Arkansas Administrative Code
Agency 010 - Department of Labor
Division 14 - Labor Standards Division
Rule 010.14.10-002 - Prevailing Wage Division Administrative Regulations
Current through Register Vol. 49, No. 9, September, 2024
Chapter 1 - GENERAL PROVISIONS
Alterations and additions to nonresidential buildings
Apartment buildings (5 stories and above)
Arenas (enclosed)
Auditoriums
Automobile parking garages
Banks and financial buildings
Barracks
Churches
City halls
Civic centers
Commercial buildings
Court houses
Detention facilities
Dormitories
Farm buildings
Fire stations
Hospitals
Industrial buildings
Institutional buildings
Libraries
Mausoleums
Motels
Museums
Nursing & convalescent facilities
Office buildings
Out-patient clinics
Passenger and freight terminal buildings
Police stations
Power plants
Prefabricated buildings
Remodeling buildings
Renovating buildings
Repairing buildings
Restaurants
Schools
Service stations
Shopping centers
Stores
Student housing
Subway stations
Theaters
Warehouses
Water & Sewage treatment plants (building only)
Antenna towers
Bridges (major bridges designed for commercial navigation) Breakwaters
Caissons (other than building or highway)
Canals
Channels
Channel cut-offs
Chemical complexes or facilities (other than buildings)
Cofferdams
Coke ovens
Dams
Demolition (not incidental to construction)
Dikes
Docks
Drainage projects
Dredging projects
Electrification projects (out-door)
Flood control projects
Industrial incinerators (other than building)
Irrigation projects
Jetties
Kilns
Land drainage (not incidental to other construction)
Land leveling (not incidental to other construction)
Land reclamation
Levees
Locks, waterways
Oil refineries
Parking lots
Pipe lines
Ponds
Pumping stations (prefabricated drop-in units)
Railroad construction
Reservoirs Revetments
Runways
Sewage collection and disposal lines
Sewers (sanitary, storm, etc.)
Shoreline maintenance
Ski tows
Storage tanks
Swimming pools (outdoor)
Subways (other than buildings)
Taxiways
Tipples
Tunnels
Unsheltered piers & wharves
Viaducts (other than highway)
Water mains
Waterway construction
Water supply lines (not incidental to building)
Water and sewage treatment plants (other than buildings)
Wells
Alleys
Excavation and embankment (for road construction)
Fencing (highway)
Grade crossing elimination (overpasses or underpasses)
Guard rails on highway
Highway signs
Highway bridges (overpasses; underpasses; grade separation)
Medians
Resurfacing streets and highways
Roadbeds
Roadways
Shoulders
Stabilizing courses
Storm sewers incidental to road construction
Street paving
Taxiway
Such "highway" construction which does not qualify for the exemption contained in Ark. Code Ann. § 22-9-303(b) and 010.14-200(d)(5) shall be considered "heavy construction. "
Town or Row houses
Apartment buildings (4 stories or less and excluding student housing)
Single family houses
Mobile home developments
Multi-family houses
Chapter 2 - PREDETERMINATION OF WAGE RATES
Chapter 3 - PAYMENT OF PREVAILING WAGE RATES
If the cost on which the deduction is based does not exceed the actual cost to the employer where the equipment is purchased from him and does not include any direct or indirect monetary return to the employer where the equipment is purchased from a third person, and if the deduction is either:
The phrase "fund, plan, or program" is merely intended to recognize the various types of arrangements commonly used to provide fringe benefits through employer contributions.
In interpreting this phrase, the department will be guided by the experience and interpretation of the U.S. Department of Labor in administering the Davis-Bacon Act.
For example, the W construction contractor pays his laborers or mechanics $12.00 in cash under a wage determination which requires a basic hourly rate of $10.00 and a fringe benefit contribution of $2.00 per hour. The contractor pays the $2.00 per hour in cash because he made no payments and incurred no costs for fringe benefits. Overtime compensation in this case would be computed on a regular or basic rate of $10.00 an hour. However, in some cases a question of fact may be presented in ascertaining whether or not a cash payment made to laborers or mechanics is actually in lieu of a fringe benefit or is simply part of their straight time cash payment is not excludable in computing overtime compensation. Consider the examples set forth in paragraphs (a)(2) and (3) of this section.
Chapter 4 - RECORD KEEPING
All records required by Regulation 010.14-210 shall be maintained for a period of three (3) years.
The prevailing wage determination issued for a project shall be posted by the general contractor/construction manager in a prominent and easily accessible place at the work site. Easily accessible shall be a place which is actually accessible to all workers on the site and is commonly used by the workers on site.
The general contractor/construction manager and all subcontractors required to be listed in the bid proposal pursuant to the provisions of the Ark. Code Ann. § 22-9-204 shall complete a Statement of Intent to Pay Prevailing Wages. Such statements shall be filed by the general contractor/construction manager with the department within thirty (30) days of receipt of the official notice to proceed. Such filings shall be on a form approved by the director. The form may be obtained from the department or is contained herein as Appendix C.
Chapter 5 - ADMINISTRATION AND ENFORCEMENT.
If any provision of these regulations or the application thereof to any person or circumstance is held invalid, such invalidity shall not effect other provisions or applications of the regulations which can be given effect without the invalid provision or application, and to this end the provisions of these regulations are declared to be severable.
Appendix A
Determination Request Form
10421 ARKANSAS DEPARTMENT OF LABOR
WEST MARKHAM
LITTLE ROCK, AR 72205
TELEPHONE (501) 682-4536
FAX (501) 682-4508
EMAIL: jill.stacy@arkansas.gov
WEBSITE: www.arkansas.gov/labor/
REQUEST FOR DETERMINATION OF PREVAILING WAGE RATES PLEASE COMPLETE ENTIRE FORM
DATE OF REQUEST:
NAME OF INQUIRER: COMPANY NAME: MAILING ADDRESS:
TELEPHONE NUMBER:
FAX NUMBER:
EMAIL ADDRESS:
U.S. DECISION NO. (if applicable):
TITLE OF PROJECT:
LOCATION OF PROJECT (city & county):
ESTIMATED VALUE OF CONTRACT:
PROJECT FUND SOURCE:
PUBLIC BODY AWARDING CONTRACT:
NAME/ADDRESS/PHONE NUMBER OF CONTACT PERSON WITH PUBLIC BODY:
PROJECTED BID DATE:
JOB CLASSIFICATIONS REQUIRED:
General Building Construction Trades
General Heavy or Utility Construction Trades
Both Building and Heavy Trades (Please call before sending request for both)
BRIEF DESCRIPTION OF WORK TO BE PERFORMED:
Appendix B
Omitted Classification Request Form
ARKANSAS DEPARTMENT OF LABOR
10421 WEST MARKHAM
LITTLE ROCK, AR 72205
(501) 682-4536 OR 682-4599 TELEPHONE (501) 682-4508 FAX
REQUEST FOR DETERMINATION OF PREVAILING WAGE RATES
OMITTED CLASSIFICATIONS
DATE OF REQUEST:
NAME OF INQUIRER:
COMPANY NAME:
MAILING ADDRESS:
TELEPHONE NUMBER/FAX NUMBER:
PREVAILING WAGE DETERMINATION NUMBER:
TITLE OF PROJECT: LOCATION OF PROJECT (city & county):
List all classifications omitted from the initial wage determination & a brief description of the duties performed:
Appendix C
Statement of Intent to Pay Prevailing Wage Form
Appendix D
Prevailing Wage Claim Form