' FUB N/2 S/2 E/2 W/2 gov. 1/4 1/4 sec |
20 |
160' |
||
34-63 |
Travis Peak (Hogg) 3900'-4000' |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
160' |
||
8-87 |
Union |
Graves & Meakin |
Dissolve 10-ac. units of Ord. 6-53 - SE NW SW & SW NW SW Sec. 19-T18S-R14W & create irreg. unit N/2 S/2 NW/4 SW/4 19-T18S-R14W |
|||
HIBANK CREEK |
3-59 |
Union |
Tuscaloosa |
50' of line conn C. two 1/4 1/4 1/4 sec N/2 S/2 E/2 W/2 1/4 1/4 sec. |
20 |
100' |
HILLSBORO |
84-82 |
Union |
Travis Peak |
280' from unit bound 1/4 1/4 gov. sec. |
20 |
160' (3000-4000') |
36-84 |
Primm |
660' FUB of gov. 1/4 sec. |
160 |
100' |
||
338-84 |
Primm |
Ext to cover SW/4 Sec. 7-18S-13W |
||||
HILLSBORO SOUTH |
89-65 |
Union |
Rodessa |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
160' |
50-66 |
Pine Island & Travis Peak |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
300' |
||
13-68 |
Travis Peak (gas sand) |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
40 |
300' |
||
HOGG |
190-84 |
Union |
Cotton Valley |
330' FUB of gov 1/4 1/4 sec and 660' from existing Cotton Valley well |
40 |
B-15 |
HOLMES CREEK |
15-59 |
Union |
Blossom |
50' from C of NE/4 & SW/4 of N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
28-60 |
Blossom |
50' NW/4 SE/4 of E/2 W/2 gov. 1/4 1/4 sec |
20 |
100' |
||
61-60 |
Blossom |
Amend spacing 50' of line Conn. C of two 10-acre tracts |
||||
48-69 |
Tokio |
Ext to cover W/2 Sec. 14, all of Sec. 15, E/4 Sec. 16, N/2 N/2 Sec. 22, N/2 NW/4 Sec. 23-16S-16W |
||||
121-79 |
Blossom |
280' FUB Gov. 1/4 1/4 1/4 sec. |
10 |
100' |
||
HORSEHEAD |
9-52 |
Columbia |
Pettet |
Not more than 200' from C. of NW/4 or SE/4 E/2 or W/2 of 1/4 sec. Not nearer than 1467' to each other |
80 |
500' |
17-57(C) |
Pettet |
Unitized |
||||
029A-2016-04 |
Columbia |
Pettet |
Dissolution of Field-Wide Unit created by Order No. 17-57(c) |
|||
HORSEHEAD CREEK |
239-85 |
Columbia |
Smackover |
660' FUB of gov. 1/4 sec. |
160 |
B-15 |
IRMA |
46-53 |
Nevada |
Travis Peak |
50' of line Conn. C. of two 1/4 1/4 1/4 E/2 W/2 1/4 1/4 sec. |
20 |
100' |
44-63 |
Paluxy, Upper Tokio Lower Tokio |
280' FUB E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
||
54-64 |
Nacatoch |
Unitized |
||||
42-67 |
Nevada |
Nacatoch |
Unitized |
|||
13-72 |
Smackover |
280' FUB; Gov. 1/4 1/4 sec. |
40 |
300' |
||
68-94 Corr. |
Nevada |
Rodessa |
280' FUB; Gov 1/4 1/4 sec. |
40 |
300' |
|
30-2000-03 |
Smackover |
Ext to cover N/2 SE/4 SW/4& S/2 E/4 SW/4 Sec. 31-13S-20W |
||||
JENNINGS |
6-91 |
Columbia |
Cotton Valley |
330' FUB; Gov 1/4 Sec |
160 |
B-15 |
28-92 |
Cotton Valley |
Ext. to cover N/2 of irregular W/2 SW/4 & S/2 of irregular W/2 NW/4 Sec. 19-19S-18W |
||||
68-93 |
Cotton Valley |
Ext. to cover SE/4 Sec 13-19S-19W |
||||
KELLY BAYOU |
43-62 |
Miller |
Jeter/Rodessa |
200' of C; NW/4 or SE/4 of E/2 or W/2 Gov. 1/4 sec. |
80 |
500' |
11-63 |
Jeter/Rodessa |
Ext. to cover W/2 29, 19, 30-33-T19S-R27W; 23-26, 35-36-T19S-R28W; 3-10 & pt. 15-18-T20S-R27W; 1-2-T20S-R28W & add Rule 9 - Gas/Oil ratio |
||||
45-63 |
Miller |
Amend 43-62 & 11-63 to realign into N-S 80-ac. Units -SE/4 31-T19S-R27W |
80 |
|||
52-63 |
Miller |
Jeter/Rodessa |
Amend 43-62 & 11-63 to realign into N-S 80-ac. Units - E/2 9-T20S-R27W |
80 |
||
56-63 |
Miller |
Jeter |
Unitized |
|||
27-64 |
Miller |
Jeter/Rodessa |
Unitized |
|||
44-64 |
Miller |
Jeter/Rodessa |
Unitized |
|||
14-65 |
Miller |
Jeter/Rodessa |
Delete 7 & Frc. 18-T20S-R27W |
|||
77A-2008-02 |
Miller |
Jeter |
Rescind Order No. 56-63, as amended |
|||
86-2008-02 |
Miller |
Jeter/Rodessa |
Delete Sec. 26-T19S-R28W |
|||
87-2008-02 |
Miller |
Jeter/Rodessa |
Delete Sec. 35-T19S-R28W |
|||
370-1-2014-12 |
Miller |
Jeter/Rodessa |
Unitized |
|||
086-2015-07 |
Miller |
Jeter/Rodessa |
Amend & Remand of 370-2014-12 - Amend tract factors |
|||
006-2016-01 |
Miller |
Jeter/Rodessa |
Extend Order Nos. 370-1-2014 -12, 370-2-2014 -12, & 086-2015-07 |
|||
032-2016-05 |
Miller |
Jeter/Rodessa |
Extend Order Nos. 370-1-2014 -12, 370-2-2014 -12, 086-2015-07, & 006-2016-01 |
|||
KEOUN CREEK |
4-83 |
Lafayette |
Smackover |
1,320 FUB Gov sec. |
640 |
Rules B-15 |
270-83 |
Columbia & Lafayette |
Smackover |
Ext. to cover 34-T19S-R23W Gov. sec. |
|||
35-84 |
Haynesville |
660' FUB of N/2 or S/2 or Gov. sec. |
320 |
1500' |
||
189-84 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 2-T20S-R23W; disolve 34-84 & create D.U. S/2 sec. 35-T19S-R23W & N/2 Sec. 2-T20S-R23W |
640 |
||
383-84 |
Columbia & Lafayette |
Haynesville |
Ext. 35-84 to cover S/2 36-T19S-R23W & 1, 2, 3, 4-T20S-R23W; N/2 or S/2 |
320 |
||
384-84 |
Columbia |
Smackover |
Ext. 4-83 to cover N/2 1-T20S-R23W & S/2 36-T19S-R23W & D.U. S/2 Sec. 36-T19S-R23W & N/2 1-T20S-R23W |
640 |
||
6-86 |
Pettet |
330' FUB of E/2 or W/2 of Gov. 1/4 sec. |
80 |
500' |
||
122-86 |
Columbia |
Smackover |
Rescind 42-86A & ext. Field Rules to cover S/2 31-T19S-R22W (taken from Welcome Fld.) |
|||
KERLIN PETTET |
18-70 |
Columbia |
Smackover |
Redesignate field rules from Calhoun to Kerlin Brine Field |
||
35-77 |
Columbia |
Pettet |
460' from unit bound Gov. 1/4 1/4 sec. |
40 |
150' |
|
27-78 |
Pettet |
280' FUB by Director |
||||
91-78 |
Columbia |
Pettet |
Ext. to cover NW/4 & NW/4 SW/4 Sec. 9-T17S-R20W |
|||
9-79 |
Columbia |
Pettet |
Ext. to cover NE/4 SW/4 & S/2 SW/4 Sec. 9, NW/4 & N/2 SW/4 Sec. 16-T17S-R20W |
40 |
||
34-79 |
Columbia |
Pettet |
Ext. to cover W/2 NE/4 Sec. 9; S/2 SE/4, W/2 NE/4 & W/2 Sec. 4-T17S-R20W |
|||
217-82 |
Pettet |
Create 2 sep. distinct zones: Res. "A" & Res. "B") |
||||
224-82 |
Pettet |
Unitized |
||||
368-85 |
Cotton Valley |
280' FUB; commingling in well bore |
80 |
B-15 |
||
KIBLAH |
3-54 |
Rodessa |
Not to exceed 175 bbls./day |
|||
24-54 |
Lafayette |
Gloyd |
150' of line conn C. of two 1/4 1/4 sec. E/2 or W/2 of 1/4 sec. |
80 |
500' |
|
14-59 |
Lafayette |
Gloyd |
Ext. to cover NE/4 SW/4 Sec. 32-T19S-R26W |
|||
7-60 |
Lafayette |
Gloyd |
Amend Surface casing |
500' |
||
149-84 |
Gloyd |
Amend 24-52 to 330' FUB & ext. to cover SW/4 & E/2 Sec. 1 & N/2 Sec. 12-T20S-R27W; E/2, W/2, N/2 or S/2 of Gov 1/4 sec. |
||||
187-84 |
Miller |
Pettet |
B-38 waived for Pettet Formation |
|||
85-87 |
Mitchell |
Amend Gloyd Field Rules to cover the Mitchell |
||||
26-88 |
Miller |
Hill |
Ext. 24-54 to cover N. 3/4 E/2 Sec. 7 & N3/4 W/2 Sec. 8-T20S-R26W, Hill Formation - 280' FUB; N/2, S/2, E/2 or W/2 Gov. 1/4 sec. |
80 |
||
27-88 |
Miller |
Hill |
Ext. 26-88 to cover 12-T20S-R27W; 2 contig. 40-ac. Gov. 1/4 1/4 sec. - E-W or N-S |
80 |
||
12-89 |
Tokio |
280' FUB of Gov. 1/4 1/4 sec. |
40 |
B-15 |
||
346A-2007-08 |
Miller/Lafayette |
Rescind Order No. 5-62, as amended (Kiblah Goyd Field Wide Unit |
||||
KILGORE LODGE |
12-66 |
Columbia |
Smackover |
Casing program for Brine supply wells |
500' |
4500' |
23-69 |
Smackover |
200' of line conn C. of two 1/4 1/4 sec N/2 S/2 E/2 W/2 of 1/4 sec. |
80 |
1000' |
||
KRESS CITY |
39-58 |
Lafayette |
Travis Peak |
100' of C. of Gov. 1/4 1/4 sec. |
40 |
500' |
8-76 |
Ford |
660' FUB & not closer than 1,320' to any well producing from Ford zone |
160 |
1000' |
||
61-77 |
Lafayette |
Ford |
Ext. 8-76 to cover SW/4 22 & SE/4 21-T16S-R24W; Reg. Gov. 1/4 sec. |
|||
11-78 |
Lafayette |
Ford |
Ext. 8-76 & 61-77 to cover NW/4 22-T16S-R24W |
|||
20-78 |
Lafayette |
Ford |
Ext. 8-76, 61-77, 11-78 to cover SE 22, NE 28-T16S-R24W |
160 |
||
134-80 |
Smackover |
Unitized |
||||
45-89 |
Mitchell |
280' FUB of Gov. 1/4 1/4 sec |
40 |
300' |
||
LAKE ERLING |
41-60 |
Lafayette |
Smackover |
1320' from center of Gov. sec. |
640 |
1800' |
31-62 |
Comm. |
|||||
126-83 |
Smackover |
Amend location provisions 1320' FUB |
||||
141-84 |
Lafayette |
Smackover |
Ext. to cover 29-T19S-R24W |
|||
339-84 |
Ext. to cover S/2 36-T19S-R24W & N/2 1-T20S-R24W |
|||||
18-85 |
Lafayette |
Cotton Valley |
660' FUB |
160 |
1250' |
|
70-85 |
Lafayette |
Smackover |
Ext. to cover 27-T19S-R24W |
|||
274-85 |
Lafayette |
Smackover |
Ext. to cover 2-T20S-R24W |
|||
7-86 |
Lafayette |
Smackover |
Ext. to cover S/2 36-T19S-R24W & N/2 1-T20S-R24W |
640 |
||
164-86 |
Lafayette |
Smackover |
Ext. to cover 26-T19S-R24W |
