These rules are adopted pursuant to Subchapter 9 of Chapter 5 of Title 15 of the Arkansas Code Annotated (the act creating the "Construction Assistance Revolving Loan Fund") as amended by Act 459 of 2001 and in accordance with the requirements of the Federal Water Pollution Control Act of 1972 as amended by Public Law 100-4; February 4, 1987. As Contemplated by the Federal Act, the Arkansas General Assembly at its 1987 session enacted Act 1030, which was superseded at its 1991 session by Act 718, Arkansas Code Annotated, Section 15-5-901 to -906, establishing the Construction Assistance Revolving Loan Fund to be administered by the Arkansas Department of Environmental Quality. The Arkansas General Assembly at its 2001 Regular Session enacted Act 459, which converted the administration of the Program and Fund to the Arkansas Soil and Water Conservation Commission effective July 1, 2001.
Due to the very specialized nature and complexity of administration of the fund, the rules, regulations, modes of procedure, Commission policies and guidelines herein provided shall, in all instances, be subject to and given a liberal, reasonable, fair and impartial construction, interpretation and application to the end that the intent and purposes hereof may be obtained in compliance with the laws of the State and the public purposes sought to be served thereby.
The following words and terms, when used in this regulation, shall have the following meanings, unless the context clearly indicates otherwise:
Act - The Federal Water Pollution Control Act, as amended, 33 USC 1251 et.seq.
Administration Fee - A fee charged to the borrower at loan closing. The Administration Fee is used to cover the costs of the program for both The Authority and the Commission. The amount of the Fee will be what is in effect at the time the Memorandum of Agreement is executed by both parties. The Executive Director will be responsible for setting the Administration Fee.
Arkansas Clean Water Revolving Loan Fund Program (CWRLF) - Program created pursuant to Subchapter 9 of Chapter 5 of Title 15 of the Arkansas Code Annotated in accordance with the Federal Water Control Act of 1972 as amended by Public Law 100-4 February 4, 1987.
Authority - the Arkansas Development Finance Authority.
Best Practicable Waste Treatment Technologies (BPWTT) - The cost-effective technology that can treat wastewater, combined sewer overflows and non-excessive infiltration and inflow in publicly owned or individual wastewater facilities. These technologies must meet the applicable provisions of federal and state effluent limitations, groundwater protection or other applicable standards.
Binding commitment - A legal obligation, enforceable under state law, specifying the terms and schedules under which assistance is provided. For the purpose of this program, the Bond Purchase Agreement will normally be used as the Binding Commitment.
Bond - The bond, note, renewal note, refunding bond, interim certificate, certification of indebtedness, debenture, warrant, commercial paper or other obligation or evidence of indebtedness authorized to be issued by the State of Arkansas.
Bond Purchase Agreement - A legal agreement specifying the terms and schedules under which the Commission and Authority will purchase bonds issued by the borrower for financing the cost of construction.
Borrower - A city, town, district, county or public body created and recognized under State law having jurisdiction over transport, treatment and/or disposal of sewage, industrial waste or other waste.
Building - The erection, acquisition, alteration, remodeling, improvement or extension of wastewater facilities.
Capitalization grant - Federal grant assistance awarded to the state for the establishment of the Arkansas Clean Water Revolving Loan Fund Program.
Change order - The documents issued by the borrower, upon recommendation of the consulting engineer and with the approval of the Commission staff. The Change Order authorizes a change, alteration or variance in previously approved engineering plans and specifications for construction. This includes, but is not limited to, additions or deletions of work to be performed pursuant to the contract, a change in the completion time of the contract or a change in costs for work done pursuant to the contract.
Clean Water Act - The Federal Water Pollution Control Act of 1972 ( Public Law 92-500 ) (as amended in 1977 ( Public Law 95-217 ), 1981 ( Public Law 97-117 ) and 1987 ( Public Law 100-4 ). The purpose of the Act is to restore and maintain the chemical, physical and biological integrity of the nation's water.
Collector sewer - The common lateral sewers, within a publicly owned treatment system, which are primarily installed to receive wastewater directly from facilities that convey wastewater from individual systems or from private property.
Commission - The Arkansas Soil and Water Conservation Commission.
Commission staff - The staff of the Arkansas Soil and Water Conservation Commission Water Resources Development Division responsible for administering the Arkansas Clean Water Revolving Loan Fund program under the Supervision of the Executive Director.
Construction - Any one or more of the following:
Consulting engineer - The engineer or engineering firm retained by the borrower to provide professional engineering services during the planning, design and/or construction of a project.
Cost-effectiveness analysis - An analysis done to decide which waste treatment management system or component part will result in the minimum total monetary costs (resources) over time. This analysis is done with consideration given to overriding non-monetary costs needed to meet federal, state and local requirements.
Default - One of several possible events:
Designated management agency, waste treatment management agency - A community/municipality of the state that is designated by the governor and approved by Environmental Protection Agency to receive federal assistance pursuant to Section 208 and Section 303(e) of the Act.
Disadvantaged Community/System - An Arkansas disadvantaged community/system is a Community / System which;
* is below the State's average Medium Household Income (MHI) level (in accordance with the latest U.S. Census Data), or
* the system's user charge ratio is equal to or greater than 1.0%. The user charge ratio is the projected system's average yearly residential water user charge rate* for four thousand gallons of water divided by the system's MHI.
* Note: the projected average yearly residential water user charge rate will include all applicable sewer costs after the project is completed. Sewer costs include all operations, maintenance and replacement (O,M & R) costs, debt service, debt service reserve, required coverage and any other legal obligations / costs.
Note: the executive director may adjust the term, conditions and interest rate for a disadvantaged community / system bond.
Disbursement - Transfer of cash from the Clean Water Revolving Loan Fund to the borrower.
Effluent limitation - Any restriction established by the state or the Environmental Protection Agency administrator on quantities, rates and concentrations of chemical, physical, biological and other constituents that are discarded from a point source into waters of the state.
Eligible cost - Those project costs that the Commission staff shall participate in which are reasonable, necessary and allocable to the project and approved in the loan agreement.