|||
99-90 |
Abolish D.U. S/2 Sec. 25 & N/2 Sec. 36-T19S-R24W |
|||||
85-92 |
Smackover |
Unitized |
||||
LAKE ERLING EAST |
71-92 & Corr. |
Lafayette |
Hill (Rodessa) |
280' FUB; 1/2 Gov. 1/4 sec. - N/S or E/W |
80 |
500' |
129-2002-10 |
Lafayette |
Rodessa "Hill Sand" |
Township 20 South, Rand 24 West, Amend field rules for the Lake Erling East Field |
|||
LAKE ERLING SOUTH |
10-86 & 11-86 |
Lafayette |
Smackover |
660' FUB of N/2 or S/2 of gov sec |
320 |
1500' |
15-89 |
Tokio |
330' FUB N/2 S/2 E/2 or W/2 of gov 1/4 1/4 sec |
20 |
B-15 |
||
85-92 |
Unitize |
|||||
82-2001--05 |
Lafayette |
Haynesville |
660' from the East Line and 1,200 feet from the South Line |
160 |
||
LANEY ROAD |
21-2004-03 |
Union |
Cameron Zone of the Cotton Valley Formation |
Establish field rules and create drilling units in section 19-19S-16W |
40 |
1,600 |
053-2012-03 |
Union |
Cameron Zone of the Cotton Valley Formation |
Unitized |
220 |
||
LANGLEY |
68-67 |
Ouachita |
Buckrange |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
LAPILE |
3-78 |
Union |
Cotton Valley |
280' FUB Gov. 1/4 1/4 sec. |
40 |
500' |
57-89 |
Cotton Valley |
Unitized |
||||
LAPILE EAST |
72-96 |
Cotton Valley |
280' FUB of gov. 1/4 1/4 sec. |
40 |
300' |
|
LAWSON |
27-56 |
Union |
Graves |
467' of C. of drilling unit Gov. 1/4 sec. |
160 |
100' |
38-58 |
Travis Peak |
50' of line Conn. .C Gov. 1/4 1/4 1/4 N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
||
59-66 |
Meakin |
280' FUB E/2 or W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
||
LAWSON NORTH |
48-89 |
Upper Graves |
280' FUB N/2 S/2 E/2 or W/2 of Gov 1/4 1/4 sec. |
20 |
160 |
|
LAWSON SOUTH |
8-55 |
Primm |
660' from property or division line of drilling unit |
160 |
125' |
|
36-84 |
Primm |
Dissolve SE/4 Sec. 1 & NE/4 Sec. 12-T18S-R14W (See Hillsboro Field) |
||||
LEWISVILLE |
22-39 |
Lafayette |
Glen Rose |
330' FUB & 660' from drag or completed well |
20 |
100' |
15-61 |
Paluxy Down Thrown |
50' of line conn. c. of two 1/4 1/4 1/4 sec. E/2 or W/2 Gov. 1/4 sec. |
1/4 20 |
200' |
||
26-61 |
Paluxy Downthrown |
Amend 15-61with regard to W/2 SE/4 SW/4 13-T16S-R24W to permit simultaneous production of all zones |
||||
40-62 |
Paluxy Downthrown |
Amend 15-61 with regard to SE SW 13-T16S-R24W to permit simultaneous production of all zones |
||||
11-66 |
Lafayette |
Rodessa |
Unitized |
|||
55-69 |
Smackover Limestone |
280' FUB adjoining unit to be any two 1/4 1/4 sec. with long axis to be E-W or N-S |
80 |
750' |
||
22-74 |
Paluxy Up Thrown |
280' FUB N/2 or S/2 Gov. 1/4 1/4 sec. |
20 |
160' |
||
21-75 |
Smackover Limestone |
Unitized |
||||
LEWISVILLE NE |
129-2004-10 |
Lafayette |
SMACKOVER LIMESTONE |
ESTABLISH FIELD RULES 330 FEET FUB N/2 SW/4 & NW/4 SE/4 SEC. 1-16S-24W |
120 |
1000' |
138-2004-10(4) |
Lafayette |
EXTENSION OF CONFIDENTIALITY PERIOD OF LOGS |
||||
57-2005-05 |
Lafayette |
NOT SHOWN IN MINUTES |
AMEND 129-2004-10 FIELD RULES TO ADD SECOND WELL TO PREVIOUSLY ESTABLISHED ONE WELL |
|||
LEWISVILLE NW |
144-2004-12 |
Lafayette |
SMACKOVER LIMESTONE |
ESTABLISH FIELD RULES 330 FEET FUB PORTION OF SEC. 5-16S-24W |
1,000 |
|
LEWISVILLE OLD TOWN |
45-57-A |
Lafayette |
Tuscaloosa |
50' of line conn. C. of two 1/4 1/4 1/4 sec. N/2 S/2 E/2 W/2 Gov. 1/4 1/4 |
20 |
100' |
45-57-B |
Paluxy |
50' of line conn. C. of two 1/4 1/4 1/4 sec. N/2 S/2 E/2 W/2 Gov. 1/4 1/4 |
20 |
100' |
||
38-60 |
Magee Paluxy |
50' of line conn. C. of two 1/4 1/4 1/4 sec. E/2 W/2 Gov. 1/4 1/4 |
20 |
100' |
||
15-65 |
Tuscaloosa |
Unitized |
||||
95-82 |
Mooringsport |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
300' |
||
36-83 |
Sligo |
280' FUB Gov. 1/4 1/4 sec. |
40 |
300' |
||
377-2009-05 |
Lafayette |
Kilpatrick Limestone |
Ext. Kilpatrick Limestone. 50 BOPD |
B-15 |
||
383-2010-06 |
Lafayette |
Exceptional 80 acre unit - S 330' of the SE/4 of the SW/4 and the S 330' of the SW/4 of the SE/4 of Sec. 3 and the N 990' of the NE/4 of the NW/4 and the N 990' of the NW/4 of the NE/4 of Sec. 10-T16S-R24W |
80 |
|||
014-2014-01 |
Lafayette |
Hill Sand |
E 3/4 S/2 SE/4 SW/4 & W/2 SW/4 SW/4 SE/4 of Sec, 3-T16S-R24W. Expires 2/14/15. |
20 |
||
016-1-2014-01 |
Lafayette |
Dissolution of Magee Water Injection Project (Order No. 24-69), and Baker Sand Waterflood Unit (Order No. 15-65) |
||||
016-2-2014-01 |
Lafayette |
Tuscaloosa Sand |
Exceptional 80 acre unit - East 3/4 S/2 SE/4 SW/4 & W/2 SW/4 SW/4 SE/4 of Sec. 3-T16S-R24W |
20 |
||
354-2014-12 |
Lafayette |
Tokio |
Amend to include Tokio Formation. Created D.U. = East 3/4 S/2 SE/4 SW/4 & W/2 SW/4 SW/4 SE/4 Sec. 3-T16S-R24W & auto extensions. 40 BOPD / well |
20 |
B-15 |
|
027-2015-02 |
Lafayette |
Ferry Lake Anhydrite |
Amend to include Ferry Lake Anydrite Formation. Create D.U. = S/2 NE/4 NW/4, S/2 NW/4 NE/4, N/2 SE/4 NW/4, N/2 |
80 |
B-15 |
|
LEWISVILLE WEST |
22-51 |
Lafayette |
Tokio-Paluxy |
50' of line conn. c. of two 1/4 1/4 1/4 sec E/2 W/2 1/4 1/4 sec. |
20 |
100' |
3-71 |
Smackover |
280' FUB Gov. 1/4 1/4 sec. |
40 |
750' |
||
13-81 |
Tokio-Paluxy |
Amend Loc. Prov. to N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
||||
145-86 |
Smackover |
Unitized |
||||
LIBERTY CHURCH |
4-76 |
Lafayette |
Smackover |
330' FUB and 1000' a part E/2 W/2 Gov. 1/4 |
80 |
1000' |
125-81 |
Ford |
330' FUB and 1000' a part Gov. 1/4 sec |
160 |
1000' |
||
209-81 |
Smackover |
Ext to cover E/2 SW/4 W/2 SW/2 Sec. 28-36S-23W |
||||
56-97 |
Smackover |
Ext. to cover S/2 SE/4 Sec. 28 & N/2 NE/4 Sec. 33 & S/2 SW/4 Sec. 27 & N/2 NW/4 Sec. 34-16S-23W |
||||
LICK CREEK |
7-58 |
Union |
Meakin |
50' of line Conn c. of Gov. 1/4 1/4 1/4 sec. N/2 S/2 E/2 W/2 1/4 1/4 sec. |
20 |
100' |
19-70 |
Travis Peak |
280' FUB Gov. 1/4 1/4 1/4 sec. |
10 |
100' |
||
47-70 |
Cotton Valley |
280' FUB of any two 1/4 1/4 1/4 sec with long axis to be E-W or N-S |
20 |
160' |
||
62-74 |
Meakin |
Unitized |
||||
79-99 & 80-99 |
Meakin |
Rescind Order No 62-74 (Unitized) |
||||
LISBON |
568-2008-12 |
Union |
Cotton Valley Formation |
280' FUB. 60 barrel per day allowable |
80 |
800' |
LISBON NORTH |
44-55 |
Union |
Nacatoch |
50' of C Gov. 1/4 1/4 1/4 sec. |
10 |
100' |
LISBON NORTHWEST |
38-61 |
Union |
M. Blossom |
280' FUB Gov. 1/4 1/4 1/4 sec. |
10 |
100' |
27-62 |
M. Blossom |
Amend size of units 280' FUB of Gov 1/4 1/4 1/4 sec |
10 |
|||
30-64 |
Union |
Blossom, Lower & Middle |
Comm. |
|||
69-64 |
M. Blossom |
Unitized |
||||
76-92 |
Blossom |
Tertiary Recovery |
||||
30-64 |
Union |
Blossom - Lower & Middle |
Comm. |
|||
LISBON WEST |
19-55 |
Union |
Nacatoch |
50' of C. of Gov. 1/4 1/4 1/4 sec. |
10 |
100' |
LITTLE BODCAW |
170-83 |
Lafayette |
Tokio |
330' FUB of E/2 W/2 N/2 or S/2 of Gov 1/4 1/4 sec. |
20 |
100' |
LITTLE CHURCH |
259-84 |
Miller |
Tokio |
280' FUB of Gov 1/4 1/4 sec. |
40 |
B-15 |
186-84 |
Tuscaloosa |
280' FUB of Gov 1/4 1/4 sec. |
40 |
300' |
||
2-93 |
Paluxy |
280' FUB of gov. 1/4 1/4 sec. |
40 |
500' |
||
LLOYD CREEK |
4-69 |
Calhoun |
Nacatoch |
280' FUB or 660' from any other Nacatoch well |
40 |
100' |
LOCUST BAYOU |
8-48 |
Calhoun |
Meakin |
50' of C. NE 1/4 1/4 1/4 sec. or SW1/4 1/4 1/4 of Gov. sec. |
20 |
90' |
LOWERY BRANCH |
123-2001-07 |
Union |
Smackover |
S/2 SE/4 Sec. 21 & N/2 NE/4 Sec. 28-19S-17W |
160 |
1,600 |
MACEDONIA CHURCH |
023-2014-01 |
Union |
Middle and Lower Smackover |
SW/4 Sec. 35-T18S-R17W & auto ext. 280'FUB. Gov 1/4 1/4. 150 BOPD |
160 |
B-15 |
MAGNOLIA |
9-39 |
Columbia |
Smackover |
660' FUB not closer than 1320' from other wells |
40 |
1000' |
21-39 |
Lime |
Amend 9-39 - Gas measurement |
||||
38-40 |
Amend 9-39 - Allocation |
|||||
5-48 |
Cotton Valley |
200' of C. of gov. 40-acre unit |
40 |
1500' |
||
28-50 |
Columbia |
Cotton Valley |
Amend 5-48 to permit production in more than one zone |
|||
7-56 |
Smackover |
Unitized |
||||
19-77A |
Travis Peak |
280' FUB Gov. 1/4 1/4 |
40 |
750' |
||
19-77B |
Cotton Valley |
Amend surface casing & Ext. to cover S/2 SW/4 & SW/4 SE/4 Sec. 18, NW/4 & W/2 NE/4 & NW/4 SE/4 & N/2 SW/4 Sec. 19-17S-19W; S/2 Sec. 13, S/2 Sec. 14, SE/4 of Sec. 15, NE/4 Sec. 22, N/2 & N/2 S/2 Sec. 23, N/2 & N/2 S/2 Sec. 24-17S-20W |
750' |
|||
84-79 |
Columbia |
Travis Peak & Cotton Valley |
Comm. |
|||
26-89 |
Pettet |
330' FUB of Gov. 1/4 1/4 sec. |
40 |
B-15 |
||
275-2011-10 |
Columbia |
Pettet Limestone |
Amend to include Pettet Limestone; W/2 NW/4; 80 acre contiguous units, each 1/2, 1/4-1/4 sections; 280' FUB; 50 BOPD; and apply to auto. ext. |
80 |
600' |
|
MARS HILL |
66-85 |
Lafayette |
Smackover |
280' FUB |
80 |
1250' |
318-85 |
Lafayette |
Smackover |
Ext. 66-85 to cover 14-T17S-R24W |
|||
248-85 |
Lafayette |
Smackover |
Ext. 66-85 to cover N/2 NE 23-T17S-R24W |
|||
MARYSVILLE |
43-71 |
Union |
Cotton Valley |
330' FUB Gov. 1/4 1/4 sec. |
40 |
500' (5210-6500') 750' (6500-7186') |
MAYTON |
66-67 |
Miller |
Paluxy |
280' FUB N/2 S/2 E/2 W/2 Gov 1/4 1/4 sec |
20 |
160' |
45-68 |
Tuscaloosa |
280' FUB N/2 S/2 E/2 W/2 Gov 1/4 1/4 sec |
20 |
100' |
||
9-71 |
Paluxy |
Unitized |
||||
MCCLENDON BRANCH |
122-91 |
Columbia & Union |
Smackover |
330' FUB; N/2 or S/2 Gov 1/4 Sec |
80 |
750' |
123-91 |
Smackover |
Amend size of D.U. |
160 |
|||
72-92 |
Smackover |
Irregular D.U. Established |
||||
McKAMIE PATTON |
5-41 |
Lafayette |
Smackover |
Within 100' of C. Gov. 1/4 Sec |
160 |
350'; 2nd string 4200' |
21-41 |
Allocation of acreage for allow. |
|||||
33-48 |
Smackover (Reynolds) |
Unitized |
||||
11-50 |
Smackover (Reynolds) |
Unitized |
||||
18-51 |
Smackover |
Amend surface casing |
200' |
|||
3-54 |
Allow. 4,000 bbls/day; outside limits not to exceed 130 bbls./day |
|||||
32-60 |
Smackover |
Enlarging unit |
||||
43-63 |
Smackover |
Enlarging unit |
||||
51-66 |
Smackover |
Enlarging unit |
||||
2-68 |
Smackover |
Enlarging unit |
||||
34-71 |
James |
330' FUB not closer than 100' any well E-W-N-S |
80 |
500' |
||
14-73 |
Gloyd |
330' FUB not closer than 100' any well E-W-N-S |
80 |
300' |
||
24-73A |
Cotton Valley |
330' FUB not closer than 100' any well E-W-N-S |
80 |
750' |
||
24-73B |
Comm. |
|||||
2-75 |
Lafayette |
James |
Amend 34-71 to cover 30-T17S-R23W |
|||
24-75 |
Lafayette |
James |
Amend 34-71 to cover S/2 SW/4 Sec. 19-T17S-R23W; S/2 SE/4 Sec. 24 & N/2 NE/4 Sec. 25-T17S-R24W |
|||
39-75 |
James |
Amend 34-71 to cover N/2 N/2 NE/4 Sec. 30 & S/2 S/2 SE/4 Sec. 19-T17S-R23W |
||||
51-75 |
Lafayette |
James |
Amend 34-71 to cover 6 units: N/2 NW/4, S/2 NW/4, N/2 SW/4, S/2 N/2 NE/4 & N/2 S/2 NE/4, S/2 S/2 NE/4 & N/2 N/2 SE/4, S/2 N/2 SE/4 & N/2 S/2 SE/4 Sec. 19-T17S-R23W |
80 ea. |
||
69-76 |
Lafayette |
James |
Amend 34-71 to cover SW NW 30-T17S-R23W & SE NE 25-T17S-R24W |
80 |
||
14-77 |
Cotton Valley |
Ext. 24-73(a) to cover E/2 Sec. 30 & Ne/4 Sec. 31-T17S-R23W; Reduced to 40-ac. Reg. Gov. 1/4 1/4 sec. |
||||
69-78 |
Lafayette |
Cotton Valley |
Amend 24-73(A) to cover NW/4 & N/2 SW/4 Sec. 28, W/2 Sec. 30 & NW/4 Sec. 31-T17S-R23W |
|||
12-79 |
Lafayette |
Gloyd (Rodessa) |
Amend 14-73 to cover N/2 S/2 Sec. 28 & N/2 S/2 Sec. 33-T17S-R23W |
|||
229-82 |
James |
Unitized |
||||
320-85 |
Lafayette |
Smackover |
Amend 5-41 to rescind area in Sec. 31, 32, 33-T17S-R23W & Sec. 4-6-T18S-R23W |
|||
7-98 |
Travis Peak |
330' FUB of gov. 1/4 1/4 sec. |
40 |
500' |
||
114-2000-09 |
Lafayette |
Cotton Valley |
330' FUB, 660' between wells, up to 4 wells per 160 ac. Ut. |
160 |
750' |
|
152-2000-11 |
Lafayette |
Commingle Travis Peak & Cotton Valley |
SW/4 NE/4 SEC 29-17S-23W |
|||
109-2001-06 |
Lafayette |
Amend Surface Casing Req. |
NE/4 SE/4 32-17S-23W |
|||
McKAMIE SOUTH |
139-86 |
Lafayette |
Smackover |
500' FUB of gov. 1/2 sec. |
320 |
1250' |
McKINNEY BAYOU |
203-2009-04 |
Miller |
Paluxy |
280' FUB NW/4, NE/4, SE/4 or SW/4 of Gov. 1/4 1/4 sec. |
10 |
300' |
576-2010-12 |
Miller |
Paluxy |
More than 1 well per unit if in different Paluxy sands. |
|||
McNEIL EAST |
38-83 |
Columbia |
Travis Peak |
280' FUB N/2 E/2 S/2 W/2 Gov. 1/4 1/4 Sec. |
20 |
300' |
MERIWETHER LAKE |
30-76 |
Lafayette |
Tuscaloosa |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
14-83 |
Smackover |
660' FUB of four contiguous Gov. 1/4 1/4 sec in form of square |
160 |
750' |
||
159-84 |
Lafayette |
Smackover |
Ext. 14-83 to cover SW/4 NW/4 & NW/4 SW/4 Sec. 25 & NE/4 SE/4 & SE/4 NE/4 Sec. 26-T15S-R24W |
|||
73-96 |
Tokio |
280' FUB N/2 S/2 E/2 W/2 of gov. 1/4 1/4 sec. |
20 |
125' |
||
MERIWETHER LAKE SO. |
12-82 |
Lafayette |
Paluxy |
280' FUB E/2 or W/2 Gov. 1/4 1/4 sec. |
20 |
160' (3000-4000') |
MERIWETHER LAKE S.E. |
267-2008-05 |
Lafayette |
Smackover |
330' FUB; all of the E/2 SW/4 NE/4; SE/4 NW/4 NE/4; S/2 NE/4 NE/4; SE/4 NE/4; and NE/4 NE/4 SE/4 of Sec. 35-T15S-R24W; and NW/4 NW/4 SW/4; W/2 SW/4 NW/4; SW/4 NW/4 NW/4 of Sec. 36-T15S-R24W |
140 |
B-15 |
MIDWAY |
5-42 |
Lafayette |
Smackover |
Within 100' of C. of Gov. 1/4 1/4 sec. |
40 |
550' |
1-56 |
Smackover |
Unitized |
||||
042-2015-03 |
Lafayette |
Smackover |
Amend Order No. 1-56 to allow CO2 injection; adopt new U.A. and JOA |
|||
MIDWAY EAST |
57-70 |
Lafayette |
Tuscaloosa |
280' FUB Gov. 1/4 1/4 sec |
20 |
100' |
58-71 |
Tokio |
280' FUB N/2 E/2 S/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
||
39-74 |
Tuscaloosa |
Amend Loc. Prov. N/2 E/2 S/2 W/2 of gov. 1/4 1/4 sec. |
||||
MIDWAY WEST |
26-53 |
Lafayette |
Smackover |
Within 100' of c. of Gov. 1/4 1/4 sec. |
40 |
700' |
5-61 |
Smackover |
Unitized |
||||
84-86 |
Paluxy |
330' FUB of Gov 1/4 1/4 sec. |
40 |
B-15 |
||
MILL CREEK |
076-1-2017-07 |
Nevada |
Tokio & Tuscaloosa |
Tokio - S/2 NE/4, N/2 SE/4, NE/4 SW/4 Sec 4-T15S-R22W. 660' FUB. 50BOPD Tuscaloosa - S/2 SW/4 NE/4 & N/2 NW/4 SE/4 Sec. 4-T15S-R22W. 280' FUB. Comprised of two 1/2 1/4 1/4 sec arranged to form a square. 30 BOPD |
Tokio = 200. Tuscaloosa = 40 |
B-15. Minimum of 160' |
MILLER |
4-39 |
Gloyd Lower |
660' from well or less than 330' FUB |
20 |
800' |
|
MOCCASIN BAYOU |
251-2009-04 |
Miller |
Paluxy |
280' FUB E/2 & W/2 or N/2 & S/2 of a gov 1/4 1/4 sec arranged to create a square. |
40 |
500' |
MOHAWK |
47-73 |
Columbia |
Smackover |
660' FUB. E/2 W/2 of Gov Sec. |
320 |
1250' |
15-74 |
Columbia |
Smackover |
Ext. to cover W/2 28-T19S-R20W |
320 |
||
30-74 |
Smackover |
Ext. to cover NE/4 Sec. 28, S/2 Sec. 21, SW/4 Sec. 22 N/2 Sec. 27-19S-20W. 660' FUB of Gov. 1/4 Sec. |
160 |
|||
52-75 |
Columbia |
Smackover |
Amend to cover SE/4 Sec. 22-T19S-R20W |
|||
17-78 |
Columbia |
Smackover |
Ext. to cover NW/4, NE/4, SW/4 & SE/4 26-T19S-R20W |
|||
65-93 |
Columbia |
Smackover |
Amend to delete SW/4 Sec. 28 & SE/4 SW/4 Sec. 29-T19S-R20W |
|||
279-1-2012-12 |
Columbia |
Smackover |
Ext. to cover N/2 SE/4 Sec. 27-T19S-R20W. Create exceptional D.U. consisting of S/2 NE/4 & N/2 SE/4 Sec. 27-T19S-R20W |
80 |
||
001-1-2015-01 |
Columbia |
Smackover |
Ext. to cover N/2 SE/4 Sec. 27-T19S-R20W. Create exceptional D.U. consisting of S/2 NE/4 & N/2 SE/4 Sec. 27-T19S-R20W |
80 |
||
MORTON |
244-2014-08 |
Lafayette |
Kilpatrick Limestong |
Fract. NE/4 NW/4; fract. NW/4 NE/4; SE/4 NW/4; & SW/4 NE/4 Sec. 3-T16S-R24W. No auto ext. 280'FUB. 50 BOPD |
124.02 |
B-15 |
MT. HOLLY |
2-42 |
Union |
Smackover |
100' from center of gov. sec. |
40 |
100' |
69-67 |
Smackover |
Amend Surface Casing |
750' |
|||
173-80 |
Smackover |
Amend Loc. Prov. 280' FUB |
||||
MT. HOLLY EAST |
99-82 |
Union |
Travis Peak |
280' FUB Gov. 1/4 1/4 sec. |
40 |
300' |
MT. HOLLY NORTH |
45-67 |
Union |
Travis Peak |
330' FUB Gov. 1/4 1/4 sec. |
40 |
300' |
172-81 |
Smackover |
280' FUB |
120 |
750' |
||
32-66 |
Allowable increase |
|||||
MT. VERNON |
21-76 |
Columbia |
Smackover |
660' FUB Gov. 1/4 sec. |
160 |
1000' |
62-76 |
Columbia |
Smackover |
Ext. to cover NE/4 Sec. 30-T16S-R22W |
160 |
||
6-77 |
Lafayette & Columbia |
Smackover |
Ext. to cover NW/4 Sec. 30-T16S-R22W |
160 |
||
38-77 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 25-T16S-R22W & N/2 Sec. 30-T16S R21W |
- |
||
55-77 |
Lafayette |
Smackover |
Ext. to cover NE/4 & NW/4 25-T16S-R23W |
|||
27-81 |
Columbia |
Smackover |
Ext. to cover SW/4 19-T16S-R21W |
|||
50-81 |
Lafayette |
Smackover |
Ext. to cover S/2 SW/4 Sec. 24-T16S-R23W & Dissolve NW/4 Sec. 25-T16S-R23W in Ord. 55-77 |
|||
MT. WILLIE ROAD |
152(C)-2006-06 |
Union |
Tuscaloosa |
280' FUB; NE/4 SW/4 & NW/4 SW/4 of Sec. 24-T18S-R17 and any auto ext; 50 BOPD |
40 |