Enforceable requirements of the Act - Those conditions and limitations of permits issued pursuant to the Act, Section 402 and Section 404, which, if violated, could result in issuance of a compliance order or initiation of a civil or criminal action under the Act, Section 309. Where a permit has not been issued, but issuance is anticipated, the term means any requirement that will be in the permit when issued. Where no permit is applicable, the term means any requirement that is necessary to meet applicable criteria for best practicable waste treatment technology.
Environmental determination - A finding by the Commission regarding the potential environmental impacts of a proposed project. This determination would also describe what mitigative measures, if any, the borrower will be required to do as a condition of financial assistance.
Environmental Information Document - A written analysis prepared by the borrower. The document describes the potential environmental impacts of a proposed project. The document must be sufficient in scope to enable the Commission staff to prepare an environmental assessment to allow an environmental determination to be made by the Commission.
Environmental Impact Statement - A disclosure document setting forth impacts on the environment of a proposed course of action. The document will include recommendations to mitigate or minimize any adverse impacts.
Environmental review - The process used to decide whether a proposed project may have significant impacts on the environment and therefore require the preparation of an environmental impact statement. The evaluation is undertaken by the Commission, consistent with the National Environmental Policy Act and other federal, state and local laws and requirements.
Environmental Protection Agency Administrator - The chief officer of the Environmental Protection Agency appointed by the President of the United States.
Executive Director - The executive director of the Arkansas Soil and Water Conservation Commission.
Financing Fee - A fee charged to the borrower used to cover the administrative costs of the program for both the Authority and the Commission. The fee will be charged as part of each repayment the borrower makes to the Authority. The amount of the fee will be what is in effect at the time the Memorandum of Agreement is executed by both parties. The Executive Director will be responsible for setting the Financing Fee. The portion of this fee that the Commission receives is called the Servicing Fee.
Force account - The provision of labor necessary to design or construct the project by the borrower.
Fund - The Construction Assistance Revolving Loan Fund. the Arkansas General Assembly at its 1987 session enacted Act 1030, which was superseded at its 1991 session by Act 718, Arkansas Code Annotated, Section 15-5-901 to -906, establishing the Fund.
Infiltration - Water other than wastewater that enters a sewer system (including sewer service connections and foundation drains) from the ground through such means as defective pipes, pipe joints, connections or manholes. Infiltration does not include, and is distinguished from, inflow.
Inflow - Water other than wastewater that enters a sewer system (including sewer service connections). Inflow can be from sources such as, but not limited to, roof leaders, cellar drains, yard drains, area drains, drains from springs and swampy areas, manhole covers, cross connections between storm sewers and sanitary sewers, catch basins, cooling towers, storm waters, surface runoff, street wash waters or drainage. Inflow does not include, and is distinguished from, infiltration.
Intended Use Plan - A plan identifying the intended uses of the funds available for loans in the Arkansas Clean Water Revolving Loan Fund for each fiscal year as described in Section 606(c) of the Act.
Interceptor sewer - A sewer that is designed for one or more of the following purposes:
Interest Rate - That annual percentage of interest that is in effect at the time the Memorandum of Agreement is executed by both parties. The Executive Director will be responsible for setting the Interest Rate.
Lending Rate - The combination of the Interest Rate and the Financing Fee in effect at the time the Memorandum of Agreement is executed by both parties. The Lending Rate is associated with a specific loan repayment period.
Loan agreement - A contractual arrangement (Bond Purchase Agreement) by and between a borrower and the State acting by and through the Commission and the Authority. The loan agreement sets forth the conditions and obligations for loans to the borrower for paying the eligible costs of construction of wastewater facilities.
Loan Closing - The execution of the loan, the date to be decided by the Commission staff.
Operation and maintenance - Those functions that result in expenditures during the useful life of the wastewater facilities for materials, labor, utilities and other items. The functions must be necessary for managing and maintaining the sewage works to achieve the capacity and performance for which they were designed and constructed.
Planning - Those necessary reports and studies that directly relate to wastewater facilities needed to comply with enforceable requirements of the Act and state statutes. Planning consists of a systematic evaluation of alternatives that are feasible considering the unique demographic, topographic, hydrologic and institutional characteristics of the area. Planning will show the selected alternative is the most cost-effective.
Plans and specifications - The engineering description of the proposed construction project including engineering drawings, maps, technical specifications, design reports and construction contract documents in sufficient detail to allow contractors to bid on the work.
Point source - Any discernible, confined and discrete conveyance from which pollutants are or may be discharged. This would include but not be limited to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, vessel or other floating craft or concentrated animal feeding operation. This term does not include agricultural stormwater discharges and return flows from irrigated agriculture.
Pollution - The discharge, release, escape, deposit or disposition, directly or indirectly, of treated or untreated sewage, industrial wastes or other wastes, of whatever kind or character, in or near any waters of the State. Any discharge in such condition, manner or quantity, which does, will or is likely to contaminate or substantially contribute to the alteration of the physical, chemical or biological properties of any such waters. A discharge will be considered pollution if such contamination or alteration is to such an extent as to make the waters:
Priority List - A list of projects that is used to allocate the funds in the Arkansas Clean Water Revolving Loan Fund account.
Priority System - A system for ranking all entities eligible for funding under the Arkansas Clean Water Revolving Loan Fund program.
Professional Services - Any service provided to the borrower concerning the project. These services include consulting engineers, bond counsel, accounting or bookkeeping, legal, financial, testing or any other service the borrower decides is needed.
Project - The scope of work for which a loan is awarded under the Arkansas Clean Water Revolving Loan Fund.
Project completion - The date operations of the wastewater facilities are initiated or can be initiated, as decided by the Commission staff.
Replacement - Expenditures for obtaining and installing equipment, accessories or appurtenances. Replacement expenditures are necessary to maintain the capacity and performance of the wastewater facilities during their useful life.
Revolving Loan Fund - The Arkansas Clean Water Revolving Loan Fund, created pursuant to the Federal Water Control Act of 1972 as amended by Public Law 100-4 February 4, 1987.
State - The State of Arkansas or any agency or instrumentality thereof.
Sub-agreement - A contractual agreement between a borrower and a contractor.
Submittal Date Penalty - The penalty that may be assessed for not meeting the terms of the Memorandum of Agreement. The Submittal Date Penalty is that in effect at the time the Memorandum of Agreement is executed by both parties. The Executive Director will be responsible for setting the Submittal Date Penalty.