160' |
151-2011-05 |
Union |
Hill Sand |
Amend to include Hill Sand Formation, 50 BOPD |
40 |
||
NEW LONDON |
21-42 |
Union |
Frost-Cotton Valley |
100' from center of 40 acre unit |
40 |
600' |
7-79 |
Cotton Valley |
280' FUB of gov. 1/4 sec. |
||||
57-89 |
Union |
Cotton Valley |
Unitized |
|||
NICK SPRINGS |
36-40 |
Union |
Travis Peak |
330' FUB & 660' from any other well |
10 |
300' |
19-62 |
Travis Peak |
Amend Surface Casing |
160' |
|||
NICK SPRINGS EAST |
2-57 |
Union |
Tuscaloosa |
50' of line conn. C. 1/4 1/4 1/4 sec N/2 S/2 E/2 W/2 Gov 1/4 1/4 |
20 |
100' |
88-91 |
Lower Graves Blossom |
See Above See Above |
||||
NICK SPRINGS WEST |
29-50 |
Union |
Meakin |
50' of line conn c. two 1/4 1/4 1/4 N/2 E/2 S/2 W/2 Gov. 1/4 1/4 |
20 |
125' |
19-69 |
Nacatoch |
Ext. to cover E/2 NW/4 SE/4 Sec. 36-17S-18W |
||||
OLIN FOREST |
25-67 |
Union |
Tuscaloosa |
280' FUB N/2 E/2 S/2 W/2 Gov. 1/4 1/4 sec. |
20 |
160' |
50-70 |
Hogg |
280' FUB Gov. 1/4 1/4 sec. |
40 |
300' |
||
OLIN FOREST NORTH |
43-66 |
Union |
James |
280' FUB N/2 E/2 W/2 S/2 Gov. 1/4 1/4 sec. |
20 |
160' |
44-66 |
Hogg |
280' FUB N/2 E/2 W/2 S/2 Gov. 1/4 1/4 sec. |
20 |
160' |
||
52-66 |
Rodessa |
280' FUB N/2 E/2 W/2 S/2 Gov. 1/4 1/4 sec. |
20 |
160' |
||
48-67 |
Travis Peak |
280' FUB N/2 E/2 W/2 S/2 Gov. 1/4 1/4 sec. |
20 |
160' |
||
PACE CITY |
13-47 |
Ouachita |
Glen Rose |
50' of line conn. c. 1/4 1/4 1/4 N/2 E/2 S/2 W/2 Gov. 1/4 1/4 sec |
20 |
100' |
4-48 |
Ouachita |
Glen Rose |
Amend Loc. Prov. Longitudal axis to be N-S or E-W direction |
|||
35-55 |
Comm. as salvage operation |
|||||
84-67 |
Blossom |
280' FUB N/2 E/2 S/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
||
22-76 |
Smackover |
280' FUB of two contiguous Gov. 1/4 1/4 sec having E-W long axis |
80 |
500' |
||
190-85 |
Cotton Valley |
280' FUB of E/2 or W/2 Gov 1/4 1/4 sec |
20 |
300' |
||
12-86 |
Smackover |
E/2 W/2 S/2 or N/2 of Gov 1/4 sec |
80 |
|||
116-1-2012-05 |
Ouachita |
Ext. and create D.U consisting of SE/4 NW/4 & SW/4 NE/4 of Sec. 26-T15S-R18W. |
80 |
|||
194-2012-08 |
Ouachita |
Cotton Valley |
Excl. D.U. - SE/4 NW/4 Sec. 25-T15S-R18W |
40 |
||
PACE CITY EAST |
3-53 |
Ouachita |
Graves |
50' of line conn. C. two 1/4 1/4 1/4 sec N/2 E/2 W/2 S/2 Gov |
20 |
100' |
29-65 |
Graves & Meakin |
Comm. |
||||
13-70 |
Smackover |
200' of line conn c. of two1/4 1/4 sec or any two adj. 1/4 1/4 sec |
80 |
500' |
||
349-1-2007-08 |
Ouachita |
Smackover |
Ext. to cover NE/4 & NW/4 29-T15S-R17W & Created 80 acre unit |
80 |
||
569-1-2008-12 |
Ouachita |
Smackover |
Ext. to cover NE/4 & NW/4 29-T15S-R17W & Created 80 acre unit |
80 |
||
279-2010-04 |
Ouachita |
Smackover |
Ext. to cover N/2 of the NE/4 of Sec. 26-15S-18W & Created two exceptional 40 acre units |
40 |
||
182-1-2011-07 |
Ouachita |
Smackover |
Ext. to cover NE/4 NW/4 Sec. 29-T15S-R17W & Created 80 Acre Unit comprised of NW/4 NE/4 Sec. 29, and NE/4 NW/4 Sec. 29-T15S-R17W. |
80 |
||
047-2012-03 |
Ouachita |
Smackover |
Est. of DU. S/2 NE/4 of Sec. 29-T15S-R17 West, |
80 |
||
210-2014-07 |
Ouachita |
Ext. to cover S/2 SW/4 Sec. 21-T15S-R17W |
80 |
|||
PALM |
15-67 |
Lafayette |
Smackover |
280' FUB Gov. 1/4 1/4 sec. |
40 |
750' |
PALM WEST |
191-84 |
Lafayette |
Paluxy |
280' FUB of E/2 W/2 N/2 or S/2 of Gov 1/4 1/4 sec |
20 |
160' |
PATMOS NORTH |
145-82 |
Hempstead |
Tokio |
280' FUB N/2 E/2 S/2 W/2 Gov. 1/4 1/4 sec |
20 |
100' |
PATTON |
29-41 |
Lafayette |
Lime |
Temporary Field Rules - 1320' from well, 660' FUB |
40 |
300' |
5-45 |
Lafayette |
Lime |
Amend Spacing - 100' from center of Gov. |
40 |
||
PAUP SPUR |
56-75 |
Miller |
Smackover |
330' FUB N/2 E/2 S/2 W/2 Gov. 1/4 sec. |
80 |
500' |
26-76 |
Miller |
Smackover |
Ext. to cover E/2 Sec. 32-T14S-R27W |
|||
64-78 |
Pettet |
330' FUB Gov. 1/4 1/4 |
40 |
300' |
||
140-86 |
Travis Peak |
330' FUB of gov. 1/2 1/4 sec. |
||||
226-87 |
Smackover |
Dissolve D.U. (N/2 Sec. 31-14S-27W) |
||||
159-2005-10 |
Smackover |
Amend field rule that 2 wells share 200 BOPD |
||||
122-2013-05 |
Miller |
Smackover |
Unitized |
800 |
||
PIGEON HILL |
55-55 |
Union |
Hosston |
50' of line conn C. two 1/4 1/4 1/4 N/2 S/2 Gov 1/4 1/4 sec |
20 |
300' |
56-55 |
Cotton Valley |
300' of C. Gov 1/4 1/4 sec |
40 |
300' |
||
17-75 |
Hosston (Travis Peak) |
Amend surface casing |
100' |
|||
PILL BRANCH |
157-87 |
Miller |
Jeter |
280' FUB of 2 contigious Gov 1/4 1/4 sec |
80 |
500' |
87-2008-02 |
Miller |
Jeter |
Delete Sec. 35-T19S-R28W |
|||
PINE TREE |
12-49 |
Columbia |
Smackover |
100' from center of gov. 40 acre unit |
40 |
1000' |
64-67 |
Smackover |
Amend Surface Casing |
100' |
|||
172-80 |
Smackover |
Amend Loc. Prov. 280' FUB |
||||
63-85 |
Smackover & Cotton Valley |
Ext to cover N/2 NE/4 Sec. 20 N/2 NW/4 Sec. 21-18S-19W |
||||
51-93 |
Travis Peak |
280' FUB of gov. 1/4 1/4 sec. |
40 |
300' |
||
PISGAH |
57-77 |
Columbia |
Pettet |
100' of C. of NE/4 or 100' of C. SW/4 of E/2 or W/2 Gov. 1/4 sec |
80 |
500' |
63-81 |
Columbia |
Pettet |
Ext. to cover SE/4 Sec. 6, 7 & W/2, W/2 E/2 Sec. 8-T20S-R20W |
|||
106-86 |
Columbia |
Pettet |
Ext. to cover W/2 NW/4 & W/2 SW/4 Sec. 4 N. of Haynesville Field Wide Pettet unit & E/2 SE/4 Sec. 5, N. of Haynesville Field Wide Pettet Unit, T20S-R20W & S/2 SW/4 Sec. 33-T19S-R20W |
|||
130-2002-10 |
Columbia |
Pettet |
Amend Field Rules No drilling closer than 280 feet from any unit boundary |
|||
86-2003-07 |
Columbia |
Pettet |
Amend field rules - add lands that were omitted from 130-2002-10 |
|||
208-2013-08 |
Columbia |
Ext. to cover S/2 S/2 Sec. 33-T19S-R20W. Create Exc. D.U comprised of S/2 S/2 Sec. 33-T19S-R20W |
160 |
|||
213-1-2013 -08 |
Columbia |
Ext. to cover portion of the N/2 NE/4 and NE/4 NW/4 of Sec. 4-T20S-R20W lying N of the Marathon Oil Company-Haynesville Waterflood Unit. Create Exc. D.U comprised of portion of the N/2 NE/4 and NE/4 NW/4 of Sec. 4-T20S-R20W lying N of the Marathon Oil Company- Haynesville Waterflood Unit. |
84.12 |
|||
221-1-2013-09 |
Columbia |
Pettet |
Dissolution of 4 D.U.; E/2 NE/4, W/2 NE/4, E/2 NW/4, W/2 NW/4 Sec. 5-T20S-R20W |
|||
221-2-2013-09 |
Columbia |
Pettet |
Exc. D.U.: S/2 N/2 Sec. 5-T20S-R20W |
160 |
||
221-3-2013-09 |
Columbia |
Pettet |
Exc. D.U.: N/2 of the N/2 Sec. 5-T20S-R20W |
160 |
||
271-1-2014-08 |
Columbia |
Pettet |
Ext. to cover N/2 N/2 & N/2 S/2 N/2 of Sec. 33-T19S-R20W |
|||
271-2-2014-08 |
Columbia |
Pettet |
Exc. D.U.: N/2 N/2, & N/2 S/2 N/2 of Section 33-T19S-R20W. 240 BOPD |
220 |
||
274-1-2014-08 |
Columbia |
Pettet |
Dissolution of two exc. D.U. created by Order Nos. 208-2013-08 and 213-1-2013-08 |
|||
274-2-2014 -08 |
Columbia |
Pettet |
Exc. D.U.: N/2 NE/4, & NE/4 NW/4 of Sec. 4-T20S-R20W lying North of the Marathon Oil Company - Haynesville Water Flood Unit, and S/2 S/2 Sec. 33-T19S-R20W, 240 BOPD |
244.12 |
||
279-1-2014-08 |
Columbia |
Pettet |
Ext. to include N/2 S/2, and the S/2 S/2 N/2 of Sec. 33-T19-R20W |
|||
279-2-2014-08 |
Columbia |
Pettet |
Exc. D.U.: N/2 S/2, and the S/2 S/2 N/2 of Sec. 33-T19-R20W. 240 BOPD |
240 |
||
284-2014-08 |
Columbia |
Pettet |
Three (3) total horizontal wells for the Pettet Limestone Formation within the Order created by 274-2-2014-08 |
244.12 |
||
002-1-2015-01 |
Columbia |
Pettet |
Dissolved certain D.U.s (E/2 NE/4, W/2 NE/4, E/2 NW/4, & W/2 NW/4 Sec. 5-T20S-R20W) |
|||
002-2-2015-01 |
Columbia |
Pettet |
Create exceptional D.U. = S/2 N/2 Sec. 5-T20S-R20W |
160 |
||
002-3-2015-01 |
Columbia |
Pettet |
Create exceptional D.U. = N/2 N/2 Sec. 5-T20S-R20W |
160 |
||
084-1-2017-09 |
Columbia |
Pettet |
Ext to cover NE/4 of Sec 6-T20S-R20W. Create irreg S/2 NE/4 of Sec 6-T20S-R20W & S/2 N/2 of Sec 5-T20S- |
240 |
||
084-2-2017-09 |
R20W. 240 BOPD per 40 acres of lateral perf |
|||||
PLAINFIELD |
3-66 |
Columbia |
Pettet |
610' FUB N/2 E/2 S/2 W/2 Gov 1/4 sec (see order) |
80 |
500' |
126-89 |
Hill |
280' FUB of Gov 1/4 1/4 sec more or less |
40 |
B-15 |
||
54-98 |
Pettet |
Dissolve D.U. (Sec. 36-19S-22W) |
||||
47-2004-05 (Corr.) |
Columbia |
Cotton Valley |
Establish Field-Wide Unit |
|||
PLEASANT GROVE |
60-61 |
Union |
Travis Peak |
50' of line conn c. 1/4 1/4 1/4 sec N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
94-97 |
Travis Peak |
Rescinded Order #60-61 |
||||
PLEASANT VALLEY SO. |
23-91 |
Lafayette |
Gloyd |
330' FUB E/2 or W/2 Gov 1/4 Sec |
80 |
500' |
PRUDHOE BAY SO. |
127-89 |
Lafayette |
Tokio |
280' FUB of Gov 1/4 1/4 sec. |
40 |
100' |
58-90 |
Paluxy |
280' FUB Gov 1/4 1/4 Sec |
40 |
160' |
||
RAINBOW SOUTH |
9-55 |
Union |
Tuscaloosa |
990' FUB |
320 |
|
14-58 |
Tuscaloosa |
50' of line conn C. 1/4 1/4 1/4 sec N/2 E/2 S/2 W/2 Gov 1/4 1/4 sec |
20 |
100' |
||
84-81 |
Union |
Travis Peak |
280' FUB Gov. 1/4 1/4 sec. |
40 |
160' (3000-4000') |
|
153-82 |
Tuscaloosa-Oakes |
280' FUB Gov. 1/4 1/4 sec. |
40 |
160' (3000-4000')' |
||
326-85 |
Cotton Valley |
280' FUB of gov. 1/4 1/4 sec |
40 |
B-15 |
||
RED ROCK |
50-75 |
Columbia |
Pettet |
467' FUB N/2 S/2 E/2 W/2 Gov 1/4 sec. (see order) |
80 |
500' |
188-85 |
Pettet |
Unitized |
||||
090A-2015-07 |
Columbia |
Pettet |
Dissolve and terminate EOR Units created by Order No. 188-85 (and others in other fields) |
|||
RITCHIE |
37-63 |
Union |
Baker |
280' FUB N/2 S/2 E/2 W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
65-68 |
Baker |
Unitized |
||||
ROCKY MOUND SO. |
4-84 |
Lower Hill |
N/2 S/2 E/2 or W/2 Gov 1/4 sec |
80 |
||
8-86 |
Miller |
Hill (Gas) & Lower Hill (Oil) |
Ext. to cover E/2 Sec. 30-T17S-R26W & Ord. 271-83 to cover N/2 SE/4 & NE/4 30-T17S-R26W |
|||
RODESSA |
4-39 |
Miller |
Gloyd |
330' FUB 660' from other wells |
20 |
800' |
16-67 |
Jeter-Rodessa |
200' of C. of SW/4 or NE/4 of 1/4 sec E/2 or W/2 of 1/4 sec. |
80 |
500' |
||
37-88 |
Gloyd |
Unitized |
||||
59-90 |
Pettet |
330' FUB; N/2,S/2,E/2,W/2 Gov 1/4 Sec |
80 |
800' |
||
75-92 |
Gloyd |
Amend; Within 50' of LA State Line inside unitized area. |
||||
30-94 |
Hill |
330' FUB S/2 NE/4 NW/4 & N/2 SE/4 NW/4 Sec. 11 |
||||
88-97 |
Pettet |
Ext. to cover E/2 of Sec. 18-20S-27W (57.25 acres) |
||||
SALEM CHURCH |
18-55 |
Union |
Hosston |
200' of center of reg. Gov. 1/16 sec. |
40 |
100' |
41-64 |
Union |
Travis Peak |
330' FUB N/2 S/2 Gov 1/4 sec |
80 |
300' |
|
9-68 |
Cotton Valley |
330' FUB N/2 S/2 Gov 1/4 |
80 |
400' |
||
SAMS |
335-1-2011-12 |
Miller |
Smackover |
280' FUB. SW/E NE/4 & SE/4 NW/4 Sec. 20-T16S-R28W. No auto ext. 2MMCF allow. (all liquid). 335-2-2011 -12 -Authority to Flare. |
80 |
550' |
SANDY BEND |
33-67 |
Union |
Nacatoch |
Unitized |
||
325-85 |
Travis Peak |
280' FUB of N/2 S/2 E/2 or W/2 of Gov 1/4 1/4 sec |
20 |
160' |
||
SAUL'S CHAPEL |
34-64 |
Union |
Tuscaloosa |
330' FUB Gov. 1/4 1/4 sec |
40 |
100' |
39-68 |
Travis Peak |
330' FUB Gov 1/4 1/4 sec 50' deviation can be granted for Travis Peak |
40 |
300' (4250-5000') |
||
237-85 |
Tuscaloosa & Travis Peak |
Amend location provisions 280' FUB |
||||
SEMINARY CHURCH |
57-71 |
Ouachita |
Tokio |
280' FUB Gov. 1/4 1/4 sec. |
40 |
100' |
7-72 |
Buckrange-Blossom |
280' FUB Gov 1/4 1/4 sec |
40 |
100' |
||
3-74 |
Tokio |
Amend loc. prov. N/2 S/2 E/2 W/2 of gov. 1/4 1/4 sec. Ext to cover W/2 SW/4 SW/4 Sec. 10, W/2 SE/4 SE/4 Sec. 9, E/2 SW/4 SE/4 Sec. 9-15S-19W |
20 |
|||
SHEPPARD BRANCH |
21-96 |
Union |
Hill |
280' FUB; N/2 S/2 E/2 W/2 of gov. 1/4 1/4 sec. |
20 |
180' |
SHILOH |
4-66 |
Lafayette |
Tokio |
280' FUB of gov. 1/4 1/4 1/4 sec. |
10 |
100' |
8-66 |
Tuscaloosa & Paluxy |
280' FUB N/2 S/2 E/2 W/2 Gov 1/4 1/4 sec |
20 |
160' (3000-4000') |
||
36-67 |
Tokio, Tuscaloosa & Paluxy |
Amend Loc. Prov. 280' from mineral div. Line or 450' from production well |
||||
509-2010-09 |
Lafayette |
Smackover Limeston |
280 FUB, Amend to include Smackover Limestone Formation, Ext. to cover E3/4 SE/4 SE/4 of Sec. 35 & SW/4 SW/4 & W1/4 SE/4 SW/4 of Sec. 36-T15S-R23, and auto ext. 100 BOPD |
80 |
B-15 |
|
126-2013-05 |
Lafayette |
Exc. D.U.: E 3/4 SE/4 SW/4, S/4 E 3/4NE/4 SW/4, S/4 NW/4 SE/4,N/2 SW/4 SE/4, N/2 SW/4 SW/4 SE/ 4, S/4 W/2 NE/4 SE/4, and NW/4 NW/4 SE/4 SE/4 of Sec. 36-T15S-R23W |
80 |
|||
SHULER |
10-39 |
Union |
Jones |
330' FUB 600' from any well |
20 |
100' |
6-41 |
Jones |
Unitized |
||||
28-41 |
Union |
Jones |
Unitized Amend |
|||
1-42 |
Union |
Above Jones Sand |
Unitized |
|||
33-52 |
Cotton Valley |
330' FUB |
40 |
800'; 2nd string 2200' |
||
5-55 |
Hill |
330' FUB |
40 |
100' |
||
21-56 |
Jones |
Allocation to Jones Sand - 400' FUB |
||||
3-57 |
Tuscaloosa |
330' from unit bound Gov 1/4 1/4 sec |
40 |
100' |
||
25-73 |
Comm. |
|||||
12-77 |
Jones |
Amend surface casing |
1000' |
|||
139-2001-08 |
Hill Sand Pool |
Amend existing field rules |
||||
030-2018-04 |
Union |
Smackover |
Excpl Unit. SE/4 SW/4 & SW/4 SE/4 Sec 13-T18S-R17W |
80 |
||
013-2019-04 |
Union |
Smackover |
Excpl Unit. SE/4 SW/4 & SW/4 SE/4 Sec 13-T18S-R17W |
80 |
||
SHULER EAST |
19-41 |
Union |
Morgan |
100' from center of gov. 40 acre unit |
40 |
100' |
26-51 |
Smackover & Lower Cotton Valley |
Two well to 1/4 1/4 each at the center of separate 10-A tract |
40 |
800' |
||
18-53 |
Jones Sand |
Unitized |
||||
34-54 |
Morgan |
Amend Loc. Prov. 330' from property or div. Line of gov. 1/4 1/4 sec. |
||||
12-55 |
L.Cotton Valley |
Comm 5600' to top of Jones Sand |
||||
13-55 |
Union |
Lagrone Sand |
Unitized |
|||
075A-2016-08 |
Union |
Jones Sand |
Dissolve and terminate EOR Unit created by Order No. 18-53 |
|||
SLOAN CREEK |
029-2018-04 |
Columbia |
Smackover |
E/2 NE/4 Sec 12-T16S-R19W & W/2 NW/4 Sec 7-T16S-R18W & Extensions. 2 1/2 gov 1/4 sect, roughly in the form of a square. 280' FUB. 60 BOPD. |
160 |
750' B15 |
SHULER EXTENSION |
44-53 |
Union |
Cotton Valley |
300' FUB Gov 1/4 1/4 sec |
40 |
800' |
26-54 |
Union |
Cotton Valley |
Amend Loc. Prov. 330' FUB; Gov. |
40 |
||
29-56 |
Pettet |
330' FUB |
40 |
800' |
||
39-67 |
Pettet |
Amend surface casing |
160' |
|||
SMACKOVER |
||||||
Crabtree area |
35-53 |
Union |
Travis Peak |
50' of C. of 1/4 1/4 1/4 sec |
10 |
100' |
6-54 |
Nacatoch |
Unitized |
||||
Sandyland area |
14-61 |
Travis Peak & Cotton Valley |
50' of line conn C. two 1/4 1/4 1/4 N/2 E/2 S/2 W/2 1/4 1/4 sec. |
20 |
160' |
|
Smackover area |
8-69 |
Nacatoch |
Unitized |
|||
Bilyeu area |
12-69 |
Travis Peak |
280' FUB Gov 1/4 1/4 1/4 sec |
10 |
100' |
|
Smackover area |
22-69 |
Nacatoch |
Unitized |
|||
30-69 |
Nacatoch |
Unitized |
||||
49-70 |
Nacatoch |
Unitized |
||||
Shuler area |
53-70 |
Travis Peak |
280' FUB Gov 1/4 1/4 sec |
40 |
160' |
|
Bollenbacher area |
56-70 |
Travis Peak |
280' FUB N/2 E/2 S/2 W/2 Gov 1/4 1/4 sec |
20 |
160' |
|
058-2018-10 |
Travis Peak |
2 Exceptional Units. Unit 1: SE/4 NW/4 SW/4 & NE/4 SW/4 SW/4 of Sec. 23-T15S-R16W; Unit 2: SW/4 NW/4 SW/4, and the NW/4 SW/4 SW/4 of |
20 |
|||
Smackover |
40-71 |
Meakin |
S 23 T15S R16W Unitized |
|||
5-73 |
Meakin |
Unitized |
||||
Bollenbacher area |
8-79 |
Travis Peak |
Comm. |
|||
Norphlet area |
482-2008-07 |
Union |
Cotton Valley |
280' FUB N/2 S/2 or E/2 W/2 |
20 |
300' |
SMACKOVER |
087-2011-04 |
Ouachita |
Smackover |
280' FUB. Four 1/4 1/4 Sections in shape of square |
160 |
550' |
SMITHVILLE |
12-67 |
Union |
Saulsbury |
280' FUB E/2 or W/2 Gov. 1/4 1/4 sec. |
20 |
100' |
SNOWHILL |
4-56 |
Union |
Travis Peak & Hosston |
280 FUB E/2 or W/2 Gov 1/4 1/4 sec |
20 |
400' |
29-58 |
Cotton Valley |
Comm. |
||||
28-93 |
Travis Peak & Cotton Valley |
Amend Loc. Prov. N/2 S/2 E/2 W/2 of gov 1/4 1/4 sec |
||||
SPIRIT LAKE |
28-46 |
Lafayette |
Temporary Field Rules - 100' from center |
40 |
700' |
|
7-47 |
Lafayette |
Amend surface casing |
700' |
|||
23-47 |
Lafayette |
Kilpatrick |
Amend to 100' of C. of unit |
40 |
700' |
|
23-47 |
Paluxy & Graves |
Amend to 50' of line conn C. two 1/4 1/4 1/4 N/2 S/2 E/2 W/2 1/4 1/4 sec |
20 |
300' |
||
57-66 |
Paluxy, Kilpatrick & Graves |
Amend surface casing |
300' |
|||
36-71 |
Paluxy, Kilpatrick & Graves |
Comm. |
||||
66-71 |
Smackover |
280' FUB Gov 1/4 1/4 sec |
40 |
750' |
||
89-78 |
Tuscaloosa |
280' FUB Gov 1/4 1/4 sec |
40 |
160' |
||
72-79 |
Paluxy 3886-3891' |
280' FUB any two contiguous 20 Acre subdiv. forming a square forming a square |
40 |
300' |
||
131-81 |
Tokio |
280' FUB N/2 or S/2 Gov 1/4 1/4 |
20 |
100' |
||
23-47 |
Paluxy & Graves |
50' of line conn C. two 1/4 1/4 1/4 N/2 S/2 E/2 W/2 1/4 1/4 sec |
20 |
300' |
||
117-82 |
Paluxy & Graves |
Amend Loc. Prov. E/2 W/2 N/2 S/2 of gov. 1/4 1/4 Sec. |
||||
83-88 |
Tuscaloosa |
330' FUB of Gov 1/4 1/4 sec. |
40 |
160' |
||
46-89 |
Tuscaloosa |
330' FUB of Gov 1/4 1/4 sec |
40 |
160' |
||
91-93 |
Smackover |
Amend 66-71 - flaring & 400 MCF allowable |
||||
SPIRIT LAKE NORTH |
107-85 |
Lafayette |
Kilpatrick |
280' FUB of Gov 1/4 1/4 sec |
40 |
160' |
374-85 |
Tokio |
280' FUB of N/2 S/2 E/2 or W/2 of Gov 1/4 1/4 sec |
20 |
150' |
||
118-88 |
Paluxy |
280' FUB of Gov 1/4 1/4 sec. |
40 |
160' |
||
SPOTTSVILLE |
19-87 |
Columbia |
Pettet |
280' FUB of N/2 or S/2 of Gov 1/4 sec. |
80 |
300' |
SPRINGHILL |
11-52 |
Columbia |
Tokio |
50' of C. Gov 1/4 1/4 1/4 sec |
10 |
100' |
17-53 |
Hill |
100' of C. Gov 1/4 1/4 1/4 sec |
40 |
500' |
||
30-53 |
Columbia |
Hill |
Allocation of E. 40 ac. - Frc. SW/4 11-T20S-R23W |
|||
204-87 |
Columbia |
Haynesville |
660' FUB and 330' F State L of the approximate 320 acre Gov sec |
320 |
1500' |
|
11-89 |
Columbia |
Haynesville |
Ext. 204-87 to cover E 3/4 Frc. Sec. 9, W 3/4 Frc. Sec. 10 & W/2 & E/2 Frc. Sec. 11, W/2 W/2 Frc. Sec. 12-T20S-R22W |
|||
128-89 |
Haynesville |
Ext. to cover S/2 Sec. 1 S/2 Sec. 2-20S-22W |
||||
82-90 |
Haynesville |
Ext to cover Frac. Sec. Sec 7-20S-21W |
||||
53-92 |
Haynesville |
Ext. to cover S/2 Sec. 2-20S-22W & Frac. Sec. 7-20S-21W |
||||
84-92 |
Columbia |
Haynesville |
Amend 204-87 - Classify as "Tight Formation" |
|||
86-92 |
Columbia |
Smackover |
Amend 18-69 & 204-87 to delete S/2 Sec. 1 & S/2 Sec. 2-T20S-R22W & all Frc. Sec. 7-T20S-R21W & include S/2 Sec. 1-T20S-R22W & Commingle |
|||
66-95 |
Columbia |
Haynesville |
Amend 204-87 - Gas Allow. |
|||
17-97 |
Haynesville |
Amend Loc. Prov. 1200' from existing wells |
||||
100-97 |
Haynesville |
Ext to cover E/2 Sec. 11 W/4 Sec 12-20S-23W |
||||
11-98 |
Columbia |
Haynesville |
Ext. 204-87 to cover 11-T20S-R23W |
|||
9-2000-02 |
Haynesville |
S/2 4-20S-22W Three well allowables |
||||
52(B)-2000-04 |
Lafayette |
Haynesville |
204-87 to cover Frc. E/2 Sec. 8; W/4 & E. 3/4 Sec. 9; Frc. W3/4 Sec. 10-T20S-R23W; Allow. & well spacing of Ord. 66-95 & 11-98 |
|||
81-2001-05 |
Haynesville |
Amend Field Rules |
||||
95-2002-07 |
Pettit |
Amend field rules 2, 3, 9 AND 12-20S-24W |
111-160 |
900 |
||
54-2003-05 |
Pettet |
Amend field rules . See Notice for locations |
||||
102-2004-08 |
Lafayette |
Pettet |
Unitized |
|||
ST. JONAH CHURCH |
7-87 |
Lafayette |
Smackover |
280' FUB and 2640' from existing unit well |
320 |
B-15 |
ST. MARY |
30-80 |
Lafayette |
Hill |
330' FUB |
80 |
500' |
122-81 |
Lafayette |
Hill |
Ext. 30-80 to cover E/2 Sec. 9, W/2 NW/4 & SW/4 Sec. 10-T19S-R25W |
|||
82-88 |
Hill |
Unitized |
||||
ST. MARY WEST |
142-84 |
Lafayette |
Smackover |
330' FUB of N/2 S/2 E/2 or W/2 Gov sec |
320 |
1500' |
143-84 |
Lafayette |
Cotton Valley |
330' FUB of N/2 S/2 E/2 or W/2 Gov sec |
80 |
1250' |
|
82-2002-06 Corr. |
Lafayette |
Cotton Valley |
Establish Field-Wide Unit |
|||
ST. MATTHEWS |
66-81 |
Columbia |
Smackover |
330' FUB Gov 1/4 sec |
160 |
750' |
STAMPS |
9-54 |
Lafayette |
Tokio |
50' of C. Gov 1/4 1/4 1/4 sec |
10 |
100' |
21A-55 |
Tokio |
50' of C. Gov 1/4 1/4 1/4 sec. |
10 |
100' |
||
45-55 |
Tokio |
50' of line conn C 1/4 1/4 1/4 E/2 or W/2 Gov 1/4 1/4 |
20 |
100' |
||
46-55 |
Tuscaloosa |
50' of line conn C 1/4 1/4 1/4 E/2 or W/2 Gov 1/4 1/4 |
20 |
100' |
||
41-56 |
Rodessa |
330' FUB Gov 1/4 1/4 sec |
40 |
150' |
||
42-56 |
Mooringsport |
Within the boundary of the rectangle formed by conn. C of gov. 1/4 1/4 1/4 sec. of D.U. N/2 S/2 E/2 W/2 |
80 |
150' |
||
11-59 |
Paluxy |
50' of line conn C. two 1/4 1/4 1/4 E/2 or W/2 Gov 1/4 1/4 sec |
20 |
100' |
||
59-60 |
Lafayette |
Paluxy |
Ext. 11-59 to cover new zone |
|||
39-69 |
Comm. |
|||||
7-71 |
Comm. |
|||||
4-72 |
Paluxy |
Unitized |
||||
38-75 |
Mooringsport |
Amend Loc. Prov. 280' FUB of gov. 1/4 1/4 sec. & surface casing |
40 |
|||
STAMPS NORTHWEST |
9-58 |
Lafayette |
Tokio |
50' of line conn C. two 1/4 1/4 1/4 N/2 E/2 W/2 S/2 Gov 1/4 1/4 sec |
20 |
100' |
42-64 |
Comm. |
|||||
STATELINE |
47-90 |
Union |
Smackover |
330' FUB of Gov 1/4 sec. |
160 |
B-15 |
56-90 |
Smackover |
Ext. to cover N/2 SE/2 & S/2 NE/4 of Sec. 27-19S-17W |
||||
79-91 |
Smackover |
Ext. to cover NE/4 Sec. 31-19S-16W |
||||
21-93 |
Smackover |
Unit Operation |
||||
STATELINE W |
074-1-2017-07 |
Union |
Smackover |
280' FUB Gov 1/4 sec. 200 BOPD. |
160 |
B-15. Minimum 2000' |
STATELINE SW |
70-95 |
Union |
Smackover |
Acreage in regular gov. 1/4 sec or S/2 of one gov. 1/4 sec. combined w/ N/2 of gov. 1/4 sec. adjoining the South |
160 |
B-15 |
79-96 |
Smackover |
Ext to cover SE/4 Sec 35 SW/4 Sec. 35-19S-17W |
||||
29-2000-03 |
Smackover |
Ext to cover W/2 Frac. Sec. 6-20S-16W (120 acres); E/2 Frac. Sec. 1-20S-16W (126 acres) |
||||
99-2000-08 |
Smackover |
Dissolve: S/2 NW/4 & N/2 SW/4 34-10S-17W & cover Unit #1 SW/4 Sec. 34-19S-17WUnit #2 SE/4 Sec. 33-19S-17WUnit #3 S/2 SE/4 Sec 34-19S-17W & N/2 NE/4 Sec. 3-20S-17W |
160 |
|||
STEPHENS |
30-41 |
Columbia-Nevada-Ouachita |
Travis Peak |
330' FUB or 660' from any well |
10 |
100' |
8-49 |
L. Graves & U Travis Peak |
50' of C of one of the two 1/4 1/4 1/4 sec forming drilling unit E/2 W/2 N/2 S/2 Gov 1/4 1/4 sec |
20 |
60' |
||
15-49 |
Columbia |
Hogg |
50' of C of one of the two 1/4 1/4 1/4 sec forming drilling unit E/2 W/2 N/2 S/2 Gov 1/4 1/4 sec |
20 |
60' |
|
24-49 |
Nevada |
Travis Peak |
50' of line conn c. two 1/4 1/4 1/4 N/2 E/2 S/2 W/2 Gov 1/4 1/4 sec. |
20 |
100' |
|
33-49 |
Nevada |
Travis Peak |
50' of line conn. C. two 10-acre tracts comprising 20 acre D.U. N/2 S/2 E/2 W/2 |
|||
8-50 |
Hogg |
Unitized |
||||
8-60 |
Columbia |
Buckrange |
Unitized |
|||
39-56 |
Smackover |
200' of C. of NE/4 SW/4 of gov 1/4 sec. N/2 S/2 |
80 |
500' |
||
18-62 |
Buckrange |
Unitized |
||||
47-62 |
Buckrange |
Unitized |
||||
7-63 |
Buckrange |
Unitized |
||||
71-65 |
Buckrange |
Unitized |
||||
37-66 |
Columbia |
Buckrange |
Amend 13-66 to cover SE SW Sec. 14-T15S-R20W |
|||
39-66 |
Nacatoch & Buckrange |
280' FUB E/2 or W/2 Gov 1/4 1/4 sec. |
20 |
100' |
||
49-66 |
Buckrange |
Unitized |
||||
10-68 |
L Cretaceous |
Comm |
||||
54-69 |
Buckrange |
Unitized |
||||
59-69 |
Buckrange |
Reaffirm Ord. 54-69 |
||||
6-72 |
Nacatoch |
280' FUB Gov 1/4 1/4 1/4 sec |
10 |
100' |
||
3-73 |
Rodessa |
280' FUB Gov 1/4 1/4 sec |
40 |
|||
4-73 |
Nevada |
James |
Unitized |
40 |
160' |
|
25-74 |
Smackover |
Amend unit size & loc. prov. 330' FUB |
40 |
|||
71-76 |
Pine Island |
"A" sand unitized |
||||
11-80 |
L. Cretaceous |
Comm |
||||
106-81 |
Pettet |
280' FUB Gov 1/4 1/4 sec |
40 |
160' |
||
205-82 |
Columbia |
Pettet |
Ext. 106-81 to cover SW/4 Sec. 25-T15S-R20W |
|||
322-85 |
Smackover & Cotton Valley |
Extend field rules to cover Cotton Valley |
||||
14-89 |
Tokio |
280' FUB of gov 1/4 1/4 1/4 sec. |
10 |
B-15 |
||
79-99 & 80-99 |
Marathon Buckrange Unit I |
Rescind Order No 38-57 (Unitized) |
||||
79-99 & 80-99 |
Marathon Buckrange Unit II |
Rescind Order No 24-63 (Unitized) |
||||
79-99 & 80-99 |
Marathon Buckrange Unit III |
Rescind Order No 72-65 (Unitized) |
||||
79-99 & 80-99 |
Sherry Buckrange Unit |
Rescind Order No 76-65 (Unitized) |
||||
79-99 & 80-99 |
R.E. Williams Buckrange Unit |
Rescind Order No 13-66 (Unitized) Ext. to include S/2 NE/4 NW/4 & N/2 SE/4 NW/4 & S/2 |
||||
236-1-2011-09 |
Ouachita |
Unknown |
NW/4 NE/4 & N/2 SW/4 NE/4 of Sec. 8-T15S-R19W Exc. D.U.: S/2 NE/4 NW/4 & N/2 SE/4 NW/4 & S/2 NW/4 |
|||
236-2-2011-09 |
Unknown |
NE/4 & N/2 SW/4 NE/4 of Sec. 8-T15S-R19W Dissolve and terminate EOR Units created by Order Nos. |
80 |
|||
090A-2015-07 |
Columbia |
Buckrange |
47-62 & 49-66 (and others in other fields) Dissolve and terminate EOR Unit created by Order No. 18- |
|||
092A-2015-07 |
Ouachita |
Buckrange |
62 (and another EOR unit in another field) |
|||
115A-2015-07 |
Ouachita |
Pine Island |
Dissolve and terminate EOR Unit created by Order No. 71- |
|||
117A-2015-07 |
Columbia |
Buckrange |
Dissolve and terminate EOR Unit created by Order No. 8-60 |
|||
STRONG |
100-80 |
Union |
Smackover |
330' FUB N/2 S/2 E/2 W/2 Gov 1/4 sec |
80 |
6240-6500' |
STRONG-NORTH |
38-59 |
Union |
Nacatoch |
500' of C. of Gov 1/4 sec |
160 |
100' |
236-85 |
Cotton Valley |
280' FUB Of E/2 or W/2 Gov 1/4 sec |
80 |
B-15 |
||
TATUM BRANCH |
367-2014-12 |
Lafayette |
Tuscaloosa |
280'FUB = Contiguous portions of governmental 1/4, 1/4 sections in shape of a square. Auto extensions. 40 BOPD / well |
40 |
B-15 |
TEXARKANA |
50-77 |
Pettet |
280' FUB N/2 S/2 E/2 W/2 Gov 1/4 sec |
80 |
300' |
|
135-89 |
Pettet |
280' FUB of any two contiguous/adjacent 1/4 1/4 sec. |
80 |
300 |
||
40-98 |
Miller |
Pettet |
Unitized |
|||
TROY |
14-56 |
Nevada |
Blossom |
50' of line conn C. 1/4 1/4 1/4 sec E/2 or W/2 Gov 1/4 1/4 sec |
20 |
100' |
13-63 |
Blossom |
Unitized |
||||
49-67 |
Nacatoch |
Unitized |
||||
50-67 |
Tokio |
Unitized |
||||
2-74 |
Smackover |
280' FUB N/2 E/2 S/2 W/2 Gov 1/4 1/4 sec |
20 |
300' |
||
184-86 |
Blossom |
Amend 13-63 - Enlarge Unit |
||||
TROY EAST |
24-56 |
Ouachita |
Nacatoch |
150' FUB Gov 1/4 1/4 1/4 sec |
10 |
100' |
7-57 |
Nacatoch |
Amend spacing 100' from perimeter boundary & loc. prov. N/2 S/2 E/2 W/2 gov 1/4 1/4 1/4 sec. & unit size |
5 |
|||
TROY WEST |
110-2006-05 |
Nevada |
Paluxy Sand |
330' FUB |
80 |
160' |
TUBAL |
29-76 |
Union & Columbia |
Smackover |
660' FUB Gov 1/4 sec |
160 |
1250' |
8-77 |
Union |
Smackover |
Ext. to cover S/2 Sec. 26, SE/4 Sec. 34 & 35-T19S-R18W |
|||
48-78 |
Union |
Smackover |
Ext. to cover W/2 & SE/4 36-T19S-R18W |
|||
14-79 |
Union |
Smackover |
Ext. to cover 1-T20S-R18W; 3 units - Gov. 1/4 sec. - N/2 & irreg. unit in 4 frc. Gov. 1/4 1/4 sec. lying bet. S. line of N/2 & AR-LA line; & Allow. reduced to 100 BOPD & irreg. unit by dividing max. DA by 160 x acres; |
|||
49-81 |
Columbia |
Smackover |
Ext. to cover SE/4 NE/4, NW/4 SW/4 Sec. 29-T19S-R18W |
|||
90-81 |
Cotton Valley |
330' FUB E/2 or W/2 Gov. 1/4 sec |
80 |
1000' |
||
197-82 |
Union |
Smackover |
Ext. 29-76 to cover NW/4 Sec. 28-T19S-R18W |
|||
101-87 |
Union |
Smackover |
Amend 14-79 to dissolve ext. 1-T20S-R18W |
|||
URBANA |
39-40 Corr. |
Union |
Crain |
330' FUB 660' from any well |
10 |
120' |
3500' |
46-58 |
Travis Peak |
Unitized |
160' |
||
61-69 |
Travis Peak |
280' FUB N/2 E/2 S/2 W/2 Gov 1/4 1/4 sec |
20 |
160' |
||
54-70 |
Comm. between base of Tokio & top of Cotton Valley |
|||||
33-71 |
Travis Peak |
Ext. to cover Sec. 23-18S-13W |
||||
166-83 |
Union |
Travis Peak |
Ext. 61-69 to cover E/2 NE/4 Sec. 9 & W/2 NW/4 Sec. 10-T18S-R13W |
|||
183-80 |
Union |
Travis Peak |
280' FUB |
40 |
160' (3000'-4000') |
|
570-2008-12 |
Union |
Travis Peak |
Rescinded Unitiation Order #46-58 |
|||
VILLAGE |
13-39 |
Columbia |
Smackover |
660' from property or division line 1320' from any well gov. 1/4 1/4 sec. |
40 |
100' |
38-40 |
Amend 13-39 - Allocating Production |
40 |
||||
6-45 |
Smackover |
Amend spacing - 100' from C gov 40-acre unit |
||||
12-46 |
Amend 13-39 Rule IX - Gas to be Metered |
|||||
27-46 |
Cotton Valley |
100' from C of Gov 1/4 1/4 sec |
40 |
100' |
||
15-47 |
Travis Peak |
100' from C of Gov 1/4 1/4 sec |
40 |
800' |
||
25-48 |
Cotton Valley |
Amend surface casing |
800' |
|||
23-49 |
Lower Pettet |
100' from C of Gov 1/4 1/4 sec |
40 |
800' |
||
12-54 |
Travis Peak |
Comm. of 4200' & 4300' Production |
||||
26-63 |
Smackover & Travis Peak |
Amend 15-47 to cover 9-T17S-R19W to recomplete from Smackover Lime to Travis Peak |
||||
42-68 |
Travis Peak & Cotton Valley |
Comm. |
||||
62-69 |
Smackover |
Amend surface casing |
1350' |
|||
193-84 |
Cotton Valley, Travis Peak, Pettet & Smackover |
280' FUB |
||||
117-91 |
Travis Peak & Cotton Valley |
Comm. |
||||
58-94 |
Travis Peak (Gas) |
280 FUB |
40 |
B-15 |
||
41-98 |
Pettet & Travis Peak |
Comm. |
||||
WALDO |
45-90 |
Columbia |
Smackover |
330' FUB of E/2 & W/2 of adjacent quarter sections |
160 |
750' |
67-93 |
Smackover |
Ext to cover E/2 SE/4 Sec. 5 W/2 SW/4 Sec. 4-16S-21W |
||||
160-2005-10 |
Columbia |
Pettet |
280' FUB |
80 |
300' |
|
269-2008-05 |
Columbia |
Pettet |
Amend & Ext to create exceptional unit. SW/4 SE/4 Sec. 5 & NW/4 NE/4 Sec. 8-16S-21W |
80 |
||
651-1-2009-09 |
Columbia |
Pettet |
Amend & Ext to create exceptional unit. SW/4 NE/4, NE/4 SW/4, SE/4 NW/4, & NW/4 SE/4 of Sec. 5 -16S-21W |
160 |
||
WALKER CREEK |
32-68 |
Columbia |
Smackover |
662' of line conn. C of two1/4 sec S/2 or N/2 of sec |
320 |
2000' |
44-68 |
Lafayette |
Smackover |
Ext. to cover N/2 Sec. 28 & S/2 Sec. 29-T19S-R23W |
|||
11-69 |
Columbia |
Smackover |
Ext. to cover N/2 & S/2 Sec. 27-T19S-R23W |
|||
21-69 |
Columbia & Lafayette |
Smackover |
Ext. to cover S/2 Sec. 15, S/2 Sec. 16, S/2 Sec. 17, S/2 Sec. 19, N/2 Sec. 20, N/2 & S/2 Sec. 22-T19S-R23W |
|||
50-69 |
Ext. to cover S/2 Sec. 23-T19S-R23W |
|||||
66-69 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 23-T19S-R23W |
|||
10-70 |
Ext. to cover N/2 & S/2 Sec. 24-T19S-R23W |
|||||
32-70 |
Columbia |
Smackover |
Ext. to cover S/2 Sec. 13 & S/2 Sec. 14-T19S-R23W |
|||
48-70 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 19-T19S-R22W |
|||
52-70 |
Columbia |
Smackover |
Ext. to cover S/2 Sec. 18-T19S-R22W |
|||
6-71 |
Ext. to cover S/2 Sec. 19-T19S-R22W |
|||||
79-71 |
Ext. to cover N/2 Sec. 20-T19S-R22W |
|||||
28-71 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 29 & N/2 Sec. 30-T19S-R22W |
|||
35-71 |
Columbia |
Smackover |
Ext. to cover S/2 Sec. 17-T19S-R22W |
|||
41-71 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 19, S/2 Sec. 18, N/2 Sec. 14-T19S-R23W & S/2 Sec. 20-T19S-R22W |
|||
42-71 |
Columbia |
Smackover |
Ext. to cover N/2 & S/2 Sec. 21-T19S-R22W |
|||
56-71 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 25-T19S-R23W |
|||
59-71 |
Lafayette |
Smackover |
Ext. to cover N/2 Sec. 15 & N/2 Sec. 18-T19S-R23W |
|||
64-71 |
Lafayette |
Smackover |
Ext. to cover N/2 Sec. 28, S/2 Sec. 30, S/2 Sec. 29-T19S-R22W |
|||
65-71 |
Columbia |
Smackover |
Ext. to cover S/2 Sec. 15, N/2 & S/2 Sec. 22-T19S-R22W |
|||
3-72 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 27-T19S-R22W |
|||
5-72 |
Columbia |
Smackover |
Ext. to cover S/2 Sec. 28-T19S-R22W |
320 |
||
21-72 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 26-T19S-R23W |
320 |
||
29-72 |
Columbia |
Smackover |
Ext. to cover S/2 Sec. 28, N/2 Sec. 33, N/2 Sec. 34-T19S-R23W |
|||
30-72 |
Columbia |
Smackover |
Ext. to cover S/2 Sec. 25 & S/2 Sec. 26-T19S-R23W |
|||
32-73 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 26-T19S-R22W |
|||
33-73 |
Columbia |
Smackover |
Ext. to cover N/2 & S/2 Sec. 25, S/2 Sec. 26-T19S-R22W |
320 |
||
20-74 |
Smackover |
Unitized |
||||
68-88 |
Lafayette |
Smackover |
Rescind S/2 Sec. 25 & N/2 Sec. 36-T19S-R24W & Adopt W/2 & E/2 Sec. 25-T19S-R24W & reform units in Ord. 20- |
|||
73-90 |
Smackover |
Ext. to cover Sec 23 & 26-19S-24W |
||||
99-90 |
Smackover |
Ext. to cover E/2 & W/2 Sec. 25-19S-24W |
||||
62-95 Corr. |
Columbia |
Smackover |
Reform 32-68 to S/2 Sec. 27, less NW SW, T19S-R23W |
|||
42-97 |
Smackover |
Ext to cover W/2 Sec. 25-19S-24W |
||||
WALNUT HILL |
35-57 |
Lafayette |
Mitchell |
200' from center of NW/4 or center of SE/4 E/2 W/2 of gov 1/4 sec. 1467' from any well |
80 |
600' |
47-57 |
Comm. |
|||||
16-75 |
Mitchell |
Amend unit location 330' FUB N/2 E/2 W/2 S/2 1000' from any well |
||||
53-79 |
Mitchell |
Delete NE/4 Sec. 9 & N/2 Sec. 10-T19S-R25W and move to St. Mary Field |
||||
20-90 |
Mitchell |
Unitized |
||||
85-89 |
Lafayette |
Mitchell |
Ext. to cover Sec. 3, SE/4 Sec. 4, NE/4 Sec. 9 & N/2 Sec. 10-T19S-R25W (from St. Mary Field); Sec. 11-T19S-R25W (from Duty Field) & Amend 35-57 to omit location requirement of min. 1000' between wells |
|||
WARE CREEK |
56-80A |
Columbia |
Smackover |
600' FUB any four Gov. 1/4 1/4 sec forming the shape of a square |
160 |
1500' |
154-80 |
Columbia |
Smackover |
Ext. to cover SE/4 & SW/4 & S/2 NW/4 31-T19S-R19W (moved from Chalybeat Springs) |
|||
25-81 |
Columbia |
Smackover |
Ext. to cover S/2 NE/4, SE/4 Sec. 36-T19S-R20W, N/2 NE/4 Sec. 1-T20S-R20W |
|||
79-95 |
Smackover |
Dissolve D.U. (S/2 SE/4 Sec. 31-19S-19W N/2 NE/4 Sec. 6-20S-19W) Ext to cover irregular D.U. N/2 N/2 Sec 6-20S-19W |
||||
492-2009-07 |
Columbia |
Ext. to N/2 NW/4 of Sec. 1-T20S-R20W and S/2 SW/4 of Sec. 36-T19S-R20W. Created 2 drilling units (S/2 SE/4 Sec. 36-T19S-R20W and N/2 NE/4 Sec. 6-T20S-R19W) |
115 |
|||
WARNOCK SPRINGS |
167-82 & 212-82 |
Columbia |
Smackover |
660' FUB of Gov. 1/4 sec |
160 |
750' |
247-82 |
Smackover |
Amend location provisions 330' FUB |
||||
WARNOCK SPRINGS East |
84-90 |
Columbia |
Smackover |
660' FUB; Gov 1/4 Sec |
160 |
750' |
WELCOME |
18-69 |
Columbia |
Smackover |
660' FUB N/2 or S/2 Gov sec |
320 |
2000' |
29-69 |
Smackover |
Ext. to cover N/2 Sec. 4-T20S, R22W |
320 |
|||
41-69 |
Columbia |
Smackover |
Ext. to cover N/2 & S/2 Sec. 34-T19S-R22W; N/2 Sec. 3-T20S-R22W |
|||
52-69 |
Columbia |
Smackover |
Ext. to cover S/2 33-T19S-R22W |
|||
1-70 |
Reclassification of oil reservoir to a gas condensate reservoir |
|||||
35-70 |
Columbia |
Smackover |
Ext. to cover N/2 Sec. 33-T19S-R22W |
|||
22-72 |
Columbia |
Smackover |
Amend 18-69 to provide balancing period for gas production |
|||
3-76 |
Ext. to cover S/2 35-T19S-R22W |
|||||
122-86 |
Columbia |
Smackover |
Delete S/2 31-T19S-R22W & move to Keoun Creek Field |
|||
48-90 |
Cotton Valley |
330' FUB of E/2 NE/4 & W/2 NW/4 or E/2 NW & W/2 NE Sec. 3 & 4-20S-22W |
160 |
B-15 |
||
78-91 |
Columbia |
Smackover |
Ext. to cover S/2 Sec. 2 & S/2 Sec. 3-T20S-R22W |
|||
81-91 |
Smackover |
Extend to cover S/2 Sec 1-20S-22W |
||||
52-92 |
Smackover |
Ext to cover S/2 Sec. 2-20S-22W Sec. 7-20S-21W |
||||
53-98 |
Smackover |
Dissolve D.U. (S/2 Sec. 35-19S-22W) |
||||
567-2008-12 |
Request Denied. |
|||||
039-1-2016-06 |
Columbia |
Smackover |
Dissolve two D.U.s = N/2 Sec. 34-T19S-R22W & S/2 Sec. 34-T19S-R22W |
320 |
||
039-2-2016-06 |
Columbia |
Smackover |
Ext. to cover SE/4 NW/4, S/2 NE/4, E/2 SW/4 & S/4 Sec. 34T19S-R22W; & SW/4 NW/4, W/2 SW/4 Sec. 35T19S-R22W |
|||
039-3-2016-06 |
Columbia |
Smackover |
Create exceptional. D.U. = SE/4 NW/4, S/2 NE/4, E/2 SW/4 & S/4 Sec. 34T19S-R22W; & SW/4 NW/4, W/2 SW/4 Sec. 35T19S-R22W |
480 |
||
071-1-2017-06 |
Columbia |
Smackover |
Ext. to cover SE/4 NW/4, S/2 NE/4, E/2 SW/4 & S/4 Sec. 34T19S-R22W; & SW/4 NW/4, W/2 SW/4 Sec. 35T19S-R22W |
|||
071-2-2017-06 |
Columbia |
Smackover |
Create exceptional. D.U. = SE/4 NW/4, S/2 NE/4, E/2 SW/4 & S/4 Sec. 34T19S-R22W; & SW/4 NW/4, W/2 SW/4 Sec. 35T19S-R22W |
480 |
||
039-1-2018-06 |
Columbia |
Smackover |
Ext. to cover SE/4 NW/4, S/2 NE/4, E/2 SW/4 & S/4 Sec. 34T19S-R22W; & SW/4 NW/4, W/2 SW/4 Sec. 35T19S-R22W |
480 |
||
039-2-2018-06 |
Smackover |
Create exceptional D.U. = SE/4 NW/4, S/2 NE/4, E/2 SW/4 & S/4 Sec. 34T19S-R22W; & SW/4 NW/4, W/2 SW/4 Sec. 35T19S-R22W |
480 |
|||
WESGUM |
11-72 |
Ouachita |
Smackover |
280' FUB - SE SE Sec. 19, S/2 SW/4 & SW/4 SE/4 Sec. 20, NW/4 NE/4 & N/2 NW/4 Sec. 29 & NE/4 NE/4 Sec. 30 -T15S-R18W |
80 |
500' |
10-75 |
Smackover |
Unitized |
||||
62-77 |
Nacatoch |
100' FUB Gov 1/4 1/4 1/4 330' from any well |
10 |
100' |
||
83-86 |
Rodessa |
280' FUB of N/2 S/2 E/2 or W/2 of Gov 1/4 1/4 sec |
20 |
B-15 |
||
18-87 |
Ouachita |
Smackover |
Ext. to cover NE/4 Sec. 29-T15S-R18W less NW NW NE & set allow. |
|||
WESSON |
23-45 |
Ouachita |
Hill & Deeper |
330' from property or division line, 660' from any well, 100' from center of gov 40 acre unit |
40 |
100' |
4-46 |
Travis Peak |
Amend spacing to 50' of line Conn. C. two 1/4 1/4 1/4 sec different horizons & D.U. |
20 |
|||
13-46 |
Hill |
50' from center of gov 10 acre unit |
10 |
|||
13-46 |
James Lime |
100' from center of gov 40 acre unit |
40 |
|||
21-46 |
Hill |
E-W 20 acre unit 50' of line Conn. C of two 1/4 1/4 1/4 sec |
||||
23-46 |
Hill |
50' tolerance C. of Gov. 1/4 1/4 1/4 (Hill zones below Wesson: E-W Gov. 20-ac. on line connecting centers of 1/4 1/4 1/4 Units) |
10 |
|||
23-46 |
Nacatoch |
C of 1/4 1/4 1/4 sec of tolerance of 50' |
10 |
|||
23-46 |
James |
E-W Gov 20-ac. 50' from line Conn. C. Two 1/4 1/4 1/4 |
20 |
|||
30-47 |
Hogg |
50' of C of 1/4 1/4 1/4 sec N/2 S/2 E/2 W/2 |
20 |
|||
33-47 |
Ouachita |
Hogg |
Allocation of Acreage - divide into 2 units: N/2 NW/4 NE/4 & S/2 NW/4 NE/4 Sec. 26-T15S-R19W |
20 |
||
39-47 |
Travis Peak |
N-S or E-W 20 2nd well 50' of C. 1/4 1/4 1/4 sec |
||||
13-48 |
Tokio |
Amend 4-46 to N-S or E-W 20 acre unit |
20 |
|||
15-48 |
Ouachita |
Tokio |
D.U. E/2 NE/4 SW/4; W/2 NE/4 SW/4; E/2 NW/4 SW/4 Sec. 14-T15S-R19W |
20 |
||
21-48 |
Hogg |
Unitized |
||||
36-48 |
Ouachita |
Hogg |
Annex & Unitize |
|||
3-49 |
Ouachita |
Hogg |
Annex & Unitize |
|||
46-66 |
Glen Rose G-12-D |
Unitized |
||||
60-67 |
Smackover |
330' FUB N/2 or S/2 Gov. 1/4 |
80 |
500' |
||
67-67 |
Buckrange |
Unitized |
||||
100-67 |
Blossom & Buckrange Sands between base of Tokio & base of Travis Peak less Hogg & G-12-D Sand of Glen Rose |
Comm. |
||||
8-68 |
Buckrange Blossom |
Unitized |
||||
12-70 |
Smackover |
Unitized |
||||
17-87 |
Ouachita |
Travis Peak (Staggs Area) |
280' FUB of Gov 1/4 sec |
40 |
B-15 |
|
79-99 & 80-99 |
Blossom/Buckrange Unit |
Rescind Order No 8-68 (Unitized) |
||||
91-2002-07 |
Ouachita |
Lower Glen Rose Group |
Amend 23-46 to 280' FUB; NW/4 SE/4 Sec. 14-T15S-R19W productive in Lower Glen Rose Group & Creation of Drilling units; Standup or Laydown rectangular comprised of two 10-ac. Gov. 1/4 1/4 1/4 sec. |
20 |
300' |
|
85-2006-04 |
Ouachita |
Glen Rose |
330' FUB |
40 |
300' |
|
273C-2006-09 |
Ouachita |
Amend field rules - Up to 8 wells in each unit; allowable not to exceed 50 bbls/day |
||||
101-2005-07 |
Ouachita |
Glen Rose |
Dissolution of three 20-acre units in Order 91-2002-07 and extablish 2 40-acre units |
40 |
||
78A-2008-02 |
Ouachita |
Buckrange |
Rescind Order No. 67-67, as amended |
|||
431-1-2008-08 |
Ouachita |
Tokio |
Creation of Exc. D.U. - S/2 S/2 SE/4 SE/4 of Sec. 14-15S-19W & N/2 N/2 NE/4 NE/4 of Sec. 23-T15S-19W |
20 |
||
566-1-2008-12 |
Ouachita |
Travis Peak |
Creation of Exc. D.U. - SW/4 SW/4 of Sec. 13-15S-19W |
40 |
||
517-2010-09 |
Ouachita |
Travis Peak |
Creation of Exc. D.U. - SE/4 SE/4 of Sec. 14-15S-19W |
40 |
||
092A-2015-07 |
Ouachita |
Glen Rose G-12-D |
Dissolve and terminate EOR Unit created by Order No. 46-66 (and another EOR unit in another field) |
|||
WESSON NORTH |
40-66 |
Ouachita |
Nacatoch, Buckrange & Blossom |
280' from unit bound E/2 or W/2 Gov 1/4 1/4 sec |
20 |
100' |
60-68 |
Buckrange Blossom |
Comm. |
||||
7-69 |
Buckrange & Blossom |
Unitized |
||||
074A-2016-08 |
Ouachita |
Buckrange & Blossom |
Dissolve and terminate EOR Unit created by Order No. 7-69 |
|||
WICKHAM CREEK |
24-74 |
Union |
Smackover |
280' FUB any contiguous 1/2 or 1/4 sec N/2 or S/2 1/4 sec |
160 |
750' |
102-91 |
Smackover |
Ext. N/2,NE/4 Sec 5-17S-18W & S/2,SE/4 Sec 32-16S-18W |
||||
WI LDWOOD |
158-87 |
Union |
Travis Peak |
280' FUB of N/2 S/2 E/2 or W/2 of Gov 1/4 1/4 sec |
20 |
B-15 |
WILLISVILLE |
36-55 |
Nevada |
Tokio & Blossom |
50' of line Conn. C. two 1/4 1/4 1/4 E/2 or W/2 Gov 1/4 1/4 sec |
20 |
100' |
51-69 |
Nacatoch |
Unitized |
||||
WILLISVILLE SO WEST |
23-56 |
Nevada |
Nacatoch |
200' from property line or180' from any boundary |
10 |
|
2-71 |
Blossom |
280' FUB N/2 E/2 S/2 W/2 Gov 1/4 1/4 sec |
20 |
100' |
||
29-82 |
Nevada |
Blossom |
Ext. 2-71 to cover N/2 NW/4 NE/4, NE/4 NW/4 Sec. 30; S/2 SE/4 Sec. 19-T14S-R21W |
|||
366-2014-12 |
Nevada |
Smackover |
Unitized |
|||
WILLISVILLE WEST |
43-55(B) |
Nevada |
Tokio |
50' of line C. 1/4 1/4 1/4 E/2 or W/2 Gov 1/4 1/4 sec |
20 |
100' |
43-73 |
Hogg |
280' FUB E/2 or W/2 Gov 1/4 1/4 sec |
20 |
100' |
||
44-75 |
Hogg |
Unitized |
||||
093A-2015-07 |
Nevada |
Hogg |
Dissolve and terminate EOR Unit created by Order No. 44-75 |
|||
WILMINGTON |
37-58 |
Union |
Travis Peak |
50' of C/ N/2 E/2 S/2 W/2 Gov 1/4 1/4 |
20 |
100' |
WINCHESTER |
40-56 |
Union |
Meakin |
50' of line conn C. 1/4 1/4 1/4 N/2 E/2 W/2 S/2 Gov 1/4 1/4 sec |
20 |
100' |
WOODLEY WEST |
6-55 |
Union |
Nacatoch |
330' from property or division line |
40 |
100' |
37-55 |
Nacatoch |
Amend loc. prov. 50' of line Conn. C. two 1/4 1/4 1/4 E/2 W/2 S/2 N/2 Gov 1/4 1/4 sec |
20 |
Please refer to actual Orders for a complete and accurate reading of Field Rules