User Charge - A charge levied on users of wastewater facilities for the cost of debt service, operation and maintenance, including replacement. Adequate revenues must be generated to provide the debt service either through the user charge or another dedicated source. All revenues needed for operation and maintenance, including replacement, must come from revenues collected from user charges.
Value engineering - A specialized cost control technique. Value engineering uses a systematic and creative approach to identify and to focus on unnecessarily high cost in a project. The goal is to arrive at a cost saving without sacrificing the reliability or efficiency of the project.
Wastewater - Any water containing sewage, industrial wastes or other wastes or contaminants derived from the prior use of such water. Wastewater shall also include surface water collected by storm sewers.
Wastewater facilities - Any devices and systems that are used in the storage, treatment, recycling and reclamation of waste. In addition, any facilities that are necessary to recycle or reuse water at the most economical cost over the estimated life of the works. These facilities would include:
Water quality management plan - A plan prepared and updated annually by the state and approved by the Environmental Protection Agency. The plan determines the nature, extent and causes of water quality problems in various areas of the state. It also identifies cost-effective and locally acceptable facility and non-point measures to meet and maintain water quality standards.
The 1987 amendments to the Act created and provided federal funding for state water pollution control revolving loan programs. These programs are intended to be perpetual funds providing low interest loan assistance for the construction of wastewater facilities. Through capitalization grants from Environmental Protection Agency and 20% State matching funds, the CWRLF has been established.
Project costs eligible for funding under the CWRLF are determined based on applicable laws and rules and are made on a project-by-project basis. The Commission staff shall make these determinations based on the requirements of Appendix A of this Title XVI.
It is the policy of the CWRLF Program to provide loans with a subsidized interest rate to public entities in the State of Arkansas. The intent is to provide loans with a Lending Rate 1% - 2% less than the current open market municipal bond rate for the same loan repayment period as contemplated on the Borrower's loan.
The Commission staff reserves the right to divide the financing of any construction project into smaller, fundable parts.
Projects will be funded according to the Priority List, the time frames established in the applicable Intended Use Plan and conditions outlined in Title XVI.
Commitments by the Commission to a project will follow this pattern:
There are many other Federal laws and Federal authorities that have applied to traditional construction grants projects, but that are not included among the authorities listed in Section 602(b)(6) of the Act.
These other Federal laws and authorities apply to activities supported with funds "directly made available by" capitalization grants and the State use of such funds in the administration of the program. Appendix B of this regulation contains a list of such Federal laws and authorities.
It is the policy of the CWRLF Program that the majority of projects are constructed through competitive bidding. The CWRLF program will allow force account work on a limited basis. This is done to make financially sound, marketable loans to large communities. Normally, these communities must already use the force account method for the type of work proposed. These communities would likely not use the CWRLF if competitive bidding were required and would use force account whatever the funding source.
General Rules for Force Account Construction
The CWRLF program is funded in part by a capitalization grant from the Environmental Protection Agency. As required by 40 CFR Part 35, Subpart K, State Revolving Fund Program Implementation Regulations dated March 19, 1990, the Commission staff must designate certain projects as equivalency projects. These projects are subject to the equivalency requirements defined in 40 CFR 35, Subpart K and in the Act. Equivalency projects are defined as those Section 212 (of the Act) wastewater treatment projects constructed wholly or in part before October 1, 1994 with funds made "directly available by" the capitalization grant.
Those projects designated as equivalency projects by the Commission staff must comply with Section 602 [b][6] of the Act. Under this Section of the Act, costs such as land for the treatment site (except land application sites), the construction of new collector sewers in existing communities, treatment plant office furnishings and the cost for treating excessive infiltration and inflow into the sewer system will not be eligible for loan funding. For equivalency projects, eligibility determinations shall be according to 40 CFR 35, Subpart I.
All funds within the CWRLF must be used solely to provide loans and other forms of assistance that may be authorized by the Act for the construction of publicly owned wastewater facilities or any other activity associated with water quality. Loans will be made to eligible entities at or below current market interest rates. The borrower is required to establish a dedicated source of revenue for repayment of loans.
Funds within the CWRLF will also be used for the reasonable costs of administering the Fund and conducting activities under Title VI of the Act.
The following categories of work will be allowable for participation in the CWRLF program:
Category |
I |
Secondary Treatment |
Category |
II A & B |
Advanced Treatment |
Category |
III A |
Infiltration/Inflow Correction |
Category |
III B |
Major Rehabilitation |
Category |
IV A |
New Collectors |
Category |
IV B |
New Interceptors |
Funding of new collectors and interceptors will be limited to that necessary to serve residential and commercial facilities in existence at the time of loan closing. Funds will not be provided for service to uninhabited areas.
In the event additional funds become available through deobligations, transfers, additional allotments, etc., the funds will be obligated through the Priority System and the project rankings and the applicable Intended Use Plan.
Facilities with the primary purpose of transporting or treating industrial wastewater will not be eligible for participation in the CWRLF program. The determination of primary purpose will be made by the Commission staff considering such factors as:
Design Capacity Population Projections Industrial Pretreatment Facilities Availability of CWRLF funds Pretreatment Requirements of the Borrower
Certain cities may be required to develop a pretreatment program. The requirements are administered through the NPDES Permit Program. Project costs related to pretreatment requirements will not be eligible for CWRLF program funding.
The Lending Rate for the CWRLF program will be set by the Executive Director. The Lending Rate is made up of the subsidized Interest Rate and the Financing Fee. Either one of these rates may be revised any time using the procedure in Section 16.205. The Lending Rate will be associated with a specific loan repayment period.
The Lending Rate may be modified if the borrower fails to meet a submittal date or the certifiable application date listed in the Memorandum of Agreement. The penalty will be stated in the executed Memorandum of Agreement.
The Interest Rate is the interest rate for the loan. It is combined with the Financing fee to create the Lending Rate of the Bond.
The Financing Fee is a method the Commission staff uses to collect funds to administer the Program. The Financing Fee is a rate that will be added to the Interest Rate to create the Lending Rate for the Bond.
Funds allotted by Title VI shall be available for obligation to the State for one year after the close of the federal fiscal year for which the funds are authorized.
According to Section 604(b) the Executive Director shall reserve some of the state's allotment from each federal fiscal year for planning under Section 205(j) and Section 303(e) of the Act. The reserve for nonpoint source pollution planning is applicable only for funds appropriated under Title II of the Act. Set-asides will be created for all mandatory reserves and state management funds as authorized.
For the purposes of this Rules, there will be three types of revisions:
According to the Act, the Commission shall hold public hearings to consider adoption and approval of the Priority List, Title XVI and amendments thereto when required.
Revisions to the Priority List found non-significant and/or minor revisions required for administrative purposes shall be made by approval of the Executive Director without a public hearing.
Revisions will need the approval of the Executive Director. The Commission staff will publish a notice of the change in a paper of statewide circulation.
The Environmental Protection Agency Administrator will conduct or require the State to have an independently conducted financial and compliance audit of the CWRLF program. The audit shall be conducted according to the auditing standards of the General Accounting Office (Standards for Audit of Governmental Organizations, Programs and Functions).
The Commission staff shall submit the Intended Use Plan with an application for the federal capitalization grant to Environmental Protection Agency.
The project Priority List is an ordered listing, prepared according to the Priority System, of projects anticipated to receive loans. All projects eligible for loan assistance must be included on the state's project Priority List. Loan assistance may be provided whatever the rank on the state's project Priority List based on readiness to proceed with construction.
The Commission staff may revise the project Priority List according to provisions in Section 16.205 as necessary to manage the Fund efficiently. The Commission staff shall submit the Priority List to Environmental Protection Agency for approval.
If a community not in the Priority List seeks funding or the factors for a community on the Priority List change, the Priority List will be amended to reflect these changes. The result of these changes will not affect communities that have already submitted a pre-application.
Any amendment to the Priority List made for these reasons will be considered minor and subject to the rules for that type of revision.
All projects will be ranked, and loans will be awarded from the Priority List. In any joint project, the combined entities must have problems in common; or both entities must be contributing to an existing water quality violation.
The project cost estimates shown in the Priority List are updated from information provided by the entities listed. These estimates will be adjusted based upon final eligibility determinations and changes in project situations at the time of the loan closing.
Each fiscal year after congress appropriates and the state receives its allocation of funds for the CWRLF, the Commission staff shall prepare an Intended Use Plan that shall be subjected to public notice. The Intended Use Plan will identify those projects on the Priority List in which loan assistance is to be provided from that year's appropriation. Only projects that anticipate the planning and design will be completed within the next 12 months will be included in the Intended Use Plan.
The Intended Use Plan shall meet the requirements of the Act. The Intended Use Plan will meet Environmental Protection Agency requirements concerning the short and long term goals and objectives of the Fund. The Intended Use Plan will show the criteria and method for the distribution of funds.
The CWRLF has been established to help and encourage communities to construct and/or improve wastewater systems required to improve water quality and public health with low interest financial assistance. Communities requesting assistance shall meet the following requirements.
In the CWRLF program, each borrower will be expected to obtain the services of a consulting engineer, bond counsel and construction contractor(s). All procurement transactions shall be conducted in a way that provides maximum open and free competition.
The borrower may purchase needed equipment and materials directly to avoid the increased costs associated with including such items in a general construction contract. Should the borrower elect to use this method, the following procedures shall apply:
A small purchase is the procurement of materials, supplies and services when the aggregate amount involved in any one transaction does not exceed the minimum amount specified by State law for competitive bidding by first class cities (e.g., ACA § 14-58-303(b) ), irrespective of the type of borrower. The small purchase limitation applies to the aggregate total of an order, including all estimated handling and freight charges, overhead and profit to be paid under the order. In arriving at the aggregate amount involved in any one transaction, all items that should properly be grouped together must be included. Reasonable competition shall be obtained by soliciting at least two quotes for each order.
Contracts for small purchases need not be a bilaterally executed written agreement. Where appropriate, unilateral purchase orders, sales slips, memoranda or oral price quotations and the like may be used to minimize paperwork. Retention in the purchase files of these documents, written quotations received, references to catalogs or printed price lists used will suffice as the record supporting the price paid.
This method may be used only with written approval of the Commission staff. To use this method one of the following must apply:
Potential applicants shall confer with the Commission staff as early in the planning process as practical. During the conference the staff will provide information, advice, instruction and guidance on the scope of work and level of effort needed to ensure that the applicant expeditiously complies with CWRLF Program requirements.
Before entering into a Memorandum of Agreement as described in Section 16.303, the applicant must submit the following documents:
The Commission staff will regulate the number and timing of projects receiving assistance in a given fiscal year through the execution of a Memorandum of Agreement. This will be done to maintain administrative control of the project workload and to assure the integrity of the CWRLF program. The Memorandum of Agreement will be negotiated between the applicant and the Commission staff and will contain submittal dates for various application documents. Submittal dates will include, but not be limited to the submittal date for the engineering report and environmental information document, construction plans and specifications, the loan application and the user charge and sewer use ordinances.
Priority for staff review of application documents will be assigned according to Memorandum of Agreement submittal dates for all projects. Provisions will be included in the Memorandum of Agreement for a revision of interim submittal dates when circumstances warrant such a revision, subject to Commission staff approval. However, such extensions will result in a lower review priority for the project and may result in the loss of funding for a given fiscal year.
The Interest Rate, Finance Fee, Administration Fee and the Submittal Date Penalty will be fixed when the Memorandum of Agreement is executed by both parties. These items will be those fees and rates in effect at that time.
Failure of the applicant to submit documents on the dates specified in the Memorandum of Agreement, the submittal of substantially incomplete or inadequate documents or not having a certifiable application on the date specified may result in the imposition of the Submittal Date Penalty. The Commission staff will then revise the submittal schedule as needed. The Submittal Date Penalty will be stated in the executed Memorandum of Agreement.
All engineering sub-agreements for planning and design that are executed by parties to a Memorandum of Agreement with the Commission staff shall contain a clause addressing the nonperformance or negligence of the consulting engineering firm. This clause shall incorporate the scheduled submittal dates from the Memorandum of Agreement and provide protection to the city for failure of performance by the consulting engineering firm. Sub-agreements shall be submitted to the Commission staff for review and approval of this clause as a condition for the Commission staff executing the Memorandum of Agreement.
The project engineering report shall contain at a minimum the information described below. The applicant shall submit two copies of the engineering report including environmental information for review.
The Commission staff will approve the engineering report after confirming that the appropriate requirements have been met. Part of the confirmation is showing that an environmental determination has been made according to Section 16.305 (relating to the Environmental Review). The applicant has to agree to incorporate all mitigating measures as directed by the Commission staff.
As required by the provisions of Section 602(b)(6) of the Act, the Commission staff will conduct an environmental review of the project proposed for funding from the CWRLF program. This review will be consistent with the National Environmental Policy Act and the Environmental Review Process for Arkansas CWRLF Projects.
As early as practical the applicant shall obtain a determination from the Commission staff as to the required scope of the environmental review and the information that must be furnished for a particular project.
Temporary loans to provide applicants funding for planning and design costs may be provided if funds are available. The Commission staff reserves the right to refuse issuance of a planning and design loan based on the applicant's financial capability and the availability of funds.
These loans, if available, are secured by a revenue bond with repayment within five years of issuance should the applicant not continue in the CWRLF program. Should the applicant continue through construction in the CWRLF program, this loan will be paid off by the construction loan at loan closing. A financing fee will be charged according to Section 16.503 and the applicant must show adequate financial capability to repay the planning and design loan.
An application shall be filed with the Commission staff that contains the following information:
General information such as the names, titles, addresses and phone numbers for the signatory authority of each participating political subdivision, the engineering consultant or consultants, the legal counsel/city attorney, the applicant's bond counsel, the applicant's independent auditor and the wastewater superintendent and his license class shall be provided on each application.
Before enactment, the applicant shall submit a proposed user charge ordinance and rate structure documentation establishing the rates that will be charged for each class of sewer customers. Upon approval of the ordinance, the applicant shall enact the ordinance according to state law. User Charge ordinances must meet the following minimum requirements:
If the applicant is proposing to levy ad valorem taxes to pay debt service, the following information must be furnished:
The applicant shall submit a copy of any actual or proposed intergovernmental contract under which the applicant either will use another system for treatment or will receive wastewater for treatment. Before loan closing, each intergovernmental agreement must be approved by the Commission staff.
The Commission staff shall review the application for funds and present it to the Executive Director or his designee for certification only after the following requirements have been satisfied:
The borrower shall direct its bond counsel to prepare a bond ordinance according to the term sheet provided by the Commission staff. The bond counsel shall assure that the ordinance is enacted according to State law and program requirements.
Sewer Improvement Districts (SID) shall be required to document the legal formation of the district and the enactment of an acceptable tax levying ordinance besides preparing the bond ordinance.
In bonds supported by a sales tax, the borrower will be required to furnish a certified copy of the sales tax ordinance and the election results besides preparing the bond ordinance. The Commission staff shall approve all sales tax election ordinances. This approval must be before scheduling a sales tax election. This is done to assure all program requirements are met.
Upon enactment of the bond ordinance, the applicant will enter into a Bond Purchase Agreement with the Commission staff. The Bond Purchase Agreement shall be prepared by the borrower's bond counsel according to the term sheet provided by the Commission staff. It shall set forth the terms and conditions that the borrower must meet to obtain funding.
Funds will not be committed until the Bond Purchase Agreement is executed. If the applicant has not had a loan closing within six months of executing the Bond Purchase Agreement, the Commission staff may terminate the assistance according to the provisions of the Bond Purchase Agreement. The Commission staff will reallocate the funds committed to the project to other projects. The applicant will be allowed to reapply for CWRLF funds, but will be subject to the rules in effect at the time of re-application.
Upon enactment of the bond ordinance and execution of the Bond Purchase Agreement, the borrower's bond counsel shall arrange a loan closing according to Commission staff requirements. Before loan closing, the borrower shall submit for approval an initial disbursement request to the Commission staff for payment at loan closing.
Normally, the loan is not closed until the Commission staff has certified the application as complete according to the requirements of Section 16.3 et seq. When it is in the best overall interest of the CWRLF program, the Commission staff may execute a Bond Purchase Agreement and close the loan before completion of the application process. Under these circumstances, construction phase funds will not be disbursed until the application has been certified according to the requirements of Section 16.3 et seq.
The applicant agrees that the Commission is not a partner, joint venturer or in any other way a party to the project or the operation of the wastewater system of the applicant. The Commission shall not in any way be liable or responsible for the payment of any claims or cost overruns concerning the project.
The applicant shall provide an estimated disbursement schedule and modify it as necessary throughout the construction period.
The borrower's annual audits must comply with the provisions of the Office of Management and Budget (OMB) Circular A-133, " Audits of States, Local Governments, and Non-Profit Organizations." This is only for those fiscal years in which the Federal financial assistance received from the CWRLF program is equal to or greater than $300,000. CWRLF participants or their independent auditors should contact the Financial Analyst in the Commission staff for the information regarding the Federal financial assistance received.
The borrower must establish and maintain separate sewer system accounts for the term of the loan agreement. This must be done according to the generally accepted accounting principles as determined by the Governmental Accounting Standards Board (GASB). The Federal regulations governing the State CWRLF program require this as specified in 40 CFR 35. The GASB specifies that all Enterprise Funds must use accrual accounting; therefore, governmental fund accounting is not an acceptable type of accounting for the accounting records of a sewer system.
Following project completion, the final loan disbursement and the completion of OMB Circular A-133 audit requirements, the borrower shall have independent annual audits done on the sewer system. These audits must be according to generally accepted accounting principles as determined by GASB for the term of the loan agreement.
All annual audits should be submitted to the Financial Analyst of the Commission staff within 120 days of the end of the borrower's fiscal year.
Borrowers will be required by the Commission staff to perform value engineering if the estimated cost of building the wastewater facilities is $20 million or more. The borrower shall use current Environmental Protection Agency guidance on the scope and performance of the value engineering analysis and the associated value engineering reports shall be submitted to the Commission staff for review and approval. Borrowers may not break up contracts to avoid this provision. The Commission staff may require borrowers to undertake a value engineering review, if it believes this has happened.
The borrower shall prepare plans and specifications for constructing the proposed project and a final engineering design report on all significant elements of the project. These documents shall conform to Recommended Standards for Sewage Works (16 State Standards, latest edition as amended by Commission minute orders). The plans and specifications shall incorporate the accepted recommendations of any value engineering done according to Section 16.401 (relating to Value Engineering). Two copies of the documents shall be submitted to the Commission staff.
Two copies of the initial plans and specifications shall be submitted to the Commission staff. The initial submittal shall be complete enough so that a contractor could develop an estimate of the project cost and will contain at least the following:
Besides the requirements for the initial submittal of plans and specifications, final plans and specifications shall contain the following:
The Commission staff approval of the plans and specifications does not relieve the borrower of any liabilities or responsibilities with respect to the design, construction, operation or performance of the project. The Commission staff will approve the plans and specifications provided the documents:
The borrower may request the disbursement of loan funds by providing necessary documents as appropriate and consistent with this regulation. Disbursements will only be made for costs incurred pursuant to work done on the project as described in the Engineering Report and Plans & Specifications approved by the Commission staff. Disbursements shall be for engineering and other professional services, bond issuance costs, interest and financing fees during construction, costs to administer the project by the borrower, equipment costs, construction costs including material stored on site less retainage and other project specific costs. These costs are subject to an eligibility determination of the Commission staff according to Appendix A.
Provided the borrower meets the provisions of the Bond Purchase Agreement, Bond Ordinance and this Title, disbursements will be made to the borrower under the following conditions:
The Authority shall be reimbursed for program administration costs by fees collected from each borrower. The fees will be assessed according to the Interagency Agreement between the Commission and the Authority.
Each borrower that has gone through loan closing shall be charged an administrative fee that will be used to defray the costs of the Commission staff in administering the program. The fee may be collected in three ways:
The borrower shall furnish to the Commission staff evidence that the treasurer of the borrower has a fidelity bond. The amount of the bond must be at least equal to the amount of funds in his possession at any time with a minimum amount of $25,000.
The borrower shall obtain authorization from the Commission staff before advertising for bids on the project. All addenda to correct errors, to clarify information in the bidding documents or to incorporate the current wage rate determination shall be approved by the Commission staff. The text of the construction contract shall not vary from the text of the contract documents approved by the Commission staff.
The borrower shall be responsible for assuring that every appropriate procedure and incidental legal requirement is observed in advertising for bids and awarding construction contracts. The borrower shall comply with the procurement requirements of Section 16.211.
The borrower shall agree to initiate and complete the construction of the project quickly. The borrower shall request a construction schedule from the contractor. The borrower will monitor the contractor's performance regarding the schedule. The borrower will act to assure construction is completed quickly. Failure to initiate and complete a project by the date specified in the bond purchase agreement may result in the stoppage of loan disbursements.
The borrower shall provide for full time inspection of the project by the consulting engineer or the borrowers engineering staff. This will be done to assure the work is being performed according to the approved plans and specifications, approved change orders and according to sound engineering principles and building practices.
The Commission staff is authorized to conduct engineering and financial inspections of each project financed in whole or in part with CWRLF funds. During normal business hours, construction and financial records of the project shall be made available to Commission staff representatives to assure that all program and contractual requirements are met. The contractor and borrower shall furnish the Commission staff representatives with every reasonable facility for finding out whether the work as performed is according to the requirements and intent of the contract.
The Commission staff shall notify the borrower and the consulting engineer of any observed deficiencies in the completed construction, procedures or materials used in construction, resident inspection, engineering supervision, financial management or any violation of loan program requirements. The Commission staff will require the borrower to take such action as may be necessary to correct any such observed deficiency.
An engineering inspection of the project will be periodically conducted by Commission staff representatives. The inspections will be done to assure that the project is being managed properly, is on schedule and is being constructed according to approved plans, specifications and change orders. Commission staff representatives will also decide if the engineering consultant's estimate of work complete agrees with actual observed construction. The staff will decide if materials and equipment delivered to the site are properly stored and meet contract requirements. The staff will also decide if other program requirements are being met.
Besides normal testing procedures required of the borrower, the Commission staff may require additional tests of building materials or processes. These tests would only become necessary as the result of some problem during the building of the project. All tests will conform to current published American Society of Testing Standards.
Such inspection will not release the contractor from any obligation to do the work according to the requirements of the contract documents. The consulting engineer would also still be responsible for determining compliance with the requirements of the contract documents.
A financial inspection of the project will be periodically conducted by Commission staff representatives. This inspection will include but not be limited to a review of all project files, all documents that substantiate project expenses, project accounting records and records on the revenues and expenses of the sewer system. Inspections shall be of sufficient scope and detail to determine conformance with terms and provisions of the bond purchase agreement and the requirements of this regulation.
Should it become apparent after contract award that changes in the approved plans and/or specifications are necessary or appropriate, a change order including written justification shall be submitted to the Commission staff for approval. A request for change order review must contain sufficient information to enable the Commission staff to review the proposal for reasonableness. This would include a description of the change, drawings, the contractor's proposal and the engineer's cost estimate.
Costs for changes to the approved plans and specifications will not be eligible for loan disbursement unless written approval is provided by the Commission staff. Should there be an immediate danger to life or property or other extenuating circumstances, tentative approval of change orders may be secured from the Commission staff via telephone and confirmed by letter.
Despite the eligibility of a change under Appendix A of this regulation, the amount of the loan cannot be increased. If necessary, the borrower must apply for a second loan to cover cost overruns beyond the initial loan amount.
In the event of contractor insolvency, any agreements that the borrower may enter into with the bonding company must be submitted for Commission staff approval.
The borrower shall prepare an operation and maintenance manual for Commission staff approval for all projects involving the construction or modification of wastewater treatment facilities. For projects involving only collection system work, operation and maintenance manuals shall be prepared and submitted for approval as required by the Commission staff.
One complete set of record drawings shall be furnished by the consulting engineer to the borrower at the completion of construction. One copy of the record drawings shall also be furnished to the Commission staff, if requested.
The borrower shall provide the Commission staff with notification that the project is complete and make a written request to the Commission staff for final inspection. The Commission staff will conduct a final on-site inspection of the project and may perform a review of any financial assistance records.
The Commission staff will not approve the final project inspection until the borrower has obtained Commission staff approval of the final operation and maintenance manual and until record drawings have been furnished to the borrower and the Commission staff as provided in Section 16.606.
The project will not be considered physically complete until the work as defined in the Engineering Report and the Plans & Specifications approved by the Commission staff has been fully done and accepted by the borrower and Commission staff. Following an acceptable final inspection by the Commission staff, the Commission staff will provide written acceptance to the borrower and the final construction disbursement shall be requested. Final acceptance of the project by the borrower will not be made without Commission staff approval.
After the satisfactory completion of the project, the borrower shall be held accountable by the Commission for the continued validity of all representations and assurances made to the Commission staff. Continuing cooperation with the Commission staff is required. To help such cooperation and to enable the Commission staff to protect the state's investment and the public interest, the following provisions shall be observed.
The borrower shall retain the engineering firm responsible for providing engineering services during construction as the prime engineer to provide the services required by the project performance work plan during the first year following initiation of operation.
Within 16 days of the date one year after the initiation of operation of the project, the borrower shall certify to the Commission staff whether the project meets the project performance standards. Project performance standards are defined as the performance and operational requirements of the project. This includes the attainment of permit requirements, performance requirements of the specifications, the quantity of excessive infiltration and inflow proposed to be eliminated and other requirements the project was designed to meet.
Should the borrower be unable to certify that the project meets project performance standards, the borrower shall immediately prepare a corrective action plan report for Commission staff approval that includes a description of the problem and proposed corrective actions. The borrower shall undertake corrective actions to assure that project performance can be affirmatively certified quickly. The borrower shall submit an affirmative certification by the date specified in the corrective action plan.
Repayment to the CWRLF by the borrower shall be according to the terms of the loan agreement. Upon an event of default under the loan, ordinance or resolution of the borrower authorizing the loan, all available remedies allowed by law will be pursued. This would include the provisions of Arkansas Code Annotated 8-16-319 that allows for the borrower's revenue turnback to be used in making repayments.
These rules are adopted under the authority of the Arkansas General Assembly at its 2001 Regular Session enacted Act 459, Arkansas Water and Air Pollution Act (A.C.A. § 8-4-161 et seq.) and according to the requirements of the Omnibus Consolidated Recissions and Appropriations Act of 1996 ( P.L. 164-134 ).
These sections shall govern the Arkansas CWRLF's Hardship Grant program as authorized by A.C.A. § 15-5-901 et seq.
The following words and terms, when used in this Section, shall have the following meanings, unless the context clearly indicates otherwise:
Hardship Criteria - The Hardship Criteria used to determine if a project is eligible for a Hardship Grant is made up of three parts:
Small Rural Community - A public entity of more than one household but no more than 3,000 inhabitants and that is not a remote area within the corporate boundaries of a larger city.
The Omnibus Consolidated Rescissions and Appropriations Act of 1996 ( P.L. 164-134 ), which became law on April 26, 1996, provided $50 million for grants. The grants were designed to be used by small rural communities, which are severely economically disadvantaged. The U.S. Environmental Protection Agency plans for these funds to be administered in concert with existing programs and procedures to the maximum extent possible.
Because of the limited funds available to this program, the State of Arkansas plans to use all of the available funds to provide assistance in planning, design and construction of wastewater collection and/or treatment services. In addition, the State of Arkansas plans to make it a condition of receiving a grant, that the community also must receive a loan from the CWRLF program.
Unless herein expressly stated differently, the intention is that the terms and conditions that are followed in the CWRLF will be applied to the Hardship Grant program. This would include such items as the application process, procurement regulations, planning, design and construction requirement, and environmental review and payment provisions.
In order to eligible to receive a Hardship Grant, the borrower must meet Environmental Protection Agency's Hardship Criteria. In general, the Hardship Grant program is designed to work in conjunction with the CWRLF program. The types of activities that the grant funds can be used for are the same as those allowed in the CWRLF program. For more information on the allowable activities refer to Section 16.201 of this regulation.
As is required by the CWRLF program, the Hardship Grant program is required to prepare an Intended Use Plan that shall be subject to public notice. Since the Hardship Grant program is designed to work in conjunction with the CWRLF program, the Intended Use Plan for each program will be merged into one document. The Intended Use Plan will identify those projects on the Priority List for which grant assistance is to be provided by that year's appropriation. Only those projects in which it is anticipated that planning and design will be completed within the next 12 months will be included in the Intended Use Plan.
The Intended Use Plan shall meet the requirements of the Omnibus Consolidated Rescissions and Appropriations Act. The Intended Use Plan will meet Environmental Protection Agency requirements concerning the short and long term goals and objectives of the Hardship Grant program. The Intended Use Plan will show the criteria and method for the distribution of funds.
It is Arkansas' intent to use these grant funds to provide gap financing for wastewater projects.
That means that a community will be expected to borrow funds from the CWRLF program to the greatest extent possible, based on the economic situation of the community. The Commission staff will look at a wide range of economic indicators, which may include per capita income or unemployment rate, to determine the maximum amount of grant funds the community will be offered. Of the total amount of project funds provided through the Arkansas CWRLF program, no more than 85% shall be grant funds and at least 15% must be in the form of a loan.
These rules are adopted under the authority of the Title VI of the Clean Water Act and 40 CFR Part 35 Subpart K.
These sections shall govern the Arkansas CWRLF's Nonpoint Source program as authorized by A.C.A. § 15-5-901 et seq.
The following words and terms shall have the following meanings, unless the context clearly indicates otherwise:
Nonpoint Source management project - A project to abate either ground or surface water pollution or a project designed to protect the resource from deterioration.
Non-point Source pollution plan - A plan for managing non-point source pollution as described in Section 319 of the Act.
Person - An individual, corporation, firm, association, partnership, limited liability company, trust, or other legal entity or group of entities, including a governmental entity or any agency or political subdivision staff thereof.
In addition to the specific eligible activities identified in Section 16.201(A), funds in the CWRLF may be used to finance nonpoint source management projects. Borrowers for these projects are frequently not local governmental entities, but other types of Persons such as homeowners, small businesses, farmers, growers, dairymen, cooperatives, and non-profit entities. The program is designed to offer these Persons a source of funding for a nonpoint source management project with below market interest rates and a reasonable repayment period. To be eligible for RLF Nonpoint Source funding, a project must be included in an approved Nonpoint Source Management Plan.
The following list provides some examples of the types of projects that are eligible for assistance from the RLF Nonpoint Source program. This list is intended as an illustration and the types of projects funded are not limited to those listed below.
Landfills
The construction of leachate collection and treatment systems, the closing and capping of landfills or the reclamation of old landfills.
Groundwater Remediation from UST
The remediation of groundwater contamination from leaking petroleum storage tanks or other underground storage tanks.
Groundwater Remediation or Protection from Well Field Sites
The remediation or protection of the groundwater from Oil wells or injection wells or other well fields.
On-site Septic Tank Repair or Replacement
The repair or replacement of on-site septic systems to protect groundwater, drinking water supplies and public health.
Stormwater Management Facilities
The purchase of equipment, land and easements, or construction of facilities to collect, store and treat stormwater runoff.
Agricultural and Animal Waste Facilities and Equipment
The construction of facilities to collect and treat waste products and the equipment needed to properly run those facilities.
Brownfield Redevelopment
The remediation or reclamation of a brownfield site to protect and/or restore groundwater.
Initially, the Nonpoint Source Program will provide assistance in the form of a "linked deposit." This form of assistance is based on the idea that local financial institutions will provide low interest loans to eligible borrowers, if the program is linked to the RLF program depositing funds in that financial institution. Loans will be made for the purpose of implementing best management practices for nonpoint source management projects. RLF program funds will be deposited into a non-interest bearing demand deposit account or other deposit account at a below market interest rate. The financial institutions will take full responsibility for the credit evaluation of the borrowers, preparation and execution of loan agreements, disbursement of funds, monitoring and servicing of loans, and take the credit risk of possible repayment problems or actual defaults. Deposits in excess of FDIC or FSLIC insured amounts will be fully collateralized by the financial institutions.
As changes in priorities require additional funding options, the RLF program will add such features as direct loans, providing funds to other state agencies in Arkansas for use in nonpoint source abatement or other types of assistance authorized by federal law and/or EPA regulation.
APPENDIX A DETERMINATION OF ELIGIBLE COSTS
The information in this appendix represents Commission policies and procedures for deciding the eligibility of project costs based on the requirements of this regulation and the Clean Water Act as amended.
This cost information applies to loan assistance awarded from the CWRLF program. Project cost determinations are not limited to the items listed in this appendix. Additional cost determinations based on applicable law and regulations will be made on a project-by-project basis by the Commission staff.
Cost as applied to wastewater treatment is the cost of acquisition and construction; the cost of all land, rights-of-way, property rights, easements, franchise rights and interests required by the Commission staff for such acquisition and construction; the cost of all machinery, furnishings and equipment; all financing fees and interest before and during construction; the cost of all engineering services and all expenses of research and development with respect to wastewater treatment facilities; the cost of all legal services and expenses; the cost of all plans, specifications, surveys and estimates of cost and revenues; all expenses necessary or incident to learning the feasibility or practicability of acquisition or construction of any such project; all administrative expenses and other expenses as may be necessary or incident to the acquisition or construction; and the financing or the placing of any such project in operation.
Those projects designated as equivalency projects by the Commission staff under Section 16.201 must comply with Section 602 [b][6] of the Act. Under this Section of the Act, costs such as land for the treatment site (except land application sites), the construction of new collector sewers in existing communities, treatment plant office furnishings and the cost for treating excessive infiltration and inflow into the sewer system will not be eligible for loan funding. For equivalency projects, eligibility determinations shall be according to 40 CFR 35, Subpart I
Eligible costs related to mitigation include:
Eligible costs for publicly owned alternative collection and treatment systems for residences and small commercial establishments as defined by this regulation include:
Eligible costs include the cost of wastewater facilities adequate to transport and treat non-excessive infiltration/inflow and for sewer system rehabilitation necessary to eliminate excessive infiltration/inflow as determined in a sewer system study.
APPENDIX B
LIST OF FEDERAL LAWS AND AUTHORITIES
Environmental:
- Archeological and Historic Preservation Act; PL 86-523 as amended
- Clean Air Act; PL 84-159 as amended
- Coastal Barrier Resources Act; 16 U.S.C. 3501 et seq.
- Coastal Zone Management Act; PL 92-583, as amended
- Endangered Species Act; Pl 93-205 as amended
- Farmland Protection Policy Act; PL 97-98
- Fish and Wildlife Coordination Act, PL 85-624 as amended
- Floodplain Management, Executive Order 11988 as amended by Executive Order 12148
- National Historic Preservation Act; PL 89-665 as amended
- Protection and Enhancement of the Cultural Environment; Executive Order 11593
- Protection of Wetlands, Executive Order 11990
- Safe Drinking Water Act; Section 1424(e), PL 95-523 as amended
- Wild and Scenic Rivers Act; PL 90-542 as amended
Economic:
- Administration of the Clear Air Act and the Federal Water Pollution Control Act with respect to Federal Contracts, Grants or Loans, Section 306 of the Clean Air Act and Section 508 of the Clean Water Act, including Executive Order 11738
- Brooks - Murkowski Amendment; Section 169, PL 160-202
- Demonstration Cities and Metropolitan Development Act; PL 89-754, as amended
Social Legislation:
- Age Discrimination Act, PL 94-135
- Civil Rights Act of 1964, Title VI, PL 88-352
- Drug-Free Workplace Act, PL 160-690
- Equal Employment Opportunity; Executive Order 11246 as amended
- Prohibition against sex discrimination under the Federal Water Pollution Control Act; Section 13 of PL 92-500
- Rehabilitation Act; PL 93-112 (including Section 504 and Executive Orders 11914 and 11250)
- Women and Minority Business Enterprise; Executive Orders 11625, 12138 and 12432
Miscellaneous Authority:
- Debarment and Suspension; Executive Order 12549
- Uniform Relocation and Real Property Acquisition Policies Act; PL 91-646
APPENDIX C
PRIORITY SYSTEM AND LIST
While not a part of Title XVI, the Priority System and List is appended herein for reference only. The Priority System and List is required under Title VI of the Act. It is used by the Commission to establish priorities for the expenditure of loan funds. Periodic revisions to the Priority System and List will be done according to Environmental Protection Agency requirements and are subject to Environmental Protection Agency approval